Shakopee Energy Park
3030 Vierling Dr. E, Shakopee, MN 55379Plant Summary Information
Shakopee Energy Park is ranked #29 out of 52 natural gas power plants in Minnesota in terms of total annual net electricity generation.
Shakopee Energy Park is comprised of 5 generators and generated 6.3 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Shakopee Energy Park |
---|---|
Utility Name | Minnesota Municipal Power Agny |
Location | Scott County, MN |
Initial Operation Date | February 2017 |
Last Update | Dec 2023 |
Annual Generation | 25.2 GWh |
Annual Consumption | 240.9 k MMBtu |
Ranked #4,778 out of 11,852 Power Plants Nationwide | |
Ranked #1,334 out of 2,254 Natural Gas Power Plants Nationwide | |
Ranked #107 out of 736 Minnesota Power Plants | |
Ranked #29 out of 52 Minnesota Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Shakopee Energy Park
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Shakopee Energy Park.
Monthly Net Generation for Shakopee Energy Park
Shakopee Energy Park Details
Summary Information | |
---|---|
Plant Name | Shakopee Energy Park (60647) |
Plant Address | 3030 Vierling Dr. E, Shakopee, MN 55379 |
Utility | Minnesota Municipal Power Agny (12667) |
Latitude, Longitude | 44.78361, -93.48111 |
Generation Dates on File | Feb 2017 to Dec 2023 |
Initial Operation Date | February 2017 |
Annual Generation | 25.2 GWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | MRO |
Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Municipality |
Ash Impoundment | No |
Transmission / Distribution Owner | Shakopee Public Utilities Comm (16971) MN |
Grid Voltage | 13.80 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | CENTERPOINT ENERGY |
Natural Gas Storage | Yes |
Liquefied Natural Gas Storage | Yes |
Generator SQA01 Details Operating February 2017
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 9.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 9.3 MW |
Winter Capacity | 9.3 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | February 2017 |
---|---|
Combined Heat & Power | Yes |
Sector Name | Electric Utility (1) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator SQA02 Details Operating February 2017
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 9.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 9.3 MW |
Winter Capacity | 9.3 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | February 2017 |
Combined Heat & Power | Yes |
Sector Name | Electric Utility (1) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator SQA03 Details Operating February 2017
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 9.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 9.3 MW |
Winter Capacity | 9.3 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | February 2017 |
Combined Heat & Power | Yes |
Sector Name | Electric Utility (1) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator SQA04 Details Operating February 2017
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 9.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 9.3 MW |
Winter Capacity | 9.3 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | February 2017 |
Combined Heat & Power | Yes |
Sector Name | Electric Utility (1) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator SQA05 Details Operating February 2017
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 9.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 9.3 MW |
Winter Capacity | 9.3 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | February 2017 |
Combined Heat & Power | Yes |
Sector Name | Electric Utility (1) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Shakopee Energy Park Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1324 | Midway Peaking LLC | Firebaugh, CA | 25.7 GWh |
#1325 | Harbor Cogen | Wilmington, CA | 25.6 GWh |
#1326 | Saint Agnes Medical Center | Fresno, CA | 25.5 GWh |
#1327 | Montefieor Medical Center Moses Division | Bronx, NY | 28.7 GWh |
#1328 | Pine Street | Sebewaing, MI | 25.4 GWh |
#1329 | Opryland USA | Nashville, TN | 25.4 GWh |
#1330 | OBP Cogen | New York, NY | 25.4 GWh |
#1331 | Fairfield University CHP Plant | Fairfield, CT | 25.3 GWh |
#1332 | Illumina Way SD | San Diego, CA | 25.3 GWh |
#1333 | Elkins Generating Center | Elkins, AR | 25.2 GWh |
#1335 | Central Michigan University | Mt. Pleasant, MI | 25.1 GWh |
#1336 | Univ of NC Chapel Hill Cogen Facility | Chapel Hill, NC | 45.6 GWh |
#1337 | Hutchinson Plant #2 | Hutchinson, MN | 25.0 GWh |
#1338 | New Haven Harbor | New Haven, CT | 30.1 GWh |
#1339 | Orchard Park | Chambersburg, PA | 25.2 GWh |
#1340 | ECP Uptown Campus | Pittsburgh, PA | 24.7 GWh |
#1341 | Rensselaer Cogen | Rensselaer, NY | 24.7 GWh |
#1342 | Cutrale Citrus Juices USA I | Leesburg, FL | 24.5 GWh |
#1343 | Frito Lay Incorporated | Dayville, CT | 24.4 GWh |
#1344 | Plant No 2 Freeport | Freeport, NY | 24.6 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Shakopee Energy Park.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Black Dog | Burnsville, MN | 1.8 TWh | 11.5 mi |
Blue Lake | Shakopee, MN | 63.1 GWh | 2.4 mi |
Blue Lake Solar | Shakopee, MN | 4.4 GWh | 2.7 mi |
Covanta Hennepin Energy | Minneapolis, MN | 207.2 GWh | 16.9 mi |
Hennepin Island | Minneapolis, MN | 43.4 GWh | 17.7 mi |
Koda Biomass Plant | Shakopee, MN | 43.2 GWh | 2.9 mi |
Lake Waconia Community Solar Garden | Waconia, MN | 785.0 MWh | 17.5 mi |
Lake Waconia IV Community Solar Garden | Waconia, MN | 785.0 MWh | 17.5 mi |
Minnesota River | Chaska, MN | 7.4 GWh | 5 mi |
MSC-Scott01 LLC | Jordan, MN | 2.0 GWh | 8 mi |
Porter Way Community Solar Garden | Waconia, MN | 4.8 GWh | 15.3 mi |
SAF Hydroelectric LLC | Minneapolis, MN | 28.7 GWh | 17.7 mi |
Schultz CSG | Webster, MN | 3.0 GWh | 16.4 mi |
Shakopee Met Council WTP | Shakopee, MN | 2.0 GWh | 2.3 mi |
St. Paul Intl Airport Red & Blue Parking | St. Paul, MN | 3.0 GWh | 14.9 mi |
Twin Cities Hydro LLC | St. Paul, MN | 71.6 GWh | 16.5 mi |
USS DVL Solar CSG | Waconia, MN | 2.1 GWh | 15.1 mi |
USS Eggo Solar CSG | Cologne, MN | 2.2 GWh | 15.7 mi |
USS Hancock Solar LLC CSG | Cologne, MN | 2.2 GWh | 16 mi |
USS Westeros Solar LLC CSG | Belle Plaine, MN | 2.0 GWh | 15.8 mi |