Whitegrass No. 1
21 Julian Lane, Yerington, NV 89447Plant Summary Information
Whitegrass No. 1 is ranked #26 out of 26 geothermal power plants in Nevada in terms of total annual net electricity generation.
Whitegrass No. 1 is comprised of 4 generators and generated 5.0 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Whitegrass No. 1 |
---|---|
Utility Name | Open Mountain Energy LLC. |
Location | Lyon County, NV |
Initial Operation Date | October 2018 |
Last Update | Dec 2023 |
Annual Generation | 17.7 GWh |
Annual Consumption | 67.2 k MMBtu |
Ranked #5,201 out of 11,835 Power Plants Nationwide | |
Ranked #63 out of 63 Geothermal Power Plants Nationwide | |
Ranked #96 out of 109 Nevada Power Plants | |
Ranked #26 out of 26 Nevada Geothermal Power Plants | |
Fuel Types | Geothermal |
Map of Whitegrass No. 1
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Whitegrass No. 1.
Monthly Net Generation for Whitegrass No. 1
Whitegrass No. 1 Details
Summary Information | |
---|---|
Plant Name | Whitegrass No. 1 (63001) |
Plant Address | 21 Julian Lane, Yerington, NV 89447 |
Utility | Open Mountain Energy LLC. (62861) |
Latitude, Longitude | 39.16328, -119.18047 |
Generation Dates on File | Jan 2019 to Dec 2023 |
Initial Operation Date | October 2018 |
Annual Generation | 17.7 GWh |
Fuel Types | Geothermal |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | Nevada Power Company (NEVP) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Nevada Power Co (13407) NV |
Grid Voltage | 24.90 kV |
Energy Storage | No |
Generator OH1 Details Operating October 2018
Technology | Geothermal |
---|---|
Prime Mover | Turbines Used in a Binary Cycle |
Ownership | Single Owner |
Nameplate Capacity | 1.9 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 1.9 MW |
Winter Capacity | 1.9 MW |
Minimum Load | 0.3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 2018 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Geothermal |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator OH2 Details Operating October 2018
Technology | Geothermal |
---|---|
Prime Mover | Turbines Used in a Binary Cycle |
Ownership | Single Owner |
Nameplate Capacity | 1.9 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 1.9 MW |
Winter Capacity | 1.9 MW |
Minimum Load | 0.3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 2018 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Geothermal |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator OL1 Details Operating October 2018
Technology | Geothermal |
---|---|
Prime Mover | Turbines Used in a Binary Cycle |
Ownership | Single Owner |
Nameplate Capacity | 1.3 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 1.3 MW |
Winter Capacity | 1.3 MW |
Minimum Load | 0.3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 2018 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Geothermal |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator OL2 Details Operating October 2018
Technology | Geothermal |
---|---|
Prime Mover | Turbines Used in a Binary Cycle |
Ownership | Single Owner |
Nameplate Capacity | 1.3 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 1.3 MW |
Winter Capacity | 1.3 MW |
Minimum Load | 0.3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 2018 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Geothermal |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Whitegrass No. 1 Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Geothermal.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#43 | Galena 3 Geothermal Power Plant | Reno, NV | 92.1 GWh |
#44 | Desert Peak Power Plant | Fernley, NV | 91.9 GWh |
#45 | Raft River Geothermal Power Plant | Malta, ID | 88.6 GWh |
#46 | Stillwater Facility | Fallon, NV | 123.7 GWh |
#47 | San Emidio | Gerlach, NV | 83.0 GWh |
#48 | Aidlin Geothermal Power Plant | Middletown, CA | 77.3 GWh |
#49 | Salton Sea Power Gen Co Unit 1 | Calipatria, CA | 75.9 GWh |
#50 | ENEL Salt Wells LLC | Fallon, NV | 73.2 GWh |
#51 | Ormesa III | Holtville, CA | 68.5 GWh |
#52 | Jersey Valley Geothermal Power Plant | Imlay, NV | 66.7 GWh |
#53 | Mammoth G2 | Mammoth Lakes, CA | 62.3 GWh |
#54 | Mammoth G1 | Mammoth lakes, CA | 57.7 GWh |
#55 | CE Turbo LLC | Calipatria, CA | 54.8 GWh |
#56 | Thermo No 1 | Milford, UT | 54.8 GWh |
#57 | Star Peak Geothermal Plant | Imlay, NV | 51.8 GWh |
#58 | Steamboat III | Reno, NV | 45.6 GWh |
#59 | Steamboat II | Reno, NV | 42.1 GWh |
#60 | Galena 2 Geothermal Power Plant | Reno, NV | 38.1 GWh |
#61 | Lightning Dock Geothermal HI-01, LLC | Animas, NM | 31.2 GWh |
#62 | North Brawley Geothermal Plant | Brawley, CA | 28.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Whitegrass No. 1.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
ENEL Salt Wells LLC | Fallon, NV | 73.2 GWh | 33.8 mi |
Fleish | Fleish, NV | 20.7 GWh | 23.6 mi |
Fort Churchill | Yerington, NV | 508.0 GWh | 3.5 mi |
Ft. Churchill PV | Yerington, NV | 23.7 GWh | 3.3 mi |
Galena 2 Geothermal Power Plant | Reno, NV | 38.1 GWh | 34.4 mi |
Galena 3 Geothermal Power Plant | Reno, NV | 92.1 GWh | 34.2 mi |
Lahontan | Fallon, NV | 8.4 GWh | 21.6 mi |
New Lahontan | Fallon, NV | 17.2 GWh | 21.6 mi |
Patua Acquisition Project, LLC | Hazen, NV | 137.1 GWh | 29.8 mi |
Soda Lake 3 | Fallon, NV | 108.4 GWh | 32.3 mi |
Steamboat Hills LP | Reno, NV | 235.6 GWh | 34.5 mi |
Steamboat II | Reno, NV | 42.1 GWh | 34.3 mi |
Steamboat III | Reno, NV | 45.6 GWh | 34.3 mi |
Tesla Reno GigaFactory | Sparks, NV | 11.1 GWh | 29.4 mi |
Tracy | Sparks, NV | 4.0 TWh | 33.2 mi |
Turquoise Nevada, LLC | Sparks, NV | 106.3 GWh | 33.8 mi |
Verdi | Verdi, NV | 19.1 GWh | 24 mi |
Washoe | Verdi, NV | 11.1 GWh | 22.5 mi |
Waste Management Lockwood LFGTE | Sparks, NV | 23.7 GWh | 32.7 mi |
Western 102 Power Plant | McCarran, NV | 491.8 GWh | 32.6 mi |