White Rock/Slab Creek
Highway 50, Placerville, CA 95709Plant Summary Information
White Rock/Slab Creek is ranked #19 out of 222 hydroelectric power plants in California in terms of total annual net electricity generation.
White Rock/Slab Creek is comprised of 4 generators and generated 51.0 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | White Rock/Slab Creek |
---|---|
Utility Name | Sacramento Municipal Util Dist |
Location | El Dorado County, CA |
Initial Operation Date | February 1968 |
Last Update | Sep 2024 |
Annual Generation | 470.3 GWh |
Annual Consumption | 1.7 M MMBtu |
Ranked #1,348 out of 11,852 Power Plants Nationwide | |
Ranked #91 out of 1,371 Water Power Plants Nationwide | |
Ranked #90 out of 1,570 California Power Plants | |
Ranked #19 out of 222 California Water Power Plants | |
Fuel Types | Water |
Map of White Rock/Slab Creek
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for White Rock/Slab Creek.
Monthly Net Generation for White Rock/Slab Creek
White Rock/Slab Creek Details
Summary Information | |
---|---|
Plant Name | White Rock/Slab Creek (435) |
Plant Address | Highway 50, Placerville, CA 95709 |
Utility | Sacramento Municipal Util Dist (16534) |
Latitude, Longitude | 38.76534, -120.78737 |
Generation Dates on File | Jan 2001 to Sep 2024 |
Initial Operation Date | February 1968 |
Annual Generation | 470.3 GWh |
Fuel Types | Water |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | Balancing Authority of Northern California (BANC) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | South Fork American River |
Ash Impoundment | No |
Transmission / Distribution Owner | Sacramento Municipal Util Dist (16534) CA |
Grid Voltage | 230.00 kV |
Energy Storage | No |
Generator H2 Details Operating February 1968
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 133 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 133 MW |
Winter Capacity | 133 MW |
Minimum Load | 1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | February 1968 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator H1 Details Operating June 1968
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 133 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 108 MW |
Winter Capacity | 108 MW |
Minimum Load | 1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | June 1968 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator H4 Details Out of Service June 1983
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 0.5 MW |
Nameplate Power Factor | 0.86 |
Summer Capacity | 0.5 MW |
Winter Capacity | 0.5 MW |
Minimum Load | 0.5 MW |
Uprate/Derate Completed | No |
Status | Out of Service |
---|---|
First Operation Date | June 1983 |
Planned Retirement | December 2024 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator H3 Details Operating December 2020
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 2.7 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 2.7 MW |
Winter Capacity | 2.7 MW |
Minimum Load | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 2020 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
White Rock/Slab Creek Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#81 | Wyman Hydro | Bingham, ME | 501.6 GWh |
#82 | Barkley | Kuttawa, KY | 500.5 GWh |
#83 | Table Rock | Branson, MO | 499.1 GWh |
#84 | Don Pedro | La Grange, CA | 491.6 GWh |
#85 | Balch 2 | Balch Camp, CA | 489.7 GWh |
#86 | Ryan | Great Falls, MT | 486.3 GWh |
#87 | Pine Flat | Piedra, CA | 485.0 GWh |
#88 | Middle Fork | Foresthill, CA | 475.6 GWh |
#89 | Merwin | Ariel, WA | 471.6 GWh |
#90 | Wolf Creek | Jamestown, KY | 470.5 GWh |
#92 | Narrows (NC) | Badin, NC | 462.5 GWh |
#93 | Cannelton Hydroelectric Plant | Hawesville, KY | 460.6 GWh |
#94 | Ralston | Foresthill, CA | 459.9 GWh |
#95 | Lay Dam | Clanton, AL | 454.7 GWh |
#96 | Guntersville | Guntersville, AL | 453.4 GWh |
#97 | Cheoah | Tapoco, NC | 447.8 GWh |
#98 | Summer Falls Power Plant | Coulee City, WA | 447.2 GWh |
#99 | Fairfield Pumped Storage | Jenkinsville, SC | 442.4 GWh |
#100 | Apalachia | Reliance, TN | 435.9 GWh |
#101 | Hawks Nest Hydro | Gauley Bridge, WV | 435.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding White Rock/Slab Creek.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Blue Shld Of Cal- El Dorado Hlls Mtr B | El Dorado Hills, CA | 3.0 GWh | 17.4 mi |
Broadridge Cogen | El Dorado Hills, CA | 19.3 GWh | 17.7 mi |
Camino | Camino, CA | 282.3 GWh | 14.2 mi |
Chili Bar | Placerville, CA | 43.5 GWh | 1.5 mi |
Deer Creek 2 | Shingle Springs, CA | 2.7 GWh | 14.2 mi |
El Dorado | Pollock Pines, CA | 101.0 GWh | 9.3 mi |
El Dorado County | Placerville, CA | 3.8 GWh | 5.1 mi |
El Dorado Solar, LLC | El Dorado Hills, CA | 3.3 GWh | 17.1 mi |
Folsom | Folsom, CA | 626.4 GWh | 20.4 mi |
Folsom SP and CSP Sacramento | Represa, CA | 611.0 MWh | 20.8 mi |
Halsey | Auburn, CA | 7.3 GWh | 19.1 mi |
Intel Folsom Phase 3 | Folsom, CA | 8.7 GWh | 21.8 mi |
Jaybird | Camino, CA | 431.9 GWh | 14.6 mi |
Middle Fork | Foresthill, CA | 475.6 GWh | 20.7 mi |
Newcastle | Auburn, CA | 17.3 GWh | 17.1 mi |
Oxbow (CA) | Foresthill, CA | 13.8 GWh | 16.6 mi |
Ralston | Foresthill, CA | 459.9 GWh | 16.6 mi |
Rock Creek LP | Placerville, CA | 1.0 GWh | 1.3 mi |
Union Valley | Fresh Pond, CA | 168.2 GWh | 19.7 mi |
Wise | Auburn, CA | 64.6 GWh | 18.8 mi |