Triple H Wind Project
TBD, Highmore, SD 57266Plant Summary Information
Triple H Wind Project is ranked #6 out of 50 power plants in South Dakota in terms of total annual net electricity generation.
Triple H Wind Project generated 225.0 GWh during the 3-month period between May 2024 to August 2024.
Plant Name | Triple H Wind Project |
---|---|
Utility Name | Engie North America |
Location | Hyde County, SD |
Initial Operation Date | November 2020 |
Last Update | Aug 2024 |
Annual Generation | 953.4 GWh |
Annual Consumption | 3.5 M MMBtu |
Ranked #761 out of 11,835 Power Plants Nationwide | |
Ranked #79 out of 1,343 Wind Power Plants Nationwide | |
Ranked #6 out of 50 South Dakota Power Plants | |
Ranked #2 out of 25 South Dakota Wind Power Plants | |
Fuel Types | Wind |
Map of Triple H Wind Project
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Triple H Wind Project.
Monthly Net Generation for Triple H Wind Project
Triple H Wind Project Details
Summary Information | |
---|---|
Plant Name | Triple H Wind Project (63103) |
Plant Address | TBD, Highmore, SD 57266 |
Utility | Engie North America (56201) |
Latitude, Longitude | 44.40104, -99.60384 |
Generation Dates on File | Nov 2020 to Aug 2024 |
Initial Operation Date | November 2020 |
Annual Generation | 953.4 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Basin Electric Power Coop (1307) ND |
Grid Voltage | 345.00 kV |
Energy Storage | No |
Generator WTG Details Operating November 2020
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 250.2 MW |
Summer Capacity | 250.2 MW |
Winter Capacity | 250.2 MW |
Minimum Load | 2.7 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | November 2020 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Turbines/Hydrokinetic Buoys | 92 |
Turbine Details | |
Number Of Turbines | 92 |
---|---|
Predominant Turbine Manufacturer | GE |
Predominant Turbine Model Number | 2.7-116 |
Design Wind Speed | 20.1 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 295 |
Triple H Wind Project Plant Owners
Owner Name | Address | Ownership |
---|---|---|
Triple H Wind Project, LLC | 1990 Post Oak BLVD., Suite 1900, Houston, TX 77056 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#69 | Irish Creek Wind | Frankfort, KS | 981.1 GWh |
#70 | Rush Springs Wind | Marlow, OK | 970.2 GWh |
#71 | Pomeroy Wind Farm | Fonda, IA | 967.2 GWh |
#72 | Priddy Wind Project | Goldthwaite, TX | 961.0 GWh |
#73 | Little Blue Wind Project, LLC | Blue Hill, NE | 960.5 GWh |
#74 | Nobles 2 Wind Project | Wilmont, MN | 958.7 GWh |
#75 | Seven Cowboy Wind Project, LLC | Gage, OK | 956.0 GWh |
#76 | Wake Wind Energy Center | Floydada, TX | 954.0 GWh |
#77 | Balko Wind LLC | Balko, OK | 953.8 GWh |
#78 | La Joya NM | Encino, NM | 953.5 GWh |
#80 | Ponderosa Wind Energy Center | Beaver, OK | 939.9 GWh |
#81 | Ida Grove Wind | Ida Grove, IA | 939.8 GWh |
#82 | Pratt Wind, LLC | Andover, KS | 938.4 GWh |
#83 | Kingfisher Wind LLC | Kingfisher, OK | 937.8 GWh |
#84 | Great Western Wind Energy, LLC | Arnett, OK | 937.2 GWh |
#85 | TX Jumbo Road Wind | Hereford, TX | 935.0 GWh |
#86 | Sapphire Sky Wind Energy LLC | Farmer City, IL | 930.9 GWh |
#87 | Maverick Wind Project, LLC | Meno, OK | 929.9 GWh |
#88 | Biglow Canyon Wind Farm | Wasco, OR | 926.4 GWh |
#89 | Armadillo Flats Wind Project, LLC | Enid, OK | 924.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Triple H Wind Project.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Aberdeen CT | Aberdeen, SD | 44.3 GWh | 89.5 mi |
Aurora County Wind | White Lake, SD | 70.8 GWh | 62.3 mi |
Big Bend Dam | Chamberlain, SD | 770.5 GWh | 26.2 mi |
Bob Glanzer Generating Station | Huron, SD | 96.4 GWh | 70.7 mi |
Brule County Wind | Kimball, SD | 64.6 GWh | 58.1 mi |
Campbell County Wind Farm | Pollock, SD | 318.8 GWh | 99 mi |
Chamberlain Wind Project | Chamberlain, SD | 98.0 MWh | 42.1 mi |
Crocker Wind Farm | Conde, SD | 788.7 GWh | 98.1 mi |
Ft. Pierre | Fort Pierre, SD | 52.9 MWh | 38.4 mi |
Groton Generation Station | Groton, SD | 201.9 GWh | 99.7 mi |
North Bend Wind Project, LLC | Highmore, SD | 599.5 GWh | 3.2 mi |
Oahe | Pierre, SD | 2.1 TWh | 38.8 mi |
Oak Tree Energy | Clark, SD | 66.7 GWh | 98.6 mi |
Pierre Solar | Pierre, SD | 17.0 MWh | 34.7 mi |
POET Bioprocessing- Mitchell | Mitchell, SD | 17.6 GWh | 85.2 mi |
Prairie Winds SD1 | Crow Lake, SD | 343.7 GWh | 53.9 mi |
Rolling Thunder Wind Farm Hybrid | Miller, SD | 79.7 GWh | 23.8 mi |
South Dakota Wind Energy Cente | Highmore, SD | 78.5 GWh | 11.4 mi |
Sweetland Wind Farm, LLC | St. Lawrence, SD | 713.3 GWh | 39.6 mi |
Wessington Springs | Wessington Springs, SD | 221.8 GWh | 57.2 mi |