Sutter Greenworks LLC
NY State Rte 25 and Fresh Pond, Calverton, NY 11933Plant Summary Information
Sutter Greenworks LLC is ranked #62 out of 452 solar farms in New York in terms of total annual net electricity generation.
Sutter Greenworks LLC generated 1.5 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Sutter Greenworks LLC |
---|---|
Utility Name | AES Distributed Energy |
Location | Suffolk County, NY |
Initial Operation Date | October 2015 |
Last Update | Dec 2023 |
Annual Generation | 8.0 GWh |
Annual Consumption | 28.5 k MMBtu |
Ranked #6,650 out of 11,852 Power Plants Nationwide | |
Ranked #2,084 out of 5,655 Solar Power Plants Nationwide | |
Ranked #342 out of 832 New York Power Plants | |
Ranked #62 out of 452 New York Solar Power Plants | |
Fuel Types | Solar |
Previous Operators |
sPower (2013 to 2013) Sustainable Power Group, LLC (2014 to 2020) AES Distributed Energy (2021 to 2023) |
Map of Sutter Greenworks LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Sutter Greenworks LLC.
Monthly Net Generation for Sutter Greenworks LLC
Sutter Greenworks LLC Details
Summary Information | |
---|---|
Plant Name | Sutter Greenworks LLC (59274) |
Plant Address | NY State Rte 25 and Fresh Pond, Calverton, NY 11933 |
Utility | AES Distributed Energy (61012) |
Latitude, Longitude | 40.92806, -72.77111 |
Generation Dates on File | Oct 2015 to Dec 2023 |
Initial Operation Date | October 2015 |
Annual Generation | 8.0 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | NPCC |
Balancing Authority | New York Independent System Operator (NYIS) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Long Island Power Authority (11171) NY |
Grid Voltage | 13.00 kV |
Energy Storage | No |
Generator SUTTG Details Operating October 2015
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 5 MW |
Summer Capacity | 4 MW |
Winter Capacity | 4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | October 2015 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Multiple Fuels | No |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 25 |
DC Net Capacity | 7.2 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Sutter Greenworks LLC Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#2074 | Fox CSG, LLC | Taylors Falls, MN | 8.0 GWh |
#2075 | Lenoir Farm 2 | Kinston, NC | 8.0 GWh |
#2076 | Duplin Solar LLC | Warsaw, NC | 8.0 GWh |
#2077 | 299 Farm to Market Rd Hybrid(CSG) | Wareham, MA | 7.9 GWh |
#2078 | Happy Hollow CSG Hybrid | Winchendon, MA | 8.0 GWh |
#2079 | Chocowinity Solar LLC | Chocowinity, NC | 8.0 GWh |
#2080 | RT405 Westerlo Solar 2 | Albany, NY | 8.0 GWh |
#2081 | Arcadia Solar | Arcadia, WI | 8.0 GWh |
#2082 | Webster Holdco Solar CSG | Webster, MN | 8.0 GWh |
#2083 | Cokato CSG | Cokato, MN | 8.0 GWh |
#2085 | Cameron Solar II | Cameron, SC | 7.9 GWh |
#2086 | Lancaster Little Rock | Landers, CA | 7.9 GWh |
#2087 | Burgaw Solar, LLC | Burgaw, NC | 7.9 GWh |
#2088 | Podunque Road CSG | Rushford, NY | 7.9 GWh |
#2089 | RT32 Westerlo Solar 1 | Westerlo, NY | 7.9 GWh |
#2090 | ELP Greenport CSG | Hudson, NY | 7.9 GWh |
#2091 | North Palm Springs 4A | Palm Springs, CA | 7.9 GWh |
#2092 | Shorthorn Holdings | McColl, SC | 7.9 GWh |
#2093 | Benson Solar, LLC | Benson, NC | 7.9 GWh |
#2094 | White Cross Farm | Chapel Hill, NC | 7.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Sutter Greenworks LLC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Caithness Long Island Energy Center | Yaphank, NY | 1.8 TWh | 11.8 mi |
Calabro Airport North Solar Project | Shirley, NY | 2.2 GWh | 9.1 mi |
Calabro Airport South Solar Project | Shirley, NY | 2.2 GWh | 9.2 mi |
Calverton | Calverton, NY | 4.1 GWh | 1.5 mi |
Calverton Solar Energy Center | Calverton, NY | 43.3 GWh | 1.5 mi |
Holtsville | Holtsville, NY | 15.9 GWh | 17.2 mi |
Holtsville Solar Project | Holtsville, NY | 2.1 GWh | 16.4 mi |
Leavenworth Greenworks LLC | Calverton, NY | 15.7 GWh | 0.4 mi |
Long Island Solar Farm LLC | Upton, NY | 47.7 GWh | 6.1 mi |
Orbit Bloom Fuel Cell | Medford, NY | 42.6 GWh | 12.7 mi |
Port Jefferson | Port Jefferson, NY | 396.4 GWh | 16.1 mi |
Richard M Flynn | Holtsville, NY | 429.5 GWh | 17.2 mi |
Riverhead Solar Farm | Calverton, NY | 30.4 GWh | 0.5 mi |
Shoreham | Wading River, NY | 767.0 MWh | 5.4 mi |
Shoreham Energy LLC | Shoreham, NY | 13.3 GWh | 5.3 mi |
Shoreham Solar Commons | Shoreham, NY | 47.4 GWh | 6.1 mi |
Stony Brook Cogen Plant | Stony Brook, NY | 288.5 GWh | 18.7 mi |
SWM Fuel Cell | Yaphank, NY | 57.4 GWh | 12.6 mi |
Wading River | Shoreham, NY | 12.7 GWh | 5.9 mi |
William Floyd School District | Mastic Beach, NY | 3.2 GWh | 11.2 mi |