Watts Bar Hydro

6868 Watts Bar Hwy, Spring City, TN 37381

Plant Summary Information

Watts Bar Hydro is ranked #48 out of 1,369 hydroelectric power plants nationwide in terms of total annual net electricity generation.

Watts Bar Hydro is comprised of 5 generators and generated 182.8 GWh during the 3-month period between September 2023 to December 2023.

Plant NameWatts Bar Hydro
Utility NameTennessee Valley Authority
LocationRhea County, TN
Initial Operation DateMarch 1942
Last Update Dec 2023
Annual Generation 812.4 GWh
Annual Consumption 3.0 M MMBtu
Ranked #872 out of 11,866 Power Plants Nationwide
Ranked #48 out of 1,369 Water Power Plants Nationwide
Ranked #11 out of 84 Tennessee Power Plants
Ranked #2 out of 28 Tennessee Water Power Plants
Fuel Types Water

Map of Watts Bar Hydro

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Watts Bar Hydro.

Create Your Account Today

Monthly Net Generation for Watts Bar Hydro

Watts Bar Hydro Details

Summary Information
Plant NameWatts Bar Hydro (3420)
Plant Address6868 Watts Bar Hwy, Spring City, TN 37381
UtilityTennessee Valley Authority (18642)
Latitude, Longitude35.61967, -84.78553
Generation Dates on FileJan 2001 to Dec 2023
Initial Operation DateMarch 1942
Annual Generation 812.4 GWh
Fuel Types Water
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusRegulated
NERC RegionSERC
Balancing AuthorityTennessee Valley Authority (TVA)
NAICS CodeUtilities (22)
Sector Electric Utility (1)
Water SourceTennessee River
Ash Impoundment
Transmission / Distribution OwnerTennessee Valley Authority (18642) TN
Grid Voltage 161.00 kV
Energy StorageNo

Generator HY3 Details Operating March 1942

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
Nameplate Capacity33.4 MW
Nameplate Power Factor0.94
Summer Capacity39.3 MW
Winter Capacity36.9 MW
Minimum Load16 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMarch 1942
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceWater
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo

Generator HY2 Details Operating April 1942

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
Nameplate Capacity33.4 MW
Nameplate Power Factor0.94
Summer Capacity39.3 MW
Winter Capacity36.9 MW
Minimum Load16 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateApril 1942
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceWater
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo

Generator HY1 Details Operating July 1942

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
Nameplate Capacity41 MW
Nameplate Power Factor0.94
Summer Capacity39.3 MW
Winter Capacity36.9 MW
Minimum Load16 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJuly 1942
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceWater
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo

Generator HY5 Details Operating March 1944

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
Nameplate Capacity33.4 MW
Nameplate Power Factor0.94
Summer Capacity39.3 MW
Winter Capacity36.9 MW
Minimum Load16 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMarch 1944
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceWater
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo

Generator HY4 Details Operating April 1944

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
Nameplate Capacity33.4 MW
Nameplate Power Factor0.94
Summer Capacity39.2 MW
Winter Capacity36.7 MW
Minimum Load30 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateApril 1944
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceWater
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo

Watts Bar Hydro Plant Owners

Owner NameAddressGeneratorOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Water.

RankPlant NamePlant LocationAnnual Generation
#38Safe HarborConestoga, PA989.2 GWh
#39HoltwoodHoltwood, PA949.8 GWh
#40Davis DamKingman, AZ908.9 GWh
#41Oxbow (OR)Oxbow, OR900.1 GWh
#42MossyrockSilver Creek, WA860.6 GWh
#43Devil CanyonSan Bernardino, CA856.1 GWh
#44YellowtailHardin, MT846.0 GWh
#45KeokukKeokuk, IA834.9 GWh
#46Cabinet GorgeClark Fork, ID815.7 GWh
#47Fontana DamFontana Dam, NC813.6 GWh
#49Selis Ksanka QlispePolson, MT804.8 GWh
#50Round ButteMadras, OR780.2 GWh
#51Big Bend DamChamberlain, SD770.5 GWh
#52Bull ShoalsMountain Home, AR750.5 GWh
#53Great Lakes Hydro America - MEMillinocket, ME737.2 GWh
#54Gavins PointCrofton, NE715.3 GWh
#55Sidney A Murray Jr HydroelectricVidalia, LA707.5 GWh
#56Fort PeckFort Peck, MT701.2 GWh
#57Big Creek 3Auberry, CA693.9 GWh
#58GorgeRockport, WA685.4 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Watts Bar Hydro.

Plant NamePlant LocationAnnual GenerationDistance
ApalachiaReliance, TN435.9 GWh41.7 mi
Buffalo Mountain Energy CenterOliver Springs, TN16.2 GWh42.9 mi
Bull RunClinton, TN750.8 GWh44.8 mi
CalderwoodTallassee, TN521.6 GWh46.1 mi
Chattanooga Metropolitan Airport SolarChattanooga, TN2.4 GWh47.5 mi
CheoahTapoco, NC447.8 GWh49.1 mi
ChickamaugaChattanooga, TN657.3 GWh43.7 mi
ChilhoweeTallassee, TN146.9 GWh41.6 mi
Fort LoudounLenoir City, TN676.5 GWh32.7 mi
Great Falls (TN)Rock Island, TN32.2 GWh49.3 mi
Hiwassee DamMurphy, NC232.2 GWh47.1 mi
KingstonKingston, TN3.3 TWh24.4 mi
Melton HillLenoir City, TN91.5 GWh32.8 mi
Ocoee 1Benton, TN69.8 GWh37.1 mi
Ocoee 2Benton, TN80.7 GWh40.7 mi
Ocoee 3Benton, TN141.4 GWh41.3 mi
Primient Loudon PlantLoudon, TN402.4 GWh27.4 mi
SequoyahSoddy Daisy, TN15.1 TWh32.2 mi
Volkswagen Solar SystemChattanooga, TN11.7 GWh40.9 mi
Watts Bar Nuclear PlantSpring City, TN19.1 TWh1.2 mi