Sage Draw Wind
789 FM 212, Wilson, TX 79381Plant Summary Information
Sage Draw Wind is ranked #38 out of 1,345 wind farms nationwide in terms of total annual net electricity generation.
Sage Draw Wind generated 256.8 GWh during the 3-month period between July 2024 to October 2024.
Plant Name | Sage Draw Wind |
---|---|
Utility Name | Sage Draw Wind, LLC |
Location | Lynn County, TX |
Initial Operation Date | August 2021 |
Last Update | Oct 2024 |
Annual Generation | 1.2 TWh |
Annual Consumption | 4.2 M MMBtu |
Ranked #674 out of 11,866 Power Plants Nationwide | |
Ranked #38 out of 1,345 Wind Power Plants Nationwide | |
Ranked #107 out of 758 Texas Power Plants | |
Ranked #18 out of 218 Texas Wind Power Plants | |
Fuel Types | Wind |
Map of Sage Draw Wind
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Sage Draw Wind.
Monthly Net Generation for Sage Draw Wind
Sage Draw Wind Details
Summary Information | |
---|---|
Plant Name | Sage Draw Wind (62620) |
Plant Address | 789 FM 212, Wilson, TX 79381 |
Utility | Sage Draw Wind, LLC (62113) |
Latitude, Longitude | 33.3035, -101.65722 |
Generation Dates on File | Apr 2020 to Oct 2024 |
Initial Operation Date | August 2021 |
Annual Generation | 1.2 TWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | PUCT-49411 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Sharyland Utilities LP (17008) |
Grid Voltage | 345.00 kV |
Energy Storage | No |
Generator SD Details Operating August 2021
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 338.4 MW |
Summer Capacity | 338.4 MW |
Winter Capacity | 338.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | August 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Turbines/Hydrokinetic Buoys | 120 |
Turbine Details | |
Number Of Turbines | 120 |
---|---|
Predominant Turbine Manufacturer | GE |
Predominant Turbine Model Number | 2.82-127 |
Design Wind Speed | 15.7 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 292 |
Sage Draw Wind Plant Owners
Owner Name | Address | Ownership | |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#28 | Jordan Creek Wind Farm, LLC | Judyville, IN | 1.2 TWh |
#29 | Santa Rita Wind Energy | Big Lake, TX | 1.2 TWh |
#30 | Thunderhead Wind Energy LLC | Boone, NE | 1.2 TWh |
#31 | High Lonesome Wind Power, LLC Hybrid | Rankin, TX | 1.2 TWh |
#32 | Red Cloud Wind LLC | Corona, NM | 1.2 TWh |
#33 | Mesquite Star | Roscoe, TX | 1.2 TWh |
#34 | Stephens Ranch Wind Energy LLC | O'Donnell, TX | 1.2 TWh |
#35 | Foard City Wind | Crowell, TX | 1.2 TWh |
#36 | Ranchero Wind Farm LLC | Iraan, TX | 1.2 TWh |
#37 | Santa Rita East | Barnhart, TX | 1.2 TWh |
#39 | Azure Sky Wind Project, LLC Hybrid | Throckmorton, TX | 1.2 TWh |
#40 | Western Plains Wind Farm | Spearville, KS | 1.1 TWh |
#41 | Arbor Hill Wind Farm | Greenfield, IA | 1.1 TWh |
#42 | Flat Ridge 2 Wind Energy LLC | Zenda, KS | 1.1 TWh |
#43 | Tahoka Wind | Tahoka, TX | 1.1 TWh |
#44 | Upland Prairie | Spencer, IA | 1.1 TWh |
#45 | Soldier Creek Wind | Corning, KS | 1.1 TWh |
#46 | Bethel Wind Farm LLC | Dimmitt, TX | 1.1 TWh |
#47 | 25 Mile Creek | Gage, OK | 1.1 TWh |
#48 | Solomon Forks Wind Project, LLC | Colby, KS | 1.1 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Sage Draw Wind.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
BESSP1, LLC. | Shallowater, TX | 1.2 GWh | 32.6 mi |
Brandon Station | Lubbock, TX | 21.7 GWh | 23.5 mi |
Brazos Wind Farm | Fluvanna, TX | 82.9 GWh | 38.4 mi |
Bull Creek Wind | O'Donnell, TX | 269.0 GWh | 26.3 mi |
ENGIE Long Draw Solar LLC | Gail, TX | 532.6 GWh | 38.9 mi |
Fluvanna | Fluvanna, TX | 526.8 GWh | 39.3 mi |
GE-Lubbock | Lubbock, TX | 24.3 GWh | 30.4 mi |
Gopher Creek Wind Farm | Fluvanna, TX | 573.7 GWh | 39.4 mi |
J Robert Massengale | Lubock, TX | 48.1 GWh | 23.3 mi |
Jones | Lubbock, TX | 2.4 TWh | 15.9 mi |
Juno Solar Project | Lamesa, TX | 795.9 GWh | 39.8 mi |
Lorenzo Wind | Lorenzo, TX | 356.3 GWh | 28.4 mi |
Pleasant Hill Wind Energy Project | Lorenzo, TX | 32.0 GWh | 31.7 mi |
Post Wind Farm LP | Fluvanna, TX | 311.7 GWh | 36.4 mi |
Ralls Wind Farm | Ralls, TX | 11.0 GWh | 29.1 mi |
Stephens Ranch Wind Energy LLC | O'Donnell, TX | 1.2 TWh | 26.1 mi |
Tahoka Wind | Tahoka, TX | 1.1 TWh | 10.6 mi |
Texas Solar Nova 1 | Spur, TX | 689.0 GWh | 39 mi |
Texas Solar Nova 2 | Spur, TX | 423.2 GWh | 39 mi |
Ty Cooke | Lubbock, TX | 3.7 GWh | 16.9 mi |