Topaz Generating
5651 Attwater Avenue, Texas City, TX 77590Plant Summary Information
Topaz Generating is ranked #91 out of 304 natural gas power plants in Texas in terms of total annual net electricity generation.
Topaz Generating is comprised of 10 generators and generated 264.3 GWh during the 3-month period between May 2024 to August 2024.
Plant Name | Topaz Generating |
---|---|
Utility Name | ProEnergy Services |
Location | Galveston County, TX |
Initial Operation Date | July 2021 |
Last Update | Aug 2024 |
Annual Generation | 657.2 GWh |
Annual Consumption | 8.0 M MMBtu |
Ranked #1,015 out of 11,835 Power Plants Nationwide | |
Ranked #507 out of 2,253 Natural Gas Power Plants Nationwide | |
Ranked #179 out of 749 Texas Power Plants | |
Ranked #91 out of 304 Texas Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Topaz Generating
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Topaz Generating.
Monthly Net Generation for Topaz Generating
Topaz Generating Details
Summary Information | |
---|---|
Plant Name | Topaz Generating (63688) |
Plant Address | 5651 Attwater Avenue, Texas City, TX 77590 |
Utility | ProEnergy Services (63082) |
Latitude, Longitude | 29.42639, -94.97667 |
Generation Dates on File | Jul 2021 to Aug 2024 |
Initial Operation Date | July 2021 |
Annual Generation | 657.2 GWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | EG20-250-000 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Texas-New Mexico Power Co (40051) TX |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | FLORIDA GAS TRANSMISSION COMPANY |
Natural Gas Storage | No |
Liquefied Natural Gas Storage | No |
Generator CTG-9 Details Operating October 2021
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | 138_ATT_TPZ |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 44.5 MW |
Winter Capacity | 49.8 MW |
Minimum Load | 22.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator CTG-1 Details Operating July 2021
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | 138_ATT_TPZ |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 44.5 MW |
Winter Capacity | 49.8 MW |
Minimum Load | 22.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator CTG-2 Details Operating July 2021
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | 138_ATT_TPZ |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 44.5 MW |
Winter Capacity | 49.8 MW |
Minimum Load | 22.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator CTG-3 Details Operating July 2021
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | 138_ATT_TPZ |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 44.5 MW |
Winter Capacity | 49.8 MW |
Minimum Load | 22.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator CTG-4 Details Operating July 2021
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | 138 ATT TPZ |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 44.5 MW |
Winter Capacity | 49.8 MW |
Minimum Load | 22.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator CTG-5 Details Operating July 2021
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | 138_ATT_TPZ |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 44.5 MW |
Winter Capacity | 49.8 MW |
Minimum Load | 22.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator CTG-6 Details Operating July 2021
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | 138_ATT_TPZ |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 44.5 MW |
Winter Capacity | 49.8 MW |
Minimum Load | 22.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator CTG-7 Details Operating July 2021
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | 138_ATT_TPZ |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 44.5 MW |
Winter Capacity | 49.8 MW |
Minimum Load | 22.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator CTG-8 Details Operating August 2021
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | 138_ATT_TPZ |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 44.5 MW |
Winter Capacity | 49.8 MW |
Minimum Load | 22.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | August 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator CTG10 Details Operating August 2021
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | 138_ATT_TPZ |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 44.5 MW |
Winter Capacity | 49.8 MW |
Minimum Load | 22.5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | August 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Topaz Generating Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
Topaz Generating, LLC | 8303 McHard Road, Houston, TX 77053 | Generator CTG-1 | 100.00% |
Topaz Generating, LLC | 8303 McHard Road, Houston, TX 77053 | Generator CTG-2 | 100.00% |
Topaz Generating, LLC | 8303 McHard Road, Houston, TX 77053 | Generator CTG-3 | 100.00% |
Topaz Generating, LLC | 8303 McHard Road, Houston, TX 77053 | Generator CTG-4 | 100.00% |
Topaz Generating, LLC | 8303 McHard Road, Houston, TX 77053 | Generator CTG-5 | 100.00% |
Topaz Generating, LLC | 8303 McHard Road, Houston, TX 77053 | Generator CTG-6 | 100.00% |
Topaz Generating, LLC | 8303 McHard Road, Houston, TX 77053 | Generator CTG-7 | 100.00% |
Topaz II, LLC | 8303 McHard Road, Houston, TX 77053 | Generator CTG-8 | 100.00% |
Topaz II, LLC | 8303 McHard Road, Houston, TX 77053 | Generator CTG-9 | 100.00% |
Topaz II, LLC | 8303 McHard Road, Houston, TX 77053 | Generator CTG10 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#497 | San Jacinto Steam Electric Station | La Porte, TX | 716.0 GWh |
#498 | Hawthorn | Kansas City, MO | 3.0 TWh |
#499 | Axiall Natrium Plant | New Martinsville, WV | 727.6 GWh |
#500 | Clark (NVE) | Las Vegas, NV | 693.0 GWh |
#501 | EG178 Facility | Snyder, TX | 686.9 GWh |
#502 | Cannon Falls Energy Center | Cannon Falls, MN | 681.9 GWh |
#503 | Martinez Refining | Martinez, CA | 702.3 GWh |
#504 | Deerhaven Generating Station | Gainesville, FL | 673.3 GWh |
#505 | Marathon Bay Area Cogen | Martinez, CA | 661.2 GWh |
#506 | Maddox | Hobbs, NM | 659.1 GWh |
#508 | Mountain Creek | Dallas, TX | 654.1 GWh |
#509 | Plant X | Earth, TX | 660.3 GWh |
#510 | Astoria Generating Station | Astoria, NY | 729.8 GWh |
#511 | Cleveland Cnty Generating Facility | Kings Mountain, NC | 640.9 GWh |
#512 | ExxonMobil Baton Rouge Turbine Generator | Baton Rouge, LA | 639.9 GWh |
#513 | Johnsonville | New Johnsonville, TN | 642.8 GWh |
#514 | SPA Cogen 3 | Sacramento, CA | 632.0 GWh |
#515 | J K Smith | Winchester, KY | 629.8 GWh |
#516 | Power Station 4 | Texas City, TX | 629.1 GWh |
#517 | Ladysmith | Woodford, VA | 660.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Topaz Generating.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Ascend Performance Materials Texas Inc. | Alvin, TX | 192.9 GWh | 18.4 mi |
Bacliff | Bacliff, TX | 126.9 GWh | 4.6 mi |
Bayou Cogen Plant | Pasadena, TX | 2.3 TWh | 14.2 mi |
GCWA | Texas City, TX | 433.0 MWh | 3.5 mi |
Green Power 2 | Texas City, TX | 3.8 TWh | 4.3 mi |
HEB00028 | League City, TX | 338.0 MWh | 7.6 mi |
HEB00769 | Webster, TX | 289.0 MWh | 13.7 mi |
NASA Johnson Space Center CHP | Houston, TX | 84.5 GWh | 11.6 mi |
Power Station 4 | Texas City, TX | 629.1 GWh | 4.7 mi |
Texas City Plant Union Carbide | Texas City, TX | 42.2 GWh | 3.9 mi |
Texas City Power Plant | Texas City, TX | 2.1 TWh | 3.8 mi |
WAL1062 | Friendswood, TX | 317.0 MWh | 14 mi |
WAL3298 | Kemah, TX | 298.0 MWh | 7.9 mi |
WAL3510 | Pearland, TX | 162.0 MWh | 17.6 mi |
WAL462 | Alvin, TX | 324.0 MWh | 15.3 mi |
WAL504 | Galveston, TX | 262.0 MWh | 14.1 mi |
WAL5116 | Deer Park, TX | 338.0 MWh | 18 mi |
WAL529 | La Marque, TX | 274.0 MWh | 4 mi |
WAL5388 | League City, TX | 315.0 MWh | 7.4 mi |
WAL752 | Pasadena, TX | 283.0 MWh | 18.8 mi |