Searcy Solar Hybrid
TBD, Searcy, AR 72143Plant Summary Information
Searcy Solar Hybrid is ranked #27 out of 79 power plants in Arkansas in terms of total annual net electricity generation.
Searcy Solar Hybrid generated 32.4 GWh during the 3-month period between October 2024 to January 2025.
Plant Name | Searcy Solar Hybrid |
---|---|
Utility Name | Searcy Solar, LLC |
Location | White County, AR |
Initial Operation Date | January 2022 |
Last Update | Jan 2025 |
Annual Generation | 209.6 GWh |
Annual Consumption | 748.1 k MMBtu |
Ranked #2,300 out of 11,979 Power Plants Nationwide | |
Ranked #287 out of 5,765 Solar Power Plants Nationwide | |
Ranked #27 out of 79 Arkansas Power Plants | |
Ranked #5 out of 33 Arkansas Solar Power Plants | |
Fuel Types | Solar |
Map of Searcy Solar Hybrid
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Searcy Solar Hybrid.
Monthly Net Generation for Searcy Solar Hybrid
Searcy Solar Hybrid Details
Summary Information | |
---|---|
Plant Name | Searcy Solar Hybrid (62617) |
Plant Address | TBD, Searcy, AR 72143 |
Utility | Searcy Solar, LLC (62109) |
Latitude, Longitude | 35.233, -91.69 |
Generation Dates on File | Jan 2022 to Jan 2025 |
Initial Operation Date | January 2022 |
Annual Generation | 209.6 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | SERC |
Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Entergy Arkansas LLC (814) AR |
Grid Voltage | 161.00 kV |
Energy Storage | Yes |
Generator SEABT Details Operating January 2022
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
Nameplate Capacity | 10 MW |
Summer Capacity | 10 MW |
Winter Capacity | 10 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | January 2022 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Electricity used for energy storage |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 30 |
---|---|
Maximum Charge Rate | 10 MW |
Maximum Discharge Rate | 10 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 7.8 |
Storage Enclosure Type | CS |
System Peak Shaving | Yes |
Excess Wind And Solar Generation | P |
DC Coupled | Yes |
Direct Support Of Another Unit | Yes |
Direct Support Plant Id | 62617 |
Direct Support Gen Id | SEARC |
Support T D Asset | No |
Generator SEARC Details Operating January 2022
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 100 MW |
Summer Capacity | 100 MW |
Winter Capacity | 100 MW |
Minimum Load | 1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | January 2022 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Solar |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 90 |
DC Net Capacity | 145.2 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Searcy Solar Hybrid Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#277 | Granite Mountain Solar East, LLC | Cedar City, UT | 213.5 GWh |
#278 | Grant County | Town of Potosi, WI | 213.0 GWh |
#279 | Escalante Solar I, LLC | Milford, UT | 212.6 GWh |
#280 | Samson Solar Energy III LLC | Cunningham, TX | 211.5 GWh |
#281 | Holliday Creek Solar | Fort Dodge, IA | 211.3 GWh |
#282 | Waverly Solar, LLC | Waverly, VA | 211.0 GWh |
#283 | Escalante Solar III, LLC | Milford, UT | 210.9 GWh |
#284 | Delta's Edge Solar | Greenwood, MS | 210.5 GWh |
#285 | Point Beach Solar | Two Creeks, WI | 210.3 GWh |
#286 | Cutlass Solar 1 LLC | Richmond, TX | 210.0 GWh |
#288 | Hunter Solar, LLC (CO) | Bennett, CO | 208.2 GWh |
#289 | Happy Solar 1 | Searcy, AR | 207.7 GWh |
#290 | Cavalier Solar | Smithfield, VA | 207.6 GWh |
#291 | Taylor County Solar | Butler, GA | 206.7 GWh |
#292 | Wagyu | Damon, TX | 205.2 GWh |
#293 | Onion River | Sheboygan Cedar Grove, WI | 204.3 GWh |
#294 | Two Creeks Solar | Two Rivers, WI | 204.1 GWh |
#295 | Cereal City Solar, LLC | Battle Creek, MI | 203.1 GWh |
#296 | Clover Creek Solar Community Solar | Mona, UT | 201.5 GWh |
#297 | Sigurd Solar LLC | Sigurd, UT | 201.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Searcy Solar Hybrid.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Farmers Electric Cooperative | Newport, AR | 2.2 GWh | 37.7 mi |
FECC Solar Benton | Benton, AR | 967.0 MWh | 65 mi |
Forrest City- Eldridge Road | Forrest City, AR | 2.1 GWh | 51.7 mi |
Forrest City- Prison Site | Forrest City, AR | 2.1 GWh | 52.9 mi |
Greers Ferry Lake | Heber Springs, AR | 209.7 GWh | 26.3 mi |
Happy Solar 1 | Searcy, AR | 207.7 GWh | 4.8 mi |
Harry L. Oswald | Little Rock, AR | 941.0 GWh | 53.4 mi |
Independence Steam Electric Station | Newark, AR | 5.4 TWh | 34.6 mi |
Jonesboro City Water & Light Plant | Jonesboro, AR | 84.7 GWh | 68.9 mi |
Murray | North Little Rock, AR | 142.4 GWh | 48.3 mi |
Newport Solar Project | Newport, AR | 353.8 GWh | 41.3 mi |
Stuttgart Solar | Stuttgart, AR | 155.8 GWh | 56.6 mi |
Two Pine Landfill Gas Recovery | North Little Rock, AR | 26.5 GWh | 38.2 mi |
Walnut Bend Solar Station PV | Moro, AR | 58.5 GWh | 51.5 mi |
Whillock | Morrilton, AR | 135.3 GWh | 62.6 mi |
White Bluff | Redfield, AR | 2.1 TWh | 61.5 mi |
White River Lock and Dam 1 | Batesville, AR | 15.3 GWh | 36.4 mi |
White River Lock and Dam 2 | Locust Grove, AR | 15.4 GWh | 35.6 mi |
White River Lock and Dam 3 | Marcella, AR | 30.7 GWh | 43.1 mi |
Woodruff County Solar | Augusta, AR | 58.5 GWh | 19.8 mi |