Spring Valley Wind Project
1212 SR 893, Ely, NV 89301Plant Summary Information
Spring Valley Wind Project is ranked #33 out of 109 power plants in Nevada in terms of total annual net electricity generation.
Spring Valley Wind Project generated 69.9 GWh during the 3-month period between May 2024 to August 2024.
Plant Name | Spring Valley Wind Project |
---|---|
Utility Name | Pattern Operators LP |
Location | White Pine County, NV |
Initial Operation Date | August 2012 |
Last Update | Aug 2024 |
Annual Generation | 289.9 GWh |
Annual Consumption | 1.1 M MMBtu |
Ranked #1,868 out of 11,835 Power Plants Nationwide | |
Ranked #566 out of 1,343 Wind Power Plants Nationwide | |
Ranked #33 out of 109 Nevada Power Plants | |
Ranked #1 out of 1 Nevada Wind Power Plants | |
Fuel Types | Wind |
Map of Spring Valley Wind Project
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Spring Valley Wind Project.
Monthly Net Generation for Spring Valley Wind Project
Spring Valley Wind Project Details
Summary Information | |
---|---|
Plant Name | Spring Valley Wind Project (57192) |
Plant Address | 1212 SR 893, Ely, NV 89301 |
Utility | Pattern Operators LP (56545) |
Latitude, Longitude | 39.10417, -114.49222 |
Generation Dates on File | Jul 2012 to Aug 2024 |
Initial Operation Date | August 2012 |
Annual Generation | 289.9 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | Nevada Power Company (NEVP) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Sierra Pacific Power Co (17166) NV |
Grid Voltage | 230.00 kV |
Energy Storage | No |
Generator WTG Details Operating August 2012
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 150 MW |
Summer Capacity | 150 MW |
Winter Capacity | 150 MW |
Minimum Load | 150 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | August 2012 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 66 |
Turbine Details | |
Number Of Turbines | 66 |
---|---|
Predominant Turbine Manufacturer | Siemens |
Predominant Turbine Model Number | SWT-2.3-101 |
Design Wind Speed | 16.7 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 262.4 |
Spring Valley Wind Project Plant Owners
Owner Name | Address | Ownership |
---|---|---|
Spring Valley Wind LLC | Pier 1, Bay 3, San Francisco, CA 94111 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#556 | Fenton Wind Farm | Chandler, MN | 294.7 GWh |
#557 | Shiloh IV Wind Project LLC | Birds Landing, CA | 294.4 GWh |
#558 | MinnDakota Wind LLC | Ivanhoe, MN | 294.1 GWh |
#559 | Rosewater Wind Farm | Chalmers, IN | 293.6 GWh |
#560 | Lone Tree Wind, LLC | Tiskilwa, IL | 293.4 GWh |
#561 | Penascal II Wind Project LLC | Sarita, TX | 292.7 GWh |
#562 | Black Oak Wind Farm | Sauk Centre, MN | 292.4 GWh |
#563 | Buffalo Gap 3 Wind Farm | Nolan, TX | 292.1 GWh |
#564 | Deerfield Wind Energy 2 | Port Hope, MI | 291.8 GWh |
#565 | Kossuth County Wind | Lu Verne, IA | 291.6 GWh |
#567 | Elk River Wind | Beaumont, KS | 287.8 GWh |
#568 | New Creek Wind | New Creek, WV | 284.9 GWh |
#569 | Mountain View I & II | North Palm Springs, CA | 284.6 GWh |
#570 | Twin Buttes II Wind | Lamar, CO | 283.1 GWh |
#571 | Crane Creek Wind Energy Center | Riceville, IA | 282.2 GWh |
#572 | Wheatridge 1 | Lexington, OR | 280.2 GWh |
#573 | Tatanka Wind Power LLC | Ashley, ND | 279.3 GWh |
#574 | Northwest Ohio Wind | Haviland, OH | 281.0 GWh |
#575 | Tuscola Wind II LLC | Reese, MI | 277.0 GWh |
#576 | Campbell Hill Windpower | Glenrock, WY | 276.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Spring Valley Wind Project.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Beryl Solar Plant | Beryl, UT | 6.1 GWh | 111.1 mi |
Blue Mountain Biogas | Milford, UT | 12.0 MWh | 91.1 mi |
Blundell | Milford, UT | 248.2 GWh | 98 mi |
Cove Mountain Solar 2 | Beryl, UT | 317.3 GWh | 111.4 mi |
Enel Cove Fort | Cove Fort, UT | 155.0 GWh | 109.5 mi |
Escalante Solar I, LLC | Milford, UT | 212.6 GWh | 88.1 mi |
Escalante Solar II, LLC | Milford, UT | 212.9 GWh | 89.1 mi |
Escalante Solar III, LLC | Milford, UT | 209.7 GWh | 91.2 mi |
Granite Mountain Solar West, LLC | Cedar City, UT | 127.8 GWh | 110.2 mi |
Granite Peak Solar Plant | Milford, UT | 6.1 GWh | 94.4 mi |
Intermountain Power Project | Delta, UT | 4.1 TWh | 106 mi |
Laho Solar Plant | Milford, UT | 6.1 GWh | 96.6 mi |
Milford 2 | Milford, UT | 6.5 GWh | 94.8 mi |
Milford Flat Solar Plant | Milford, UT | 6.1 GWh | 97.8 mi |
Milford Solar 1 | Milford, UT | 260.4 GWh | 90 mi |
Milford Wind Corridor I LLC | Milford, UT | 346.0 GWh | 92.6 mi |
Milford Wind Corridor Stage II LLC | Milford, UT | 162.6 GWh | 91.3 mi |
Smithfield 3 | Milford, UT | 2.0 GWh | 96.4 mi |
South Milford Solar Plant | Milford, UT | 7.1 GWh | 95 mi |
Thermo No 1 | Milford, UT | 54.8 GWh | 95.7 mi |