Zeltmann
31-03 20th Ave, Astoria, NY 11105Plant Summary Information
Zeltmann is ranked #13 out of 833 power plants in New York in terms of total annual net electricity generation.
Zeltmann is comprised of 3 generators and generated 866.2 GWh during the 3-month period between October 2024 to January 2025.
Plant Name | Zeltmann |
---|---|
Utility Name | New York Power Authority |
Location | Queens County, NY |
Initial Operation Date | December 2005 |
Last Update | Jan 2025 |
Annual Generation | 3.6 TWh |
Annual Consumption | 28.3 M MMBtu |
Ranked #323 out of 11,979 Power Plants Nationwide | |
Ranked #184 out of 2,255 Natural Gas Power Plants Nationwide | |
Ranked #13 out of 833 New York Power Plants | |
Ranked #7 out of 116 New York Natural Gas Power Plants | |
Fuel Types | Natural Gas : 98.9% Distillate Fuel Oil : 1.1% |
Map of Zeltmann
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Zeltmann.
Monthly Net Generation for Zeltmann
Zeltmann Details
Summary Information | |
---|---|
Plant Name | Zeltmann (56196) |
Plant Address | 31-03 20th Ave, Astoria, NY 11105 |
Utility | New York Power Authority (15296) |
Latitude, Longitude | 40.7889, -73.9069 |
Generation Dates on File | Jan 2006 to Jan 2025 |
Initial Operation Date | December 2005 |
Annual Generation | 3.6 TWh |
Fuel Types | Natural Gas : 98.9% Distillate Fuel Oil : 1.1% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | NPCC |
Balancing Authority | New York Independent System Operator (NYIS) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | East River |
Ash Impoundment | No |
Transmission / Distribution Owner | Consolidated Edison Co-NY Inc (4226) NY |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | CONSOLIDATED EDISON NEW YORK INC |
Natural Gas Storage | Yes |
Liquefied Natural Gas Storage | No |
Generator CA01 Details Operating December 2005
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CC1 |
Ownership | Single Owner |
Duct Burners | No |
Nameplate Capacity | 188 MW |
Nameplate Power Factor | 1 |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2005 |
Combined Heat & Power | No |
---|---|
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas / Distillate Fuel Oil |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator CT01 Details Operating December 2005
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 170 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 238 MW |
Winter Capacity | 270.2 MW |
Minimum Load | 135 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2005 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas / Distillate Fuel Oil |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | No |
---|---|
Net Summer Capacity With Natural Gas | 238 MW |
Net Winter Capacity With Natural Gas | 270.2 MW |
Net Summer Capacity With Oil | 238 MW |
Net Winter Capacity With Oil | 270.2 MW |
Time To Switch From Gas To Oil | 6H |
Time To Switch From Oil To Gas | 6H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Air Permit Limits | Yes |
Generator CT02 Details Operating December 2005
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 170 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 238 MW |
Winter Capacity | 270.2 MW |
Minimum Load | 135 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2005 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas / Distillate Fuel Oil |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | No |
---|---|
Net Summer Capacity With Natural Gas | 238 MW |
Net Winter Capacity With Natural Gas | 270.2 MW |
Net Summer Capacity With Oil | 238 MW |
Net Winter Capacity With Oil | 270.2 MW |
Time To Switch From Gas To Oil | 6H |
Time To Switch From Oil To Gas | 6H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Air Permit Limits | Yes |
Zeltmann Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#174 | Long Ridge Energy Generation | Hannibal, OH | 3.7 TWh |
#175 | Rayburn Energy Station LLC | Sherman, TX | 3.7 TWh |
#176 | Decatur Energy Center | Decatur, AL | 3.7 TWh |
#177 | Klamath Cogeneration Plant | Klamath Falls, OR | 3.7 TWh |
#178 | Middletown Energy Center | Middletown, OH | 3.7 TWh |
#179 | CPV St Charles Energy Center | Waldorf, MD | 3.6 TWh |
#180 | Thomas C Ferguson | Horseshoe Bay, TX | 3.6 TWh |
#181 | Dynegy Moss Landing Power Plant Hybrid | Moss Landing, CA | 3.5 TWh |
#182 | Marshall (NC) | Terrell, NC | 7.8 TWh |
#183 | Harquahala Generating Project | Tonopah, AZ | 3.6 TWh |
#185 | Mesquite Generating Station Block 1 | Arlington, AZ | 3.6 TWh |
#186 | Ontelaunee Energy Center | Reading, PA | 3.6 TWh |
#187 | Harding Street | Indianapolis, IN | 3.5 TWh |
#188 | Northport | Northport, NY | 3.7 TWh |
#189 | Lagoon Creek | Brownsville, TN | 3.5 TWh |
#190 | Arlington Valley Energy Facility | Arlington, AZ | 3.5 TWh |
#191 | Odyssey Energy Altura Cogen, LLC | Channelview, TX | 3.5 TWh |
#192 | Bethlehem Energy Center | Glenmont, NY | 3.5 TWh |
#193 | Rhode Island State Energy Center | Johnston, RI | 3.5 TWh |
#194 | Bridgeport Station | Bridgeport, CT | 3.5 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Zeltmann.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
59th Street | New York, NY | 612.0 MWh | 4.6 mi |
74th Street | New York, NY | 176.0 MWh | 2.7 mi |
Astoria Energy | New York, NY | 4.2 TWh | 0.7 mi |
Astoria Energy II | Astoria, NY | 4.0 TWh | 0.8 mi |
Astoria Gas Turbines | Astoria, NY | 33.5 GWh | 0.2 mi |
Astoria Generating Station | Astoria, NY | 729.8 GWh | 0.3 mi |
Bronx Zoo | New York, NY | 20.4 GWh | 4.1 mi |
Harlem River Yard | Bronx, NY | 92.5 GWh | 0.8 mi |
Hell Gate | Bronx, NY | 99.8 GWh | 0.7 mi |
Hilton NY Co Gen Plant | New York City, NY | 5.3 GWh | 4.2 mi |
MER Queens | Elmhurst, NY | 7.8 GWh | 4.2 mi |
Mount Sinai Hospital | New York, NY | 263.0 MWh | 2.4 mi |
New York Presbyterian Hospital-168th St | New York, NY | 126.0 MWh | 4 mi |
New York University Central Plant | New York, NY | 74.2 GWh | 0.9 mi |
NY - PANYNJ - LaGuardia - Rooftop | Queens, NY | 1.5 GWh | 2 mi |
NY - Presbyt. Hospital - 525 E 68TH St | New York, NY | 48.1 GWh | 3 mi |
NY Times Daily Production Facility | Flushing, NY | 19.0 MWh | 4.1 mi |
NYU LANGONE HEALTH | New York, NY | 42.9 GWh | 4.5 mi |
Ravenswood | Long Island, NY | 2.5 TWh | 2.9 mi |
Vernon Boulevard | Long Island City, NY | 120.4 GWh | 3.3 mi |