Vega Solar
25100 S. Woo Road, Los Banos, CA 93635Plant Summary Information
Vega Solar is ranked #155 out of 799 solar farms in California in terms of total annual net electricity generation.
Vega Solar generated 8.5 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Vega Solar |
---|---|
Utility Name | Vega Solar, LLC |
Location | Merced County, CA |
Initial Operation Date | March 2015 |
Last Update | Dec 2023 |
Annual Generation | 47.7 GWh |
Annual Consumption | 169.6 k MMBtu |
Ranked #3,916 out of 11,852 Power Plants Nationwide | |
Ranked #796 out of 5,655 Solar Power Plants Nationwide | |
Ranked #475 out of 1,570 California Power Plants | |
Ranked #155 out of 799 California Solar Power Plants | |
Fuel Types | Solar |
Map of Vega Solar
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Vega Solar.
Monthly Net Generation for Vega Solar
Vega Solar Details
Summary Information | |
---|---|
Plant Name | Vega Solar (59555) |
Plant Address | 25100 S. Woo Road, Los Banos, CA 93635 |
Utility | Vega Solar, LLC (59298) |
Latitude, Longitude | 36.92583, -120.82 |
Generation Dates on File | Mar 2015 to Dec 2023 |
Initial Operation Date | March 2015 |
Annual Generation | 47.7 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | 15-478-000 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Pacific Gas & Electric Co (14328) CA |
Grid Voltage | 70.00 kV |
Energy Storage | No |
Generator VEGA1 Details Operating March 2015
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 20 MW |
Summer Capacity | 20 MW |
Winter Capacity | 20 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | March 2015 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Multiple Fuels | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 90 |
DC Net Capacity | 25.9 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Vega Solar Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#786 | RE Rosamond One LLC | Rosamond, CA | 49.1 GWh |
#787 | Whitehouse Solar Farm | Louisa, VA | 49.0 GWh |
#788 | Picture Rocks Solar, LLC | Marana, AZ | 49.0 GWh |
#789 | Midway Solar Farm III | Calipatria, CA | 48.9 GWh |
#790 | Simon Solar Farm LLC | Social Circle, GA | 48.6 GWh |
#791 | Wonderful Lost Hills | Lost Hills, CA | 48.3 GWh |
#792 | Shafter Solar LLC | Bakersfield, CA | 48.2 GWh |
#793 | Red Horse III | Wilcox, AZ | 48.1 GWh |
#794 | Rio Bravo Solar II LLC | McKittrick, CA | 48.0 GWh |
#795 | RE Garland A | Rosamond, CA | 47.9 GWh |
#797 | CED Ducor 1 | Ducor, CA | 47.7 GWh |
#798 | Long Island Solar Farm LLC | Upton, NY | 47.7 GWh |
#799 | NextEra Westside PV | Five Points, CA | 47.7 GWh |
#800 | Rawhide Prairie Solar Hybrid | Wellington, CO | 47.3 GWh |
#801 | Shoreham Solar Commons | Shoreham, NY | 47.4 GWh |
#802 | Bayshore Solar A, LLC | Lancaster, CA | 47.4 GWh |
#803 | SR Odom | Moultrie, GA | 47.4 GWh |
#804 | Westmoreland County Solar Project | WARSAW, VA | 47.2 GWh |
#805 | CED Ducor 2 | Ducor, CA | 47.2 GWh |
#806 | Antelope Expansion 1B | Lancaster, CA | 46.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Vega Solar.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
CalPeak Power Panoche Peaker Plant | Firebaugh, CA | 26.4 GWh | 23 mi |
Citizen B | Mendota, CA | 6.6 GWh | 25.6 mi |
Diamond H Dairy Power | Chowchilla, CA | 10.9 GWh | 25.5 mi |
Dinosaur Point | Los Banos, CA | 7.9 GWh | 21.1 mi |
Dos Palos | Dos Palos, CA | 1.6 GWh | 11.4 mi |
El Nido Facility | El Nido, CA | 43.7 GWh | 25.6 mi |
Firebaugh-CCS-PV-1 | Firebaugh, CA | 1.6 GWh | 17.5 mi |
Henry Miller RD | Dos Palos, CA | 3.3 GWh | 13.5 mi |
Little Bear 5 | Mendota, CA | 118.0 GWh | 26.7 mi |
Merced 1 PV | Los Banos, CA | 7.3 GWh | 5.4 mi |
Midway Peaking LLC | Firebaugh, CA | 25.7 GWh | 23 mi |
North Star Solar | Mendota, CA | 135.9 GWh | 26.4 mi |
Oro Loma | Oro Loma, CA | 25.3 GWh | 9.1 mi |
Panoche Energy Center | Firebaugh, CA | 1.2 TWh | 23 mi |
Panoche Peaker | Firebaugh, CA | 1.6 GWh | 23.1 mi |
Panoche Valley Solar Farm | Paicines, CA | 297.9 GWh | 20.9 mi |
Quinto Solar PV Project | Gustine, CA | 213.5 GWh | 19.1 mi |
Sun Harvest Solar NDP1 | Dos Palos, CA | 3.7 GWh | 12.9 mi |
W R Gianelli | Gustine, CA | 40.8 GWh | 17.3 mi |
Wright Solar Park | Los Banos, CA | 354.7 GWh | 9.5 mi |