Unit 4
11775 E 18500 N, Mt Pleasent, UT 84647Plant Summary Information
Unit 4 is ranked #19 out of 27 hydroelectric power plants in Utah in terms of total annual net electricity generation.
Unit 4 is comprised of 1 generator and generated 846.0 MWh during the 3-month period between September 2022 to December 2022.
Plant Name | Unit 4 |
---|---|
Utility Name | City of Mt Pleasant - (UT) |
Location | Sanpete County, UT |
Initial Operation Date | June 1993 |
Last Update | Dec 2022 |
Annual Generation | 3.5 GWh |
Annual Consumption | 13.0 k MMBtu |
Ranked #8,399 out of 11,249 Power Plants Nationwide | |
Ranked #1,209 out of 1,354 Water Power Plants Nationwide | |
Ranked #96 out of 113 Utah Power Plants | |
Ranked #19 out of 27 Utah Water Power Plants | |
Fuel Types | Water |
Map of Unit 4
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Unit 4.
Monthly Net Generation for Unit 4
Unit 4 Details
Summary Information | |
---|---|
Plant Name | Unit 4 (7015) |
Plant Address | 11775 E 18500 N Mt Pleasent, UT 84647 |
Utility | City of Mt Pleasant - (UT) (13037) |
Latitude, Longitude | 39.54411, -111.41873 |
Generation Dates on File | Jan 2001 to Dec 2022 |
Initial Operation Date | June 1993 |
Annual Generation | 3.5 GWh |
Fuel Types | Water |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | PacifiCorp - East (PACE) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Pleasant Creek |
Ash Impoundment | No |
Transmission / Distribution Owner | City of Mt Pleasant - (UT) (13037) UT |
Grid Voltage | 2.40 kV |
Energy Storage | No |
Generator 1 Details Operating June 1993
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 1.3 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 1.3 MW |
Winter Capacity | 0.3 MW |
Minimum Load | 0.2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | June 1993 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Unit 4 Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1199 | Granite | Salt lake City, UT | 3.8 GWh |
#1200 | Last Chance | Grace, ID | 3.7 GWh |
#1201 | Angels | Angels Camp, CA | 3.7 GWh |
#1202 | China Mill Hydro | Allenstown, NH | 3.7 GWh |
#1203 | Notre Dame Hydro | South Bend, IN | 3.6 GWh |
#1204 | Stairs | Salt Lake City, UT | 3.6 GWh |
#1205 | Waterloo Hydroelectric Project | Waterloo, NY | 3.6 GWh |
#1206 | El Vado Dam | Tierra Amarilla, NM | 3.6 GWh |
#1207 | Foothill | Sylmar, CA | 3.6 GWh |
#1208 | Ball Mountain Hydro | Jamaica, VT | 3.5 GWh |
#1210 | Lake Lure | Lake Lure, NC | 3.5 GWh |
#1211 | Talcville | Edwards, NY | 3.5 GWh |
#1212 | Rock Creek II | Twin Falls, ID | 3.4 GWh |
#1213 | El Dorado Hydro Elk Creek | New Meadows, ID | 3.4 GWh |
#1214 | Kings Falls Hydroelectric | Copenhagen, NY | 3.4 GWh |
#1215 | Snake Creek | Midway, UT | 3.4 GWh |
#1216 | Scott Flat | Nevada City, CA | 3.4 GWh |
#1217 | San Gabriel Hydro Project | Azusa, CA | 3.4 GWh |
#1218 | Queens Creek | Topton, NC | 3.3 GWh |
#1219 | East Highline | Holtville, CA | 3.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Unit 4.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Bartholomew | Springville, UT | 671.6 MWh | 43.3 mi |
BYU Central Heating Plant | Provo, UT | 124.6 GWh | 50.1 mi |
Clover Creek Solar Community Solar | Mona, UT | 208.0 GWh | 32.3 mi |
Currant Creek | Mona, UT | 3.1 TWh | 31.7 mi |
Graphite Solar I | Wellington, UT | 208.8 GWh | 37.6 mi |
Gunnison Solar | Gunnison, UT | 1.0 GWh | 33.1 mi |
Hunter | Castle Dale, UT | 3.1 TWh | 32.9 mi |
Hunter Solar LLC (UT) | Clawson, UT | 287.9 GWh | 34 mi |
Huntington | Huntington, UT | 3.0 TWh | 21.4 mi |
Hydro Plant No 3 | east of Ephraim, UT | 1.9 GWh | 23.8 mi |
Manti Lower | Manti, UT | 1.4 GWh | 22.7 mi |
Manti Upper | Manti, UT | 1.5 GWh | 22.7 mi |
Nebo Power Station | Payson, UT | 944.0 GWh | 39.4 mi |
Payson | Payson, UT | 4.4 MWh | 39.3 mi |
Provo Power Plant | Provo, UT | 7.8 GWh | 50 mi |
Spanish Fork | Spanish Fork, UT | 4.6 GWh | 38.3 mi |
Spanish Fork Community Solar | Spanish Fork, UT | 7.8 GWh | 41.9 mi |
Spanish Fork Wind Park 2 LLC | Spanish Fork, UT | 47.1 GWh | 37.5 mi |
Sunnyside Cogen Associates | Sunnyside, UT | 355.3 GWh | 54.7 mi |
Whitehead | Springville, UT | 16.0 GWh | 45.3 mi |