16829 Avenal Cutoff Road, Stratford, CA 93266Plant Summary Information
Slate Hybrid is ranked #17 out of 5,655 solar farms nationwide in terms of total annual net electricity generation.
Slate Hybrid generated 235.2 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | Slate Hybrid |
---|---|
Utility Name | MN8 Energy LLC |
Location | Kings County, CA |
Initial Operation Date | November 2021 |
Last Update | Sep 2024 |
Annual Generation | 665.0 GWh |
Annual Consumption | 2.6 M MMBtu |
Ranked #1,011 out of 11,852 Power Plants Nationwide | |
Ranked #17 out of 5,655 Solar Power Plants Nationwide | |
Ranked #47 out of 1,570 California Power Plants | |
Ranked #5 out of 799 California Solar Power Plants | |
Fuel Types | Solar |
Previous Operators |
RE Slate LLC (2019 to 2019) RE Slate 1 LLC (2020 to 2020) Goldman Sachs Renewable Power LLC (2021 to 2021) MN8 Energy LLC (2022 to 2023) |
Map of Slate Hybrid
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Slate Hybrid.
Monthly Net Generation for Slate Hybrid
Slate Hybrid Details
Summary Information | |
---|---|
Plant Name | Slate Hybrid (63727) |
Plant Address | 16829 Avenal Cutoff Road, Stratford, CA 93266 |
Utility | MN8 Energy LLC (61944) |
Latitude, Longitude | 36.22696, -119.8948 |
Generation Dates on File | Nov 2021 to Sep 2024 |
Initial Operation Date | November 2021 |
Annual Generation | 665.0 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | 21-38 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Pacific Gas & Electric Co. (14328) CA |
Grid Voltage | 230.00 kV |
Energy Storage | Yes |
Generator SLATE Details Operating November 2021
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 50.5 MW |
Summer Capacity | 50.5 MW |
Winter Capacity | 50.5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | November 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
DC Net Capacity | 67 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator SLBSV Details Operating February 2022
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
Nameplate Capacity | 46.5 MW |
Summer Capacity | 46.5 MW |
Winter Capacity | 46.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | February 2022 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Electricity used for energy storage |
Time From Cold Shutdown To Full Load | 10M |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 186 |
---|---|
Maximum Charge Rate | 46.5 MW |
Maximum Discharge Rate | 46.5 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 15.2 |
Storage Enclosure Type | CS |
Co Located Renewable Firming | P |
Excess Wind And Solar Generation | Yes |
Ac Coupled | Yes |
Direct Support Of Another Unit | Yes |
Direct Support Plant Id | 63727 |
Direct Support Gen Id | SLSVC |
Support T D Asset | No |
Generator SLSVC Details Operating February 2022
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 93 MW |
Summer Capacity | 93 MW |
Winter Capacity | 93 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | February 2022 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
DC Net Capacity | 119.4 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator SL3EC Details Operating March 2022
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 67.5 MW |
Summer Capacity | 67.5 MW |
Winter Capacity | 67.5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | March 2022 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
DC Net Capacity | 87.7 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator SLB3C Details Operating March 2022
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
Nameplate Capacity | 33.8 MW |
Summer Capacity | 33.8 MW |
Winter Capacity | 33.8 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | March 2022 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Electricity used for energy storage |
Time From Cold Shutdown To Full Load | 10M |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 135 |
---|---|
Maximum Charge Rate | 33.8 MW |
Maximum Discharge Rate | 33.8 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 11.1 |
Storage Enclosure Type | CS |
Co Located Renewable Firming | P |
Excess Wind And Solar Generation | Yes |
Ac Coupled | Yes |
Direct Support Of Another Unit | Yes |
Direct Support Plant Id | 63727 |
Direct Support Gen Id | SL3EC |
Support T D Asset | No |
Generator SLBPW Details Operating March 2022
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
Nameplate Capacity | 10 MW |
Summer Capacity | 10 MW |
Winter Capacity | 10 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | March 2022 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Electricity used for energy storage |
Time From Cold Shutdown To Full Load | 10M |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 40 |
---|---|
Maximum Charge Rate | 10 MW |
Maximum Discharge Rate | 10 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 3.3 |
Storage Enclosure Type | CS |
Co Located Renewable Firming | P |
Excess Wind And Solar Generation | Yes |
Ac Coupled | Yes |
Direct Support Of Another Unit | Yes |
Direct Support Plant Id | 63727 |
Direct Support Gen Id | SLPWR |
Support T D Asset | No |
Generator SLPWR Details Operating March 2022
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 26 MW |
Summer Capacity | 26 MW |
Winter Capacity | 26 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | March 2022 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
DC Net Capacity | 34.8 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator SLBES Details Operating April 2022
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
Nameplate Capacity | 50 MW |
Summer Capacity | 50 MW |
Winter Capacity | 50 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | April 2022 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Electricity used for energy storage |
Time From Cold Shutdown To Full Load | 10M |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 200 |
---|---|
Maximum Charge Rate | 50 MW |
Maximum Discharge Rate | 50 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 16.4 |
Storage Enclosure Type | CS |
Co Located Renewable Firming | P |
Excess Wind And Solar Generation | Yes |
Ac Coupled | Yes |
Direct Support Of Another Unit | Yes |
Direct Support Plant Id | 63727 |
Direct Support Gen Id | SLSTN |
Support T D Asset | No |
Generator SLSTN Details Operating April 2022
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 63 MW |
Summer Capacity | 63 MW |
Winter Capacity | 63 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | April 2022 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
DC Net Capacity | 81.4 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Slate Hybrid Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#7 | 2W Permian Solar Project Hybrid | Andrews, TX | 898.9 GWh |
#8 | Aktina Solar | El Campo, TX | 873.0 GWh |
#9 | Solar Star 1 | Rosamond, CA | 870.3 GWh |
#10 | Daggett 3 | Daggett, CA | 857.5 GWh |
#11 | Solana Generating Station | Gila Bend, AZ | 823.1 GWh |
#12 | Juno Solar Project | Lamesa, TX | 793.4 GWh |
#13 | Prospero Solar | Andrews, TX | 747.8 GWh |
#14 | Neptune Energy Center Hybrid | Boone, CO | 701.6 GWh |
#15 | Solar Star 2 | Rosamond, CA | 708.8 GWh |
#16 | Copper Mountain Solar 5, LLC | Boulder City, NV | 691.5 GWh |
#18 | IP Radian, LLC | Brookesmith, TX | 681.1 GWh |
#19 | Agua Caliente Solar Project | Dateland, AZ | 675.2 GWh |
#20 | Prospero Solar II | Andrews, TX | 675.0 GWh |
#21 | Arroyo Solar Energy Storage Hybrid | Pueblo Pintado, NM | 653.6 GWh |
#22 | Texas Solar Nova 1 | Spur, TX | 666.4 GWh |
#23 | Desert Sunlight 300, LLC | Desert Center, CA | 659.4 GWh |
#24 | Arlington Energy Center II | Blythe, CA | 628.1 GWh |
#25 | Silver State Solar Power South | Primm Valley, NV | 650.9 GWh |
#26 | Mojave Solar Project | Hinkley, CA | 627.0 GWh |
#27 | California Valley Solar Ranch | California Valley, CA | 623.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Slate Hybrid.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Almond | Lemoore, CA | 9.6 GWh | 1.3 mi |
American Kings Solar, LLC | Lemoore, CA | 325.3 GWh | 0.9 mi |
Aquamarine | Lemoore, CA | 409.5 GWh | 2.6 mi |
Chestnut | Lemoore, CA | 322.2 GWh | 4.6 mi |
Henrietta Peaker | Lemoore, CA | 5.0 GWh | 1 mi |
Henrietta Solar Project | Lemoore, CA | 234.2 GWh | 5 mi |
Huron Solar Station | Huron, CA | 31.3 GWh | 8.2 mi |
Java Solar, LLC | Lemoore, CA | 28.6 GWh | 4.4 mi |
Lemoore 1 | Lemoore, CA | 232.0 MWh | 5.8 mi |
Mustang Two | Lemoore, CA | 393.0 GWh | 0.7 mi |
RE Kansas Solar, LLC | Lemoore, CA | 38.7 GWh | 3.7 mi |
RE Kansas South LLC | Lemoore, CA | 51.1 GWh | 3.4 mi |
RE Kent South, LLC | Lemoore, CA | 40.6 GWh | 0.6 mi |
RE Mustang LLC | Lemoore, CA | 149.9 GWh | 0.6 mi |
Solar Blue | Lemoore, CA | 560.8 GWh | 3.7 mi |
Van der Kooi Dairy Solar Array | Riverdale, CA | 3.9 GWh | 8.4 mi |
Verwey-Hanford Dairy Digester #1 | Hanford, CA | 360.0 MWh | 12.2 mi |
Verwey-Hanford Dairy Digester #2 | Hanford, CA | 5.3 GWh | 12.2 mi |
Westlands Solar PV Farm | Huron, CA | 37.8 GWh | 11.8 mi |
Westside Solar Power PV1 | Lemoore, CA | 4.6 GWh | 0.9 mi |