Wolf Hollow II
8787 Wolf Hollow Court, Granbury, TX 76048Plant Summary Information
Wolf Hollow II is ranked #43 out of 2,188 natural gas power plants nationwide in terms of total annual net electricity generation.
Wolf Hollow II is comprised of 3 generators and generated 2.5 TWh during the 3-month period between December 2023 to March 2024.
Plant Name | Wolf Hollow II |
---|---|
Utility Name | Constellation Power, Inc |
Location | Hood County, TX |
Initial Operation Date | June 2017 |
Last Update | Mar 2024 |
Annual Generation | 7.7 TWh |
Annual Consumption | 53.0 M MMBtu |
Ranked #122 out of 11,249 Power Plants Nationwide | |
Ranked #43 out of 2,188 Natural Gas Power Plants Nationwide | |
Ranked #12 out of 721 Texas Power Plants | |
Ranked #6 out of 288 Texas Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Previous Operator |
Exelon Power (2014 to 2021) Constellation Power, Inc (2022 to 2022) |
Map of Wolf Hollow II
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Wolf Hollow II.
Monthly Net Generation for Wolf Hollow II
Wolf Hollow II Details
Summary Information | |
---|---|
Plant Name | Wolf Hollow II (59812) |
Plant Address | 8787 Wolf Hollow Court Granbury, TX 76048 |
Utility | Constellation Power, Inc (6035) |
Latitude, Longitude | 32.33768, -97.73461 |
Generation Dates on File | Jun 2017 to Mar 2024 |
Initial Operation Date | June 2017 |
Annual Generation | 7.7 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | 17-19-000 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | NA |
Ash Impoundment | No |
Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
Grid Voltage | 345.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | ENERGY TRANSFER FUEL LP |
Natural Gas Storage | No |
Generator CGT4 Details Operating June 2017
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | BLK2 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | Yes |
RTO ISO LMP Node Designation | WHCCS2_4 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WHCCS2_4 |
Nameplate Capacity | 360 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 327.8 MW |
Winter Capacity | 353.3 MW |
Minimum Load | 113 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | June 2017 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator CGT5 Details Operating June 2017
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | BLK2 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | Yes |
RTO ISO LMP Node Designation | WHCCS2_5_6 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WHCCS2_5_6 |
Nameplate Capacity | 360 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 329.3 MW |
Winter Capacity | 354.6 MW |
Minimum Load | 113 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | June 2017 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator STG6 Details Operating June 2017
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | BLK2 |
Ownership | Single Owner |
Duct Burners | Yes |
RTO ISO LMP Node Designation | WHCCS2_5_6 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WHCCS2_5_6 |
Nameplate Capacity | 511.2 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 458.3 MW |
Winter Capacity | 485.1 MW |
Minimum Load | 60 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | June 2017 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Wolf Hollow II Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#33 | New Covert Generating Facility | Covert, MI | 8.1 TWh |
#34 | Colorado Bend II | Wharton, TX | 8.1 TWh |
#35 | Seminole (FL) | Palatka, FL | 11.1 TWh |
#36 | CPV Fairview Energy Center | Johnstown, PA | 7.9 TWh |
#37 | Panda Temple Power Station | Temple, TX | 7.9 TWh |
#38 | Freestone Energy Center | Fairfield, TX | 7.9 TWh |
#39 | Riviera | Riviera Beach, FL | 7.9 TWh |
#40 | Indeck Niles Energy Center | Niles, MI | 7.8 TWh |
#41 | Jackson Generation, LLC | Elwood, IL | 7.8 TWh |
#42 | Guadalupe Generating Station | Marion, TX | 7.7 TWh |
#44 | Chouteau | Pryor, OK | 7.6 TWh |
#45 | Cape Canaveral | Cocoa, FL | 7.6 TWh |
#46 | Manatee | Parrish, FL | 7.5 TWh |
#47 | Brunswick County Power Station | Freeman, VA | 7.5 TWh |
#48 | Deer Park Energy Center | Deer Park, TX | 7.5 TWh |
#49 | Odessa-Ector Power Plant | Odessa, TX | 7.4 TWh |
#50 | Chuck Lenzie Generating Station | Apex, NV | 7.4 TWh |
#51 | Tenaska Westmoreland Generating Station | Smithton, PA | 7.3 TWh |
#52 | Paradise | Drakesboro, KY | 7.2 TWh |
#53 | Oregon Clean Energy Center | Oregon, OH | 7.1 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Wolf Hollow II.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Arlington Outlet Hydroelectric Generator | Fort Worth, TX | 49.8 MWh | 35.4 mi |
Bosque County Peaking | Laquna Park, TX | 5.2 TWh | 39.7 mi |
Buckthorn Wind | Mingus, TX | 393.4 GWh | 37.6 mi |
Comanche Peak | Glen Rose, TX | 20.5 TWh | 4 mi |
DeCordova Steam Electric Station | Granbury, TX | 68.5 GWh | 4.9 mi |
Johnson County | Cleburne, TX | 1.1 TWh | 19.5 mi |
TPE Erath Solar, LLC | Stephenville, TX | 26.1 GWh | 28.1 mi |
TPE Whitney Solar, LLC | Kopperl, TX | 20.0 GWh | 30 mi |
WAL284 | Mansfield, TX | 289.5 MWh | 38.9 mi |
WAL3284 | Arlington, TX | 247.8 MWh | 38.1 mi |
WAL3631 | Crowley, TX | 340.8 MWh | 28.4 mi |
WAL3773 | Fort Worth, TX | 347.4 MWh | 33 mi |
WAL4509 | Tarrant, TX | 313.4 MWh | 28.2 mi |
WAL940 | Westworth Village, TX | 337.1 MWh | 33.7 mi |
WAL972 | Fort Worth, TX | 49.7 MWh | 37.4 mi |
Walnut Springs Solar | Walnut Springs, TX | 11.8 GWh | 18 mi |
Westside Landfill Gas Recovery | Aledo, TX | 16.3 GWh | 29.1 mi |
Whitney | Clifton, TX | 10.3 GWh | 38.9 mi |
Wolf Hollow I LP | Granbury, TX | 3.4 TWh | 0.3 mi |
Yellow Jacket | Meridian, TX | 11.5 GWh | 28.3 mi |