Sonoma Central Landfill Phase I
500 Mecham Road, Petaluma, CA 94952Plant Summary Information
Sonoma Central Landfill Phase I is ranked #31 out of 38 landfill gas power plants in California in terms of total annual net electricity generation.
Sonoma Central Landfill Phase I is comprised of 4 generators and generated 2.1 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Sonoma Central Landfill Phase I |
---|---|
Utility Name | County of Sonoma Dept of Trnsp |
Location | Sonoma County, CA |
Initial Operation Date | July 1993 |
Last Update | Dec 2023 |
Annual Generation | 8.1 GWh |
Annual Consumption | 138.4 k MMBtu |
Ranked #6,582 out of 11,835 Power Plants Nationwide | |
Ranked #244 out of 299 Landfill Gas Power Plants Nationwide | |
Ranked #907 out of 1,569 California Power Plants | |
Ranked #31 out of 38 California Landfill Gas Power Plants | |
Fuel Types | Landfill Gas |
Map of Sonoma Central Landfill Phase I
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Sonoma Central Landfill Phase I.
Monthly Net Generation for Sonoma Central Landfill Phase I
Sonoma Central Landfill Phase I Details
Summary Information | |
---|---|
Plant Name | Sonoma Central Landfill Phase I (55752) |
Plant Address | 500 Mecham Road, Petaluma, CA 94952 |
Utility | County of Sonoma Dept of Trnsp (17412) |
Latitude, Longitude | 38.3017, -122.7489 |
Generation Dates on File | Jan 2001 to Dec 2023 |
Initial Operation Date | July 1993 |
Annual Generation | 8.1 GWh |
Fuel Types | Landfill Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | 97-116-000 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Solid Waste Landfill (562212) |
Sector | Commercial Non-CHP (4) |
Water Source | Closed System/Radiator |
Ash Impoundment | No |
Transmission / Distribution Owner | Pacific Gas & Electric Co (14328) CA |
Grid Voltage | 60.00 kV |
Energy Storage | No |
Generator P-11 Details Operating July 1993
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | SNMALF_6_UNITS |
Nameplate Capacity | 0.8 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.7 MW |
Winter Capacity | 0.7 MW |
Minimum Load | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 1993 |
---|---|
Combined Heat & Power | No |
Sector Name | Commercial Non-CHP (4) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator P-12 Details Operating July 1993
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | SNMALF_6_UNITS |
Nameplate Capacity | 0.8 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.7 MW |
Winter Capacity | 0.7 MW |
Minimum Load | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 1993 |
---|---|
Combined Heat & Power | No |
Sector Name | Commercial Non-CHP (4) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator P-13 Details Operating July 1993
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | SNMALF_6_UNITS |
Nameplate Capacity | 0.8 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.7 MW |
Winter Capacity | 0.7 MW |
Minimum Load | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 1993 |
---|---|
Combined Heat & Power | No |
Sector Name | Commercial Non-CHP (4) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator P-14 Details Operating July 1993
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 0.8 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.7 MW |
Winter Capacity | 0.7 MW |
Minimum Load | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 1993 |
Combined Heat & Power | No |
Sector Name | Commercial Non-CHP (4) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Sonoma Central Landfill Phase I Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Landfill Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#234 | New River Clean Energy | Beckley, WV | 9.1 GWh |
#235 | Veolia ES Blackfoot Landfill Facility | Winslow, IN | 9.0 GWh |
#236 | Ameresco Janesville | Janesville, WI | 9.0 GWh |
#237 | Hardin County LFGTE | Elizabethtown, KY | 8.9 GWh |
#238 | Norther Tier Landfill | Burlington, PA | 8.8 GWh |
#239 | G2 Energy Marion LLC | Ocala, FL | 8.7 GWh |
#240 | Nelson Gardens Landfill Gas to Energy | San Antonio, TX | 8.5 GWh |
#241 | Horry Land Fill Gas Site | Conway, SC | 8.4 GWh |
#242 | Terreva Wayne County RNG, LLC | Dudley, NC | 8.2 GWh |
#243 | MM Taunton Energy | Taunton, MA | 8.1 GWh |
#245 | Waste Management Northern Oaks LFGTE | Harrison, MI | 8.0 GWh |
#246 | CII Methane Management IV, LLC | Smithfield, NC | 7.9 GWh |
#247 | Prairie Bluff | Houston, MS | 7.8 GWh |
#248 | Flathead Landfill to Gas Energy Facility | Kalispell, MT | 7.8 GWh |
#249 | White Street Renewables | Greensboro, NC | 14.1 GWh |
#250 | COC Surry LFG, LLC | Mount Airy, NC | 7.6 GWh |
#251 | Henrico | Glen Allen, VA | 7.3 GWh |
#252 | Sonoma Central Landfill Phase II | Petaluma, CA | 6.6 GWh |
#253 | Mas Durham Power, LLC | Durham, NC | 6.6 GWh |
#254 | Grand River | Grand Ledge, MI | 6.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Sonoma Central Landfill Phase I.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
American Canyon Solar | American Canyon, CA | 6.6 GWh | 30.6 mi |
Beringer | Saint Helena, CA | 1.3 GWh | 20.5 mi |
Bodega Avenue Solar LLC | Petaluma, CA | 4.1 GWh | 2.8 mi |
Cottonwood Solar, LLC Cottonwood Carport | Novato, CA | 1.4 GWh | 15.4 mi |
Dissigno Healdsburg FPV, LLC | Healdsburg, CA | 5.9 GWh | 20.5 mi |
Geothermal 1 | Middletown, CA | 254.1 GWh | 31.2 mi |
Geothermal 2 | Middletown, CA | 279.8 GWh | 31 mi |
Kaiser Napa Valley Corporate Dr Fuel Cell | Napa, CA | 37.4 GWh | 26 mi |
Keysight - Santa Rosa | Santa Rosa, CA | 34.4 GWh | 12.6 mi |
Laguna Water Reclamation Facility | Santa Rosa, CA | 14.2 GWh | 4.7 mi |
Lavio Solar | Petaluma, CA | 1.8 GWh | 8.7 mi |
Nove Power Plant | Richmond, CA | 35.0 MWh | 30.5 mi |
Santa Rosa Junior College Petaluma Solar | Petaluma, CA | 1.8 GWh | 11.7 mi |
SFDK Solar | Vallejo, CA | 10.0 GWh | 30.4 mi |
Silveira Ranch Road Solar | Novato, CA | 5.5 GWh | 14.3 mi |
Sonoma Central Landfill Phase II | Petaluma, CA | 6.6 GWh | 0 mi |
Soscol Ferry Solar | Napa, CA | 4.3 GWh | 26.1 mi |
Stage Gulch Solar | Petaluma, CA | 1.6 GWh | 12.6 mi |
Waste Mangement Redwood LFGTE | Novato, CA | 5.9 GWh | 13.9 mi |
Windsor Floating Solar | Windsor, CA | 2.5 GWh | 16.8 mi |