Wessington Springs
230th Street & 380th Avenue, Wessington Springs, SD 57382Plant Summary Information
Wessington Springs is ranked #23 out of 49 power plants in South Dakota in terms of total annual net electricity generation.
Wessington Springs generated 75.3 GWh during the 3-month period between December 2023 to March 2024.
Plant Name | Wessington Springs |
---|---|
Utility Name | Wessington Wind |
Location | Jerauld County, SD |
Initial Operation Date | February 2009 |
Last Update | Mar 2024 |
Annual Generation | 224.5 GWh |
Annual Consumption | 765.9 k MMBtu |
Ranked #2,205 out of 11,249 Power Plants Nationwide | |
Ranked #696 out of 1,329 Wind Power Plants Nationwide | |
Ranked #23 out of 49 South Dakota Power Plants | |
Ranked #17 out of 25 South Dakota Wind Power Plants | |
Fuel Types | Wind |
Map of Wessington Springs
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Wessington Springs.
Monthly Net Generation for Wessington Springs
Wessington Springs Details
Summary Information | |
---|---|
Plant Name | Wessington Springs (56650) |
Plant Address | 230th Street & 380th Avenue Wessington Springs, SD 57382 |
Utility | Wessington Wind (59102) |
Latitude, Longitude | 44.0025, -98.59083 |
Generation Dates on File | Dec 2008 to Mar 2024 |
Initial Operation Date | February 2009 |
Annual Generation | 224.5 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | WAPA-- Western Area Power Administration (27000) SD |
Grid Voltage | 230.00 kV |
Energy Storage | No |
Generator 1 Details Operating February 2009
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 51 MW |
Summer Capacity | 51 MW |
Winter Capacity | 51 MW |
Minimum Load | 2.6 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | February 2009 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 34 |
Turbine Details | |
Number Of Turbines | 34 |
---|---|
Predominant Turbine Manufacturer | GE |
Predominant Turbine Model Number | 1.5 SLE |
Design Wind Speed | 19 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 262.5 |
Wessington Springs Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#686 | Locust Ridge II LLC | Shenandoah, PA | 229.6 GWh |
#687 | Pinyon Pine II | Mojave, CA | 229.3 GWh |
#688 | Weaver Wind | Township 16, ME | 229.0 GWh |
#689 | Jeffers Wind 20 LLC | Jeffers, MN | 228.9 GWh |
#690 | Crescent Ridge | Tiskilwa, IL | 228.1 GWh |
#691 | Cohocton Wind Project | Cohocton, NY | 228.1 GWh |
#692 | Harvest 2 | Elkton, MI | 228.0 GWh |
#693 | NWP Indian Mesa Wind Farm | Iraan, TX | 225.7 GWh |
#694 | Twin Buttes Wind Project | Lamar, CO | 225.5 GWh |
#695 | Red Barn Energy | Montfort, WI | 224.6 GWh |
#697 | Nine Canyon | Kennewick, WA | 223.3 GWh |
#698 | Montezuma Wind II | Birds Landing, CA | 222.9 GWh |
#699 | Meadow Lake Wind Farm IV | Lafayette, IN | 221.5 GWh |
#700 | Canyon Wind Project, LLC | Scurry, TX | 221.4 GWh |
#701 | FPL Energy Burleigh County Wind | Wilton, ND | 221.0 GWh |
#702 | Wethersfield | Gainsville, NY | 220.8 GWh |
#703 | Milo Wind Project LLC | Portales, NM | 219.1 GWh |
#704 | Osceola Windpower II | Harris, IA | 218.3 GWh |
#705 | Hog Creek Wind Project | Ada, OH | 218.2 GWh |
#706 | Hawkeye Power Partners LLC | Garner, IA | 218.0 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Wessington Springs.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Aurora County Wind | White Lake, SD | 97.2 GWh | 20.7 mi |
Beethoven Wind | Tripp, SD | 358.7 GWh | 63.6 mi |
Big Bend Dam | Chamberlain, SD | 872.9 GWh | 42.6 mi |
Bob Glanzer Generating Station | Huron, SD | 39.9 GWh | 32.8 mi |
Brule County Wind | Kimball, SD | 93.8 GWh | 25.7 mi |
Chamberlain Wind Project | Chamberlain, SD | 151.1 MWh | 34.4 mi |
Crocker Wind Farm | Conde, SD | 848.2 GWh | 81.7 mi |
Day County Wind LLC | Conde, SD | 451.4 GWh | 90.3 mi |
Fort Randall | Pickstown, SD | 1.6 TWh | 64.8 mi |
Lake Preston | Lake Preston, SD | 319.8 MWh | 65 mi |
North Bend Wind Project, LLC | SD | 208.8 GWh | 59 mi |
Oak Tree Energy | Clark, SD | 84.4 GWh | 76.7 mi |
Pierre Solar | Pierre, SD | 2.1 GWh | 89.1 mi |
POET Bioprocessing- Mitchell | Mitchell, SD | 20.2 GWh | 28 mi |
Prairie Winds SD1 | Crow Lake, SD | 417.5 GWh | 12.7 mi |
Prevailing Wind Park | Lesterville, SD | 859.1 GWh | 85.3 mi |
Rolling Thunder Wind Farm Hybrid | Miller, SD | 99.8 GWh | 42.4 mi |
South Dakota Wind Energy Cente | Highmore, SD | 84.9 GWh | 58.7 mi |
Sweetland Wind Farm, LLC | St. Lawrence, SD | 379.9 GWh | 28.5 mi |
Triple H Wind Project | Highmore, SD | 996.5 GWh | 57.2 mi |