San Diego State University
5500 Campanile Drive, San Diego, CA 92182Plant Summary Information
San Diego State University is ranked #90 out of 346 natural gas power plants in California in terms of total annual net electricity generation.
San Diego State University generated 14.3 GWh during the 3-month period between May 2024 to August 2024.
Plant Name | San Diego State University |
---|---|
Utility Name | San Diego State University |
Location | San Diego County, CA |
Initial Operation Date | September 2002 |
Last Update | Aug 2024 |
Annual Generation | 56.5 GWh |
Annual Consumption | 853.6 k MMBtu |
Ranked #3,722 out of 11,835 Power Plants Nationwide | |
Ranked #1,050 out of 2,253 Natural Gas Power Plants Nationwide | |
Ranked #440 out of 1,569 California Power Plants | |
Ranked #90 out of 346 California Natural Gas Power Plants | |
Fuel Types | Natural Gas : 97.6% Solar : 2.4% |
Map of San Diego State University
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for San Diego State University.
Monthly Net Generation for San Diego State University
San Diego State University Details
Summary Information | |
---|---|
Plant Name | San Diego State University (50061) |
Plant Address | 5500 Campanile Drive, San Diego, CA 92182 |
Utility | San Diego State University (16625) |
Latitude, Longitude | 32.77823, -117.07011 |
Generation Dates on File | Jan 2001 to Aug 2024 |
Initial Operation Date | September 2002 |
Annual Generation | 56.5 GWh |
Fuel Types | Natural Gas : 97.6% Solar : 2.4% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | Yes |
FERC Cogeneration Docket Number | 85-626-000 |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Educational Services (611) |
Sector | Commercial CHP (5) |
Water Source | City Of San Diego |
Ash Impoundment | No |
Transmission / Distribution Owner | San Diego Gas & Electric Co (16609) CA |
Grid Voltage | 12.00 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | SAN DIEGO GAS AND ELECTRIC COMPANY |
Natural Gas Storage | No |
Generator GEN4 Details Operating December 2002
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CC1 |
Ownership | Single Owner |
Duct Burners | Yes |
Nameplate Capacity | 4.1 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 2.1 MW |
Winter Capacity | 1.1 MW |
Minimum Load | 1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 2002 |
Combined Heat & Power | Yes |
Sector Name | Commercial CHP (5) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Generator GEN2 Details Operating September 2002
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | Yes |
Nameplate Capacity | 5.1 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 4.5 MW |
Winter Capacity | 4.9 MW |
Minimum Load | 3.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2002 |
---|---|
Combined Heat & Power | Yes |
Sector Name | Commercial CHP (5) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator GEN3 Details Operating September 2002
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | Yes |
Nameplate Capacity | 5.1 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 4.5 MW |
Winter Capacity | 4.9 MW |
Minimum Load | 3.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2002 |
---|---|
Combined Heat & Power | Yes |
Sector Name | Commercial CHP (5) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator GEN5 Details Operating September 2009
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 0.1 MW |
Summer Capacity | 0.1 MW |
Winter Capacity | 0.1 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | September 2009 |
Combined Heat & Power | No |
Sector Name | Commercial CHP (5) |
Energy Source | Solar |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 185 |
Tilt Angle | 35 |
DC Net Capacity | 0.1 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | Yes |
Net Metering DC Capacity | 0.1 MW |
Virtual Net Metering Agreement | No |
Generator GEN6 Details Operating October 2011
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 0.3 MW |
Summer Capacity | 0.3 MW |
Winter Capacity | 0.2 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | October 2011 |
Combined Heat & Power | No |
Sector Name | Commercial CHP (5) |
Energy Source | Solar |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 265 |
Tilt Angle | 5 |
DC Net Capacity | 0.4 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | Yes |
Net Metering DC Capacity | 0.4 MW |
Virtual Net Metering Agreement | No |
Generator GEN7 Details Operating April 2012
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 0.3 MW |
Summer Capacity | 0.3 MW |
Winter Capacity | 0.2 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | April 2012 |
Combined Heat & Power | No |
Sector Name | Commercial CHP (5) |
Energy Source | Solar |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 15 |
DC Net Capacity | 0.3 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | Yes |
Net Metering DC Capacity | 0.3 MW |
Virtual Net Metering Agreement | No |
Generator GEN8 Details Operating March 2014
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 0.1 MW |
Summer Capacity | 0.1 MW |
Winter Capacity | 0.1 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | March 2014 |
Combined Heat & Power | No |
Sector Name | Commercial CHP (5) |
Energy Source | Solar |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Other Solar Technology | No |
Azimuth Angle | 180 |
Tilt Angle | 10 |
DC Net Capacity | 0.1 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | Yes |
Net Metering DC Capacity | 0.1 MW |
Virtual Net Metering Agreement | No |
San Diego State University Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1040 | Sylvamo Corporation Eastover Facility | Eastover, SC | 558.8 GWh |
#1041 | Pine Bluff Mill | Pine Bluff, AR | 289.0 GWh |
#1042 | SWM Fuel Cell | Yaphank, NY | 57.4 GWh |
#1043 | Tres Port Power, LLC | Victoria, TX | 56.4 GWh |
#1044 | Spruance Operating Services LLC | Richmond, VA | 56.2 GWh |
#1045 | Hyperion Treatment Plant CHP Plant | Playa del Rey, CA | 136.4 GWh |
#1046 | LSU Cogen | Baton Rouge, LA | 55.7 GWh |
#1047 | Cogeneration 1 | Tucson, AZ | 55.5 GWh |
#1048 | Bristol Myers Squibb New Brunswick | New Brunswick, NJ | 55.5 GWh |
#1049 | DTE Atlantic, LLC | Atlantic City, NJ | 55.3 GWh |
#1051 | Jesup Plant | Jesup, GA | 483.2 GWh |
#1052 | Certain Solar - Staten Island | Staten Island, NY | 55.0 GWh |
#1053 | Pulliam | Green Bay, WI | 54.8 GWh |
#1054 | International Paper Franklin Mill | Franklin, VA | 254.3 GWh |
#1055 | Equus Freeport Power | Village of Freeport, NY | 54.7 GWh |
#1056 | Kalkaska CT #1 | Kalkaska, MI | 54.5 GWh |
#1057 | Cymric 36W Cogen | McKittrick, CA | 54.4 GWh |
#1058 | Crete Energy Venture LLC | Crete, IL | 54.1 GWh |
#1059 | Domino Sugar Baltimore | Baltimore, MD | 54.2 GWh |
#1060 | Alpaca | Canton Township, PA | 53.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding San Diego State University.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
AT&T - San Diego Trade Street | San Diego, CA | 6.5 GWh | 9.4 mi |
Childrens Hospital | San Diego, CA | 26.7 GWh | 5 mi |
County of San Diego COC Hybrid | San Diego, CA | 3.1 GWh | 5.2 mi |
CP Kelco San Diego Plant | San Diego, CA | 83.2 GWh | 7.2 mi |
Cuyamaca Peak Energy Plant | El Cajon, CA | 12.1 GWh | 5.8 mi |
El Cajon Energy Center | El Cajon, CA | 7.6 GWh | 5.8 mi |
Grossmont Hospital | La Mesa, CA | 27.5 GWh | 3.7 mi |
Grossmont HS Solar Project | El Cajon, CA | 2.1 GWh | 4.9 mi |
Illumina Way SD | San Diego, CA | 25.3 GWh | 10 mi |
Kyocera International Inc.(San Diego) | San Diego, CA | 8.8 GWh | 5 mi |
Lindberg FIeld Solar | San Diego, CA | 4.6 GWh | 8.7 mi |
Lindberg Field Solar 2 | San Diego, CA | 3.5 GWh | 8.5 mi |
Miramar Energy Facility | San Diego, CA | 12.9 GWh | 8.8 mi |
MM San Diego-Miramar | San Diego, CA | 35.9 GWh | 7.1 mi |
Naval Hospital Medical Center | San Diego, CA | 21.4 GWh | 5.7 mi |
PFMG Solar Grossmont Helix LLC | La Mesa, CA | 2.0 GWh | 2.7 mi |
San Diego Community College | San Diego, CA | 6.5 GWh | 6 mi |
SDCCD - Miramar | San Diego, CA | 1.5 GWh | 9.3 mi |
Sycamore Energy LLC | Santee, CA | 23.2 GWh | 6 mi |
University of San Diego | San Diego, CA | 6.2 GWh | 7.1 mi |