Wild Horse
25901 Vantage Hwy, Ellensburg, WA 98926Plant Summary Information
Wild Horse is ranked #30 out of 134 power plants in Washington in terms of total annual net electricity generation.
Wild Horse generated 134.6 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | Wild Horse |
---|---|
Utility Name | Puget Sound Energy Inc |
Location | Kittitas County, WA |
Initial Operation Date | December 2006 |
Last Update | Sep 2024 |
Annual Generation | 589.0 GWh |
Annual Consumption | 2.2 M MMBtu |
Ranked #1,113 out of 11,852 Power Plants Nationwide | |
Ranked #260 out of 1,345 Wind Power Plants Nationwide | |
Ranked #30 out of 134 Washington Power Plants | |
Ranked #3 out of 23 Washington Wind Power Plants | |
Fuel Types | Wind : 99.9% |
Map of Wild Horse
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Wild Horse.
Monthly Net Generation for Wild Horse
Wild Horse Details
Summary Information | |
---|---|
Plant Name | Wild Horse (56322) |
Plant Address | 25901 Vantage Hwy, Ellensburg, WA 98926 |
Utility | Puget Sound Energy Inc (15500) |
Latitude, Longitude | 47.03627, -120.20649 |
Generation Dates on File | Dec 2006 to Sep 2024 |
Initial Operation Date | December 2006 |
Annual Generation | 589.0 GWh |
Fuel Types | Wind : 99.9% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | Puget Sound Energy (PSEI) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | N.A. |
Ash Impoundment | No |
Transmission / Distribution Owner | Puget Sound Energy Inc (15500) WA |
Grid Voltage | 230.00 kV |
Energy Storage | No |
Generator 1 Details Operating December 2006
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 228.6 MW |
Summer Capacity | 228.6 MW |
Winter Capacity | 228.6 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2006 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 127 |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 127 |
---|---|
Predominant Turbine Manufacturer | Vestas |
Predominant Turbine Model Number | V80-1.8 |
Design Wind Speed | 18 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 219.8 |
Generator WHS1 Details Operating October 2007
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 0.5 MW |
Summer Capacity | 0.4 MW |
Winter Capacity | 0.3 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | October 2007 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Multiple Fuels | No |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 37 |
DC Net Capacity | 0.5 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator WH2 Details Operating November 2009
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 44 MW |
Summer Capacity | 44 MW |
Winter Capacity | 44 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | November 2009 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 22 |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 22 |
---|---|
Predominant Turbine Manufacturer | Vestas |
Predominant Turbine Model Number | V80-2.0 |
Design Wind Speed | 15.4 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 219.8 |
Wild Horse Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#250 | Tatanka Ridge | Toronto, SD | 599.5 GWh |
#251 | NaturEner Rim Rock Energy | Kevin, MT | 595.6 GWh |
#252 | Chapman Ranch Wind I | Corpus Christi, TX | 595.2 GWh |
#253 | Pattern Panhandle Wind 2 LLC | Panhandle, TX | 595.1 GWh |
#254 | Astra Wind Farm | Happy, TX | 594.3 GWh |
#255 | Limestone Wind Project | Coolidge, TX | 594.3 GWh |
#256 | Solano Wind | Rio Vista, CA | 592.9 GWh |
#257 | Golden Hill Wind | Wasco, OR | 590.4 GWh |
#258 | Cedar Springs II | Douglas, WY | 590.0 GWh |
#259 | Jumbo Hill Wind Project | Andrews, TX | 589.0 GWh |
#261 | Langford Wind Power | Christoval, TX | 587.5 GWh |
#262 | Prairie Wind Farm | Montezuma, IA | 587.3 GWh |
#263 | Heart of Texas Wind Project | Brady, TX | 586.8 GWh |
#264 | Kings Point Wind Energy Center | Golden City, MO | 585.4 GWh |
#265 | Carousel Wind Farm LLC | Burlington, CO | 583.9 GWh |
#266 | Castle Gap Wind | Goldthwaite, TX | 583.4 GWh |
#267 | Border Winds Wind Farm | Rolla, ND | 583.3 GWh |
#268 | Limon Wind I | Limon, CO | 582.1 GWh |
#269 | English Farms | Montezuma, IA | 581.3 GWh |
#270 | Minonk Wind Farm | Minonk, IL | 580.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Wild Horse.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Camas Solar Project | Ellensburg, WA | 10.3 GWh | 15.2 mi |
Chelan | Wenatchee, WA | 305.8 GWh | 55.9 mi |
Columbia Generating Station | Richland, WA | 9.9 TWh | 56.8 mi |
Cowiche | Tieton, WA | 3.4 GWh | 34.5 mi |
Orchard Avenue 1 | Yakima, WA | 2.6 GWh | 37.7 mi |
PEC Headworks | Moses Lake, WA | 18.7 GWh | 16.9 mi |
Penstemon Solar Project | Ellensburg, WA | 10.4 GWh | 15.2 mi |
Priest Rapids | Mattawa, WA | 3.8 TWh | 30.5 mi |
Quincy Chute | Quincy, WA | 33.8 GWh | 44.9 mi |
Rock Island | Wenatchee, WA | 2.0 TWh | 22.1 mi |
Rocky Reach | Wenatchee, WA | 4.8 TWh | 34.6 mi |
Roza | Yakima, WA | 54.5 GWh | 31.6 mi |
Russell D Smith | Othello, WA | 17.0 GWh | 55.6 mi |
Sagebrush Power Partners | Ellensburg, WA | 255.0 GWh | 23.6 mi |
Summer Falls Power Plant | Coulee City, WA | 447.2 GWh | 53.6 mi |
Swauk Wind LLC | Thorp, WA | 6.0 GWh | 26.7 mi |
Tieton Dam Hydro Electric Project | Rimrock, WA | 45.0 GWh | 50.8 mi |
Urtica Solar Project | Ellensburg, WA | 11.4 GWh | 23.3 mi |
Vantage Wind Energy LLC | Ellensburg, WA | 231.6 GWh | 5.8 mi |
Wanapum | Beverly, WA | 4.0 TWh | 15.8 mi |