Western 102 Power Plant
2555 Waltham Way, McCarran, NV 89434Plant Summary Information
Western 102 Power Plant is ranked #24 out of 109 power plants in Nevada in terms of total annual net electricity generation.
Western 102 Power Plant is comprised of 15 generators and generated 142.3 GWh during the 3-month period between May 2024 to August 2024.
Plant Name | Western 102 Power Plant |
---|---|
Utility Name | Nevada Gold Mines |
Location | Storey County, NV |
Initial Operation Date | December 2005 |
Last Update | Aug 2024 |
Annual Generation | 491.8 GWh |
Annual Consumption | 4.9 M MMBtu |
Ranked #1,307 out of 11,835 Power Plants Nationwide | |
Ranked #566 out of 2,253 Natural Gas Power Plants Nationwide | |
Ranked #24 out of 109 Nevada Power Plants | |
Ranked #10 out of 17 Nevada Natural Gas Power Plants | |
Fuel Types | Natural Gas : 99.7% |
Previous Operator |
Barrick Goldstrike Mines Inc (2013 to 2018) Nevada Gold Mines (2019 to 2023) |
Map of Western 102 Power Plant
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Western 102 Power Plant.
Monthly Net Generation for Western 102 Power Plant
Western 102 Power Plant Details
Summary Information | |
---|---|
Plant Name | Western 102 Power Plant (56500) |
Plant Address | 2555 Waltham Way, McCarran, NV 89434 |
Utility | Nevada Gold Mines (55710) |
Latitude, Longitude | 39.5603, -119.5108 |
Generation Dates on File | Jan 2006 to Aug 2024 |
Initial Operation Date | December 2005 |
Annual Generation | 491.8 GWh |
Fuel Types | Natural Gas : 99.7% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | Nevada Power Company (NEVP) |
NAICS Code | Metal Ore Mining (2122) |
Sector | Industrial Non-CHP (6) |
Water Source | None |
Ash Impoundment | No |
Transmission / Distribution Owner | Nevada Power Co (13407) NV |
Grid Voltage | 120.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | TUSCARORA GAS TRANSMISSION CO |
Pipeline Notes | Sierra Pacific Power company gas supply is not used for power generation. |
Natural Gas Storage | No |
Generator A101 Details Operating December 2005
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 8.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.8 MW |
Winter Capacity | 9.3 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | Yes |
Uprate Or Derate Completed | May 2023 |
Status | Operating |
---|---|
First Operation Date | December 2005 |
Combined Heat & Power | No |
Sector Name | Industrial Non-CHP (6) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Other Planned Modifications | No |
Multiple Fuels | No |
Generator B102 Details Operating December 2005
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 8.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 7.9 MW |
Winter Capacity | 8.4 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2005 |
Combined Heat & Power | No |
---|---|
Sector Name | Industrial Non-CHP (6) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Planned Net Summer Capacity Uprate | 0.9 MW |
Planned Net Winter Capacity Uprate | 0.9 MW |
Planned Uprate | June 2026 |
Other Planned Modifications | No |
Multiple Fuels | No |
Generator B202 Details Operating December 2005
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 8.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 7.9 MW |
Winter Capacity | 8.4 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2005 |
Combined Heat & Power | No |
---|---|
Sector Name | Industrial Non-CHP (6) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Planned Net Summer Capacity Uprate | 0.9 MW |
Planned Net Winter Capacity Uprate | 0.9 MW |
Planned Uprate | April 2025 |
Other Planned Modifications | No |
Multiple Fuels | No |
Generator C102 Details Operating December 2005
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 8.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 7.9 MW |
Winter Capacity | 8.4 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2005 |
Combined Heat & Power | No |
---|---|
Sector Name | Industrial Non-CHP (6) |
Energy Source | Natural Gas |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Planned Net Summer Capacity Uprate | 0.9 MW |
Planned Net Winter Capacity Uprate | 0.9 MW |
Planned Uprate | June 2027 |
Other Planned Modifications | No |
Multiple Fuels | No |
Generator C202 Details Operating December 2005
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 8.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 7.9 MW |
Winter Capacity | 8.4 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2005 |
Combined Heat & Power | No |
---|---|
Sector Name | Industrial Non-CHP (6) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Planned Net Summer Capacity Uprate | 0.9 MW |
Planned Net Winter Capacity Uprate | 0.9 MW |
Planned Uprate | December 2026 |
Other Planned Modifications | No |
Multiple Fuels | No |
Generator D101 Details Operating December 2005
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 8.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.8 MW |
Winter Capacity | 9.3 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | Yes |
Uprate Or Derate Completed | December 2023 |
Status | Operating |
---|---|
First Operation Date | December 2005 |
Combined Heat & Power | No |
Sector Name | Industrial Non-CHP (6) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Other Planned Modifications | No |
Multiple Fuels | No |
Generator E102 Details Operating December 2005
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 8.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 7.9 MW |
Winter Capacity | 8.4 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2005 |
Combined Heat & Power | No |
---|---|
Sector Name | Industrial Non-CHP (6) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Planned Net Summer Capacity Uprate | 0.9 MW |
Planned Net Winter Capacity Uprate | 0.9 MW |
Planned Uprate | April 2024 |
Other Planned Modifications | No |
Multiple Fuels | No |
Generator E202 Details Operating December 2005
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 8.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.8 MW |
Winter Capacity | 9.3 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | Yes |
Uprate Or Derate Completed | April 2023 |
Status | Operating |
---|---|
First Operation Date | December 2005 |
Combined Heat & Power | No |
Sector Name | Industrial Non-CHP (6) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Other Planned Modifications | No |
Multiple Fuels | No |
Generator F102 Details Operating December 2005
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 8.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 7.9 MW |
Winter Capacity | 8.4 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2005 |
Combined Heat & Power | No |
---|---|
Sector Name | Industrial Non-CHP (6) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Planned Net Summer Capacity Uprate | 0.9 MW |
Planned Net Winter Capacity Uprate | 0.9 MW |
Planned Uprate | December 2025 |
Other Planned Modifications | No |
Multiple Fuels | No |
Generator F202 Details Operating December 2005
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 8.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 7.9 MW |
Winter Capacity | 8.4 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2005 |
Combined Heat & Power | No |
---|---|
Sector Name | Industrial Non-CHP (6) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Planned Net Summer Capacity Uprate | 0.9 MW |
Planned Net Winter Capacity Uprate | 0.9 MW |
Planned Uprate | March 2027 |
Other Planned Modifications | No |
Multiple Fuels | No |
Generator G102 Details Operating December 2005
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 8.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 7.9 MW |
Winter Capacity | 8.4 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2005 |
Combined Heat & Power | No |
---|---|
Sector Name | Industrial Non-CHP (6) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Planned Net Summer Capacity Uprate | 0.9 MW |
Planned Net Winter Capacity Uprate | 0.9 MW |
Planned Uprate | March 2026 |
Other Planned Modifications | No |
Multiple Fuels | No |
Generator G202 Details Operating December 2005
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 8.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 7.9 MW |
Winter Capacity | 8.4 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2005 |
Combined Heat & Power | No |
---|---|
Sector Name | Industrial Non-CHP (6) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Planned Net Summer Capacity Uprate | 0.9 MW |
Planned Net Winter Capacity Uprate | 0.9 MW |
Planned Uprate | March 2024 |
Other Planned Modifications | No |
Multiple Fuels | No |
Generator H102 Details Operating December 2005
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 8.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 7.9 MW |
Winter Capacity | 8.4 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2005 |
Combined Heat & Power | No |
---|---|
Sector Name | Industrial Non-CHP (6) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Planned Net Summer Capacity Uprate | 0.9 MW |
Planned Net Winter Capacity Uprate | 0.9 MW |
Planned Uprate | June 2025 |
Other Planned Modifications | No |
Multiple Fuels | No |
Generator H202 Details Operating December 2005
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 8.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 7.9 MW |
Winter Capacity | 8.4 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2005 |
Combined Heat & Power | No |
---|---|
Sector Name | Industrial Non-CHP (6) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Planned Net Summer Capacity Uprate | 0.9 MW |
Planned Net Winter Capacity Uprate | 0.9 MW |
Planned Uprate | December 2024 |
Other Planned Modifications | No |
Multiple Fuels | No |
Generator PV1 Details Operating December 2007
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 1 MW |
Summer Capacity | 1 MW |
Winter Capacity | 1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2007 |
---|---|
Combined Heat & Power | No |
Sector Name | Industrial Non-CHP (6) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Other Planned Modifications | No |
Multiple Fuels | No |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 21 |
DC Net Capacity | 1.3 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Western 102 Power Plant Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#556 | Kennedy International Airport Cogen | Jamaica, NY | 521.7 GWh |
#557 | SABIC Innovative Plastics Mt. Vernon | Mount Vernon, IN | 516.4 GWh |
#558 | Indeck Corinth Energy Center | Corinth, NY | 514.1 GWh |
#559 | General Electric Plastic | Burkeville, AL | 514.1 GWh |
#560 | Comanche (OK) | Lawton, OK | 511.9 GWh |
#561 | Sentinel Energy Center, LLC | Desert Hot Springs, CA | 509.8 GWh |
#562 | Fort Churchill | Yerington, NV | 508.0 GWh |
#563 | Geismar Cogen | Geismar, LA | 503.8 GWh |
#564 | Invenergy Nelson Expansion LLC | Rock Falls, IL | 510.8 GWh |
#565 | F.D. Kuester Generating Station | Negaunee, MI | 490.5 GWh |
#567 | South Belridge Cogeneration Facility | McKittrick, CA | 487.7 GWh |
#568 | Oxnard | Oxnard, CA | 483.7 GWh |
#569 | Broad River Energy Center | Gaffney, SC | 483.7 GWh |
#570 | Oak Grove (TX) | Franklin, TX | 10.7 TWh |
#571 | Sundance | Casa Grande, AZ | 480.4 GWh |
#572 | Dave Gates Generating Station | Anaconda, MT | 483.4 GWh |
#573 | Knox Lee | Longview, TX | 476.6 GWh |
#574 | Lawrence Energy Center | Lawrence, KS | 1.6 TWh |
#575 | Pensacola Florida Plant | Cantonment, FL | 461.9 GWh |
#576 | R W Miller | Palo Pinto, TX | 472.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Western 102 Power Plant.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Brady | Fallon, NV | 95.0 GWh | 31.2 mi |
Desert Peak Power Plant | Fernley, NV | 91.9 GWh | 32.5 mi |
Fleish | Fleish, NV | 20.7 GWh | 19.5 mi |
Galena 2 Geothermal Power Plant | Reno, NV | 38.1 GWh | 18.7 mi |
Galena 3 Geothermal Power Plant | Reno, NV | 92.1 GWh | 17.4 mi |
Lahontan | Fallon, NV | 8.4 GWh | 24.6 mi |
New Lahontan | Fallon, NV | 17.2 GWh | 24.7 mi |
Patua Acquisition Project, LLC | Hazen, NV | 137.1 GWh | 23.4 mi |
Richard Burdette Geothermal | Reno, NV | 110.1 GWh | 17.5 mi |
Stampede | Truckee, CA | 6.5 GWh | 32.3 mi |
Steamboat Hills LP | Reno, NV | 235.6 GWh | 19 mi |
Steamboat II | Reno, NV | 42.1 GWh | 17 mi |
Steamboat III | Reno, NV | 45.6 GWh | 17 mi |
Tesla Reno GigaFactory | Sparks, NV | 11.1 GWh | 4.1 mi |
Tracy | Sparks, NV | 4.0 TWh | 0.8 mi |
Turquoise Liberty Solar | Sparks, NV | 14.8 GWh | 2.1 mi |
Turquoise Nevada, LLC | Sparks, NV | 106.3 GWh | 1.2 mi |
Verdi | Verdi, NV | 19.1 GWh | 17.6 mi |
Washoe | Verdi, NV | 11.1 GWh | 18 mi |
Waste Management Lockwood LFGTE | Sparks, NV | 23.7 GWh | 7.4 mi |