Stock Island
6900 Front Street Extension, Stock Island, FL 33041Plant Summary Information
Stock Island is ranked #13 out of 38 distillate fuel oil power plants in Florida in terms of total annual net electricity generation.
Stock Island is comprised of 7 generators and generated 542.2 MWh during the 3-month period between September 2023 to December 2023.
Plant Name | Stock Island |
---|---|
Utility Name | Utility Board of Key West City |
Location | Monroe County, FL |
Initial Operation Date | November 1978 |
Last Update | Dec 2023 |
Annual Generation | 3.0 GWh |
Annual Consumption | 54.1 k MMBtu |
Ranked #9,017 out of 11,835 Power Plants Nationwide | |
Ranked #246 out of 1,262 Distillate Fuel Oil Power Plants Nationwide | |
Ranked #257 out of 279 Florida Power Plants | |
Ranked #13 out of 38 Florida Distillate Fuel Oil Power Plants | |
Fuel Types | Distillate Fuel Oil |
Map of Stock Island
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Stock Island.
Monthly Net Generation for Stock Island
Stock Island Details
Summary Information | |
---|---|
Plant Name | Stock Island (6584) |
Plant Address | 6900 Front Street Extension, Stock Island, FL 33041 |
Utility | Utility Board of Key West City (50079) |
Latitude, Longitude | 24.56333, -81.7342 |
Generation Dates on File | Jan 2001 to Dec 2023 |
Initial Operation Date | November 1978 |
Annual Generation | 3.0 GWh |
Fuel Types | Distillate Fuel Oil |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | SERC |
Balancing Authority | Florida Power & Light Company (FPL) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Florida Power & Light Co (6452) FL |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Generator GT1 Details Operating November 1978
Technology | Petroleum Liquids |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 23.4 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 19 MW |
Winter Capacity | 19 MW |
Minimum Load | 5 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | November 1978 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator MSD1 Details Operating June 1991
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 9.6 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 7.5 MW |
Winter Capacity | 7.5 MW |
Minimum Load | 4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | June 1991 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator MSD2 Details Operating June 1991
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 9.6 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 7.5 MW |
Winter Capacity | 7.5 MW |
Minimum Load | 4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | June 1991 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator GT2 Details Operating September 1999
Technology | Petroleum Liquids |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 19.7 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 17 MW |
Winter Capacity | 17 MW |
Minimum Load | 5 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 1999 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator GT3 Details Operating September 1999
Technology | Petroleum Liquids |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 19.7 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 17 MW |
Winter Capacity | 17 MW |
Minimum Load | 5 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 1999 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator GT4 Details Operating June 2006
Technology | Petroleum Liquids |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 42 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 44 MW |
Winter Capacity | 44 MW |
Minimum Load | 10 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | June 2006 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator EP2 Details Operating June 2012
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 2.5 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 2.5 MW |
Winter Capacity | 2.5 MW |
Minimum Load | 1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | June 2012 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Stock Island Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
Florida Municipal Power Agency | 8553 Commodity Circle, Orlando, FL 32819 | Generator EP2 | 100.00% |
Florida Municipal Power Agency | 8553 Commodity Circle, Orlando, FL 32819 | Generator GT1 | 100.00% |
Florida Municipal Power Agency | 8553 Commodity Circle, Orlando, FL 32819 | Generator GT2 | 100.00% |
Florida Municipal Power Agency | 8553 Commodity Circle, Orlando, FL 32819 | Generator GT3 | 100.00% |
Florida Municipal Power Agency | 8553 Commodity Circle, Orlando, FL 32819 | Generator GT4 | 100.00% |
Florida Municipal Power Agency | 8553 Commodity Circle, Orlando, FL 32819 | Generator MSD1 | 100.00% |
Florida Municipal Power Agency | 8553 Commodity Circle, Orlando, FL 32819 | Generator MSD2 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Distillate Fuel Oil.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#236 | Dahlberg | Nicholson, GA | 242.8 GWh |
#237 | Station I | Independence, MO | 3.1 GWh |
#238 | Chevak | Chevak, AK | 3.1 GWh |
#239 | G G Allen | Belmont, NC | 179.0 GWh |
#240 | Whelan Energy Center | Hastings, NE | 1.1 TWh |
#241 | Sand Point | Sand Point, AK | 3.3 GWh |
#242 | Pixelle Specialty Solutions LLC - Chillicothe Facility | Chillicothe, OH | 205.6 GWh |
#243 | Unalakleet | Unalakleet, AK | 3.0 GWh |
#244 | Big Stone | Big Stone City, SD | 1.6 TWh |
#245 | Nine Mile Point | Westwego, LA | 8.9 TWh |
#247 | Kasigluk | Kasigluk, AK | 2.9 GWh |
#248 | Kapstone | Charleston, SC | 372.9 GWh |
#249 | Wake County LFG Facility | Apex, NC | 57.9 GWh |
#250 | Columbus MS | Columbus, MS | 462.4 GWh |
#251 | John P Madgett | Alma, WI | 1.1 TWh |
#252 | NAEA Lakewood LLC | Lakewood, NJ | 245.5 GWh |
#253 | George Neal South | Salix, IA | 776.5 GWh |
#254 | UMCP CHP Plant | College Park, MD | 75.5 GWh |
#255 | Selawik | Selawik, AK | 2.8 GWh |
#256 | Lincoln Combustion | Stanley, NC | 3.4 GWh |
Nearby Power Plants
Below are closest 19 power plants surrounding Stock Island.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Beautyberry | Clewiston, FL | 119.7 GWh | 131.8 mi |
CSL Gas Recovery | Pompano Beach, FL | 40.0 GWh | 154.2 mi |
Dania Beach 7 | Ft. Lauderdale, FL | 6.5 TWh | 141.5 mi |
Everglades Solar Energy Center | Homestead, FL | 138.6 GWh | 100.2 mi |
FIU Solar | Miami, FL | 1.5 GWh | 119.4 mi |
Ghost Orchid Solar Energy Center | Clewiston, FL | 137.1 GWh | 135.3 mi |
IKEA Miami 327 | Miami, FL | 1.4 GWh | 119.7 mi |
Immokalee | Immokalee, FL | 150.7 GWh | 133.4 mi |
Lauderdale | Ft. Lauderdale, FL | 258.1 GWh | 141.5 mi |
Miami Dade County Resource Recovery Fac | Miami, FL | 233.7 GWh | 123.1 mi |
Miami Dade Solar Energy Center | Miami, FL | 129.6 GWh | 107.7 mi |
Pembroke Lakes Mall | Pembroke Pines, FL | 596.0 MWh | 134.1 mi |
Port Everglades | Ft. Lauderdale, FL | 5.1 TWh | 145.5 mi |
Sawgrass Solar Energy Center | Clewiston, FL | 139.2 GWh | 132.6 mi |
South District Wastewater Treatment Plt | Miami, FL | 21.7 GWh | 110.9 mi |
Turkey Point | Homestead, FL | 21.3 TWh | 106.6 mi |
Waste Management Naples LFGTE Project | Naples, FL | 24.5 GWh | 110.1 mi |
Wheelabrator South Broward | Ft. Lauderdale, FL | 413.1 GWh | 141.5 mi |
Woodyard | Clewiston, FL | 88.3 GWh | 134.5 mi |