Solar Photovoltaic Project #07
2200-2250 Palmetto Ave., Redlands, CA 92374Plant Summary Information
Solar Photovoltaic Project #07 is ranked #502 out of 747 solar farms in California in terms of total annual net electricity generation.
Solar Photovoltaic Project #07 generated 846.2 MWh during the 3-month period between September 2022 to December 2022.
Plant Name | Solar Photovoltaic Project #07 |
---|---|
Utility Name | Southern California Edison Co |
Location | San Bernardino County, CA |
Initial Operation Date | November 2012 |
Last Update | Dec 2022 |
Annual Generation | 3.3 GWh |
Annual Consumption | 12.0 k MMBtu |
Ranked #8,562 out of 11,249 Power Plants Nationwide | |
Ranked #3,516 out of 5,158 Solar Power Plants Nationwide | |
Ranked #1,185 out of 1,501 California Power Plants | |
Ranked #502 out of 747 California Solar Power Plants | |
Fuel Types | Solar |
Map of Solar Photovoltaic Project #07
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Solar Photovoltaic Project #07.
Monthly Net Generation for Solar Photovoltaic Project #07
Solar Photovoltaic Project #07 Details
Summary Information | |
---|---|
Plant Name | Solar Photovoltaic Project #07 (57221) |
Plant Address | 2200-2250 Palmetto Ave. Redlands, CA 92374 |
Utility | Southern California Edison Co (17609) |
Latitude, Longitude | 34.08611, -117.2275 |
Generation Dates on File | Nov 2012 to Dec 2022 |
Initial Operation Date | November 2012 |
Annual Generation | 3.3 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Southern California Edison Co (17609) CA |
Grid Voltage | 12.00 kV |
Energy Storage | No |
Generator S007A Details Operating November 2012
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 0.5 MW |
Summer Capacity | 0.5 MW |
Winter Capacity | 0.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | November 2012 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 5 |
DC Net Capacity | 0.6 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator S007B Details Operating November 2012
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 0.5 MW |
Summer Capacity | 0.5 MW |
Winter Capacity | 0.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | November 2012 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 5 |
DC Net Capacity | 0.6 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator S007C Details Operating November 2012
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 0.5 MW |
Summer Capacity | 0.5 MW |
Winter Capacity | 0.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | November 2012 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 5 |
DC Net Capacity | 0.6 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator S007D Details Operating November 2012
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 0.5 MW |
Summer Capacity | 0.5 MW |
Winter Capacity | 0.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | November 2012 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 5 |
DC Net Capacity | 0.6 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator S007E Details Operating November 2012
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 0.5 MW |
Summer Capacity | 0.5 MW |
Winter Capacity | 0.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | November 2012 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 5 |
DC Net Capacity | 0.6 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Solar Photovoltaic Project #07 Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#3506 | Madera 1 PV | Madera, CA | 3.3 GWh |
#3507 | Greenfield Solar PV | Greenfield, MA | 3.3 GWh |
#3508 | Oak Leaf Solar XXVII LLC | Greely, CO | 3.3 GWh |
#3509 | Tranquillity ID | Tranquillity, CA | 3.3 GWh |
#3510 | CMEEC - Bozrah | Bozrah, CT | 3.3 GWh |
#3511 | Dynamic Madison | Madison, ME | 3.3 GWh |
#3512 | Jackson Legler Solar 1 LLC | Jackson Township, NJ | 3.3 GWh |
#3513 | Wallace | Wallace, NC | 3.3 GWh |
#3514 | Gloucester | Gloucester City, NJ | 3.3 GWh |
#3515 | Blue Shld Of Cal- El Dorado Hlls Mtr B | El Dorado Hills, CA | 3.3 GWh |
#3517 | Shirley Water | Shirley, MA | 3.3 GWh |
#3518 | Hurteau Solar Project Hybrid | Uxbridge, MA | 3.3 GWh |
#3519 | Wilmington Solar | Wilmington, MA | 3.3 GWh |
#3520 | Padelford Solar | Berkley, MA | 3.3 GWh |
#3521 | Dulles | Jurupa Valley, CA | 3.3 GWh |
#3522 | Mendota Rich Dev CSG | Mendota, IL | 3.3 GWh |
#3523 | AES Tonawanda Solar LLC | Tonawanda, NY | 3.3 GWh |
#3524 | IOS - ERW9 | Carteret, NJ | 3.3 GWh |
#3525 | Rodeo Solar D2 | Lancaster, CA | 3.3 GWh |
#3526 | San Luis Solar Garden | Antonito, CO | 3.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Solar Photovoltaic Project #07.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Amazon San Bernardino | San Bernardino, CA | 6.6 GWh | 1.1 mi |
Century Generating Facility | Colton, CA | 1.1 GWh | 7.4 mi |
Colton Solar One, LLC | San Bernardino, CA | 4.9 GWh | 5.3 mi |
Drews Generating Facility | Colton, CA | 865.7 MWh | 7.4 mi |
Energy Center | Redlands, CA | 5.1 GWh | 4 mi |
IGS KSBD | Highland, CA | 6.8 GWh | 1.4 mi |
Kohls San Bernardino Solar Facility | San Bernardino, CA | 1.7 GWh | 2.3 mi |
Loma Linda University Cogen | Loma Linda, CA | 48.5 GWh | 2.7 mi |
Mountainview Generating Station | Redlands, CA | 2.7 TWh | 0.9 mi |
Redlands Community Hospital | Redlands, CA | 9.3 GWh | 3.7 mi |
RPUWD Scheuer Well Solar Project | San Bernardino, CA | 6.3 GWh | 3.2 mi |
Santa Ana 3 | Highlands, CA | 1.9 GWh | 7.5 mi |
SB Water Reclamation Fuel Cell | San Bernardino, CA | 10.4 GWh | 3.5 mi |
Solar Photovoltaic Project #05 | Redlands, CA | 1.8 GWh | 0.2 mi |
Solar Photovoltaic Project #11 | Redlands, CA | 4.3 GWh | 1.1 mi |
Solar Photovoltaic Project #13 | Redlands, CA | 2.9 GWh | 0.5 mi |
Solar Photovoltaic Project #16 | Redlands, CA | 1.9 GWh | 0.4 mi |
Solar Photovoltaic Project #22 | Redlands, CA | 429.6 MWh | 1 mi |
Solar Photovoltaic Project #28 | San Bernardino, CA | 2.5 GWh | 2.7 mi |
Solar Photovoltaic Project #48 | Redlands, CA | 4.2 GWh | 0.3 mi |