Syncarpha Blandford Hybrid CSG

80 Chester Road, Blandford, MA 1008

Plant Summary Information

Syncarpha Blandford Hybrid CSG is ranked #29 out of 487 solar farms in Massachusetts in terms of total annual net electricity generation.

Syncarpha Blandford Hybrid CSG generated 1.5 GWh during the 3-month period between September 2023 to December 2023.

Plant NameSyncarpha Blandford Hybrid CSG
Utility NameSyncarpha Blandford, LLC
LocationHampden County, MA
Initial Operation DateDecember 2019
Last Update Dec 2023
Annual Generation 8.1 GWh
Annual Consumption 29.3 k MMBtu
Ranked #6,578 out of 11,836 Power Plants Nationwide
Ranked #1,989 out of 5,644 Solar Power Plants Nationwide
Ranked #101 out of 598 Massachusetts Power Plants
Ranked #29 out of 487 Massachusetts Solar Power Plants
Fuel Types Solar

Map of Syncarpha Blandford Hybrid CSG

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Syncarpha Blandford Hybrid CSG.

Create Your Account Today

Monthly Net Generation for Syncarpha Blandford Hybrid CSG

Syncarpha Blandford Hybrid CSG Details

Summary Information
Plant NameSyncarpha Blandford Hybrid CSG (62975)
Plant Address80 Chester Road, Blandford, MA 1008
UtilitySyncarpha Blandford, LLC (62822)
Latitude, Longitude42.21307, -72.93886
Generation Dates on FileJan 2020 to Dec 2023
Initial Operation DateDecember 2019
Annual Generation 8.1 GWh
Fuel Types Solar
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusYes
FERC Small Power Producer Docket Number19-19-000
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionNPCC
Balancing AuthorityISO New England Inc. (ISNE)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water Source
Ash Impoundment No
Transmission / Distribution OwnerNSTAR Electric Company (54913) MA
Grid Voltage 23.00 kV
Energy StorageYes

Generator SYBLS Details Operating December 2019

TechnologySolar Photovoltaic
Prime MoverPhotovoltaic
OwnershipSingle Owner
Nameplate Capacity4.9 MW
Summer Capacity4.9 MW
Winter Capacity4.9 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateDecember 2019
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceSolar
Solar Details
Fixed TiltYes
Azimuth Angle180
Tilt Angle20
DC Net Capacity7.1 MW
Crystalline SiliconYes
Net Metering AgreementNo
Virtual Net Metering AgreementYes
Virtual Net Metering DC Capacity7.1 MW

Generator SYBLB Details Operating May 2020

TechnologyBatteries
Prime MoverBattery
OwnershipSingle Owner
Nameplate Capacity3.9 MW
Nameplate Power Factor1
Summer Capacity3.9 MW
Winter Capacity3.9 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2020
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceElectricity used for energy storage
Time From Cold Shutdown To Full Load10M
Energy Storage Details
Nameplate Energy Capacity MWH7.9
Maximum Charge Rate3.9 MW
Maximum Discharge Rate3.9 MW
Storage TechnologyNIB
Nameplate Reactive Power Rating2.3
Storage Enclosure TypeCT
ArbitrageYes
Frequency RegulationYes
Ramping Spinning ReserveYes
System Peak ShavingYes
Excess Wind And Solar GenerationP
Ac CoupledYes
Direct Support Of Another UnitYes
Direct Support Plant Id62975
Direct Support Gen IdSYNLB
Support T D AssetNo

Syncarpha Blandford Hybrid CSG Plant Owners

Owner NameAddressGeneratorOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Solar.

RankPlant NamePlant LocationAnnual Generation
#1979Andromeda Community SolarLester Prairie, MN8.3 GWh
#1980Oakboro FarmLaurinburg, NC8.3 GWh
#1981Wendell Solar Farm LLCWendell, NC8.3 GWh
#1982Cottage Grove CSG, LLCCottage Grove, MN8.3 GWh
#1983Lenoir FarmKinston, NC8.3 GWh
#1984Little Rock Pham SolarPalmdale, CA8.3 GWh
#19854OaksFour Oaks, NC8.3 GWh
#1986Valencia 3Imperial, CA8.3 GWh
#1987Phillips Route 82 Solar LLCEast Fishkill, NY8.3 GWh
#1988Hertford Solar FarmHertford, NC8.3 GWh
#1990Cash SolarNashville, NC8.3 GWh
#1991Koppelman Sun CSGEagle Lake, MN8.2 GWh
#1992Felton CSG PV1-5Randolph, MN8.2 GWh
#1993TroupsburgTroupsburg, NY8.2 GWh
#1994Ironwood Solar LLCBlythe, CA8.2 GWh
#1995KilvertWarwick, RI8.2 GWh
#1996Equuleus Community Solar GardensRosemount, MN8.2 GWh
#1997MontSun Community SolarMontrose, MN8.2 GWh
#1998Southwick Solar PVSouthwick, MA8.2 GWh
#1999HMW Minster PV IVillage of Minster, OH8.2 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Syncarpha Blandford Hybrid CSG.

Plant NamePlant LocationAnnual GenerationDistance
CED Northampton Solar LLC HybridNorthampton, MA6.5 GWh13.3 mi
CED Westfield Solar, LLCWestfield, MA3.3 GWh9.8 mi
Chester Solar FarmChester, MA5.0 GWh6.9 mi
Cobble MountainGranville, MA10.5 GWh7.6 mi
Easthampton CSGEasthampton, MA3.5 GWh13.5 mi
Easthampton Landfill-City of EasthamptonEasthampton, MA2.8 GWh13.2 mi
GSPP Terrawatt Westfield LLC CSGWestfield, MA5.9 GWh11.1 mi
Holiday Hill Community WindRussell, MA9.5 GWh3.5 mi
Holyoke Solar Cooperative at MuellerHolyoke, MA3.9 GWh13.2 mi
Indian River HydroRussell, MA1.8 GWh4.9 mi
International Paper Woronoco MillWoronoco, MA6.2 GWh6.7 mi
Northampton Landfill Solar PVNorthampton, MA3.7 GWh12.8 mi
Southampton Solar PVSouthampton, MA2.6 GWh11.7 mi
Sunpin BlandfordSouthwick, MA6.2 GWh5.2 mi
Syncarpha Northampton Hybrid CSGNorthampton, MA5.0 GWh12.9 mi
Tanglewood Circle Solar 1 LLCBecket, MA7.3 GWh9.2 mi
Texon Hydroelectric ProjectRussell, MA6.1 GWh4.1 mi
Tolland Solar NG LLCTolland, MA4.8 GWh10.6 mi
Town of Otis Wind Energy ProjectOtis, MA2.8 GWh4.5 mi
Twiss Street SolarWestfield, MA2.2 GWh10.7 mi