Twin Buttes Wind Project
31965 county Road, Lamar, CO 81052Plant Summary Information
Twin Buttes Wind Project is ranked #47 out of 267 power plants in Colorado in terms of total annual net electricity generation.
Twin Buttes Wind Project generated 55.2 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Twin Buttes Wind Project |
---|---|
Utility Name | Avangrid Renewables LLC |
Location | Bent County, CO |
Initial Operation Date | July 2007 |
Last Update | Dec 2023 |
Annual Generation | 219.0 GWh |
Annual Consumption | 814.3 k MMBtu |
Ranked #2,208 out of 11,852 Power Plants Nationwide | |
Ranked #674 out of 1,345 Wind Power Plants Nationwide | |
Ranked #47 out of 267 Colorado Power Plants | |
Ranked #23 out of 34 Colorado Wind Power Plants | |
Fuel Types | Wind |
Previous Operators |
Iberdrola Renewables Inc (2013 to 2014) Avangrid Renewables Inc (2015 to 2015) Avangrid Renewables LLC (2016 to 2023) |
Map of Twin Buttes Wind Project
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Twin Buttes Wind Project.
Monthly Net Generation for Twin Buttes Wind Project
Twin Buttes Wind Project Details
Summary Information | |
---|---|
Plant Name | Twin Buttes Wind Project (56460) |
Plant Address | 31965 county Road, Lamar, CO 81052 |
Utility | Avangrid Renewables LLC (15399) |
Latitude, Longitude | 37.6735, -102.8622 |
Generation Dates on File | Jul 2007 to Dec 2023 |
Initial Operation Date | July 2007 |
Annual Generation | 219.0 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | 07-15-000 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | Public Service Company of Colorado (PSCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Public Service Co of Colorado (15466) CO |
Grid Voltage | 230.00 kV |
Energy Storage | No |
Generator WT1 Details Operating July 2007
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 75 MW |
Summer Capacity | 75 MW |
Winter Capacity | 75 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 2007 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 50 |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 50 |
---|---|
Predominant Turbine Manufacturer | GE |
Predominant Turbine Model Number | 1.5 SLE |
Design Wind Speed | 18.3 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 262 |
Twin Buttes Wind Project Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#664 | Armenia Mountain Wind Farm | Mainesburg, PA | 224.0 GWh |
#665 | Broken Bow Wind LLC | Broken Bow, NE | 224.0 GWh |
#666 | Goodnoe Hills | Goldendale, WA | 223.9 GWh |
#667 | Lake Benton I | Lake Benton, MN | 223.1 GWh |
#668 | Reloj del Sol Wind Farm | San Ygnacio, TX | 222.5 GWh |
#669 | Stony Creek Wind Farm NY | Strykersville, NY | 221.7 GWh |
#670 | NaturEner Glacier Wind Energy 1 | Ethridge, MT | 221.4 GWh |
#671 | Brookfield Tehachapi 1 | Mojave, CA | 220.4 GWh |
#672 | Prairie Hill Wind Project | Mart, TX | 219.9 GWh |
#673 | Rockland Wind Farm | American Falls, ID | 219.4 GWh |
#675 | Independence Wind Farm | Manchester, IA | 218.4 GWh |
#676 | Cassadaga Wind Farm | Cherry Creek, NY | 218.2 GWh |
#677 | Wapsipinicon Wind Project | Dexter, MN | 217.0 GWh |
#678 | Harvest Wind Project | Roosevelt, WA | 216.8 GWh |
#679 | Vasco Winds | Livermore, CA | 216.0 GWh |
#680 | Foote Creek I | McFadden, WY | 215.5 GWh |
#681 | Sandy Ridge Wind 2, LLC | Tyrone, PA | 214.4 GWh |
#682 | Marshall Wind Farm | Frankfort, KS | 213.7 GWh |
#683 | Rising Tree Wind Farm | Mojave, CA | 213.4 GWh |
#684 | Coachella Hills Wind | Palm Springs, CA | 212.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Twin Buttes Wind Project.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Busch Ranch II Wind Farm | Walsenburg, CO | 176.8 GWh | 85.9 mi |
Busch Ranch Wind Energy Farm | Walsenburg, CO | 85.2 GWh | 89.5 mi |
Colorado Green Holdings LLC | Lamar, CO | 566.9 GWh | 13.2 mi |
Crossing Trails Wind Power Project LLC. | Seibert, CO | 416.3 GWh | 94.9 mi |
Holly | Holly, CO | 20.0 MWh | 49.7 mi |
Hugoton 2 | Hugoton, KS | 18.6 MWh | 90.6 mi |
Johnson | Johnson, KS | 35.0 MWh | 61.3 mi |
Johnson Corner Solar 1 | Johnson City, KS | 39.8 GWh | 58.8 mi |
Lamar Plant | Lamar, CO | 11.6 GWh | 30.5 mi |
Neptune Energy Center Hybrid | Boone, CO | 701.6 GWh | 95.9 mi |
NSE Camber BH CSG 2, LLC | Ordway, CO | 3.7 GWh | 60.8 mi |
Peak View Wind Farm | Walsenburg, CO | 183.4 GWh | 89.9 mi |
Rubart | Ulysses, KS | 70.3 GWh | 96.8 mi |
Springfield Wind | Springfield, CO | 5.0 GWh | 40.8 mi |
Sun Mountain Solar 1 | Unincorporated Pueblo, CO | 474.3 GWh | 96.8 mi |
Thunder Wolf Energy Center Hybrid | Avondale, CO | 569.1 GWh | 91 mi |
Trinidad (CO) | Trinidad, CO | 26.0 MWh | 95.5 mi |
Twin Buttes II Wind | Lamar, CO | 284.7 GWh | 18.6 mi |
USS Giveback Solar LLC (CSG) | Pueblo, CO | 60.0 MWh | 82.5 mi |
Vilas Solar Array | Springfield, CO | 8.9 GWh | 29.5 mi |