Rubart
14255 East U.S. 160 Highway, Ulysses, KS 67880Plant Summary Information
Rubart is ranked #14 out of 58 natural gas power plants in Kansas in terms of total annual net electricity generation.
Rubart is comprised of 12 generators and generated 16.4 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Rubart |
---|---|
Utility Name | Sunflower Electric Power Corp |
Location | Grant County, KS |
Initial Operation Date | September 2014 |
Last Update | Dec 2023 |
Annual Generation | 70.3 GWh |
Annual Consumption | 773.9 k MMBtu |
Ranked #3,551 out of 11,852 Power Plants Nationwide | |
Ranked #992 out of 2,254 Natural Gas Power Plants Nationwide | |
Ranked #63 out of 152 Kansas Power Plants | |
Ranked #14 out of 58 Kansas Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Rubart
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Rubart.
Monthly Net Generation for Rubart
Rubart Details
Summary Information | |
---|---|
Plant Name | Rubart (58255) |
Plant Address | 14255 East U.S. 160 Highway, Ulysses, KS 67880 |
Utility | Sunflower Electric Power Corp (18315) |
Latitude, Longitude | 37.55861, -101.09944 |
Generation Dates on File | Sep 2014 to Dec 2023 |
Initial Operation Date | September 2014 |
Annual Generation | 70.3 GWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Wells |
Ash Impoundment | No |
Transmission / Distribution Owner | Sunflower Electric Power Corp (18315) |
Grid Voltage | 115.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | SOUTHERN STAR CENTRAL GAS PIPELINE |
Natural Gas Storage | No |
Generator 01 Details Operating September 2014
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | SECIRUBART |
RTO ISO Location Designation For Reporting Wholesale Sales Data | SECIRUBART |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.8 MW |
Winter Capacity | 8.8 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2014 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 02 Details Operating September 2014
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | SECIRUBART |
RTO ISO Location Designation For Reporting Wholesale Sales Data | SECIRUBART |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.9 MW |
Winter Capacity | 8.9 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2014 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 03 Details Operating September 2014
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | SECIRUBART |
RTO ISO Location Designation For Reporting Wholesale Sales Data | SECIRUBART |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.7 MW |
Winter Capacity | 8.7 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2014 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 04 Details Operating September 2014
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | SECIRUBART |
RTO ISO Location Designation For Reporting Wholesale Sales Data | SECIRUBART |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 9 MW |
Winter Capacity | 9 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2014 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 05 Details Operating September 2014
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | SECIRUBART |
RTO ISO Location Designation For Reporting Wholesale Sales Data | SECIRUBART |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.6 MW |
Winter Capacity | 8.6 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2014 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 06 Details Operating September 2014
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | SECIRUBART |
RTO ISO Location Designation For Reporting Wholesale Sales Data | SECIRUBART |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.8 MW |
Winter Capacity | 8.8 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2014 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 07 Details Operating September 2014
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | SECIRUBART2 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | SECIRUBART2 |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.8 MW |
Winter Capacity | 8.8 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2014 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 08 Details Operating September 2014
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | SECIRUBART2 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | SECIRUBART2 |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.9 MW |
Winter Capacity | 8.9 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2014 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 09 Details Operating September 2014
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | SECIRUBART2 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | SECIRUBART2 |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 8.9 MW |
Winter Capacity | 8.9 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2014 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 10 Details Operating September 2014
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | SECIRUBART2 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | SECIRUBART2 |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 9 MW |
Winter Capacity | 9 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2014 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 11 Details Operating September 2014
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | SECIRUBART2 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | SECIRUBART2 |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 9 MW |
Winter Capacity | 9 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2014 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 12 Details Operating September 2014
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | SECIRUBART2 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | SECIRUBART2 |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 9 MW |
Winter Capacity | 9 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2014 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Rubart Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#982 | Georgia-Pacific Corp - Nekoosa Mill | Nekoosa, WI | 177.0 GWh |
#983 | WestRock (TX) | Evadale, TX | 406.8 GWh |
#984 | Boise Cascade International Falls | International Falls, MN | 336.6 GWh |
#985 | Corpus Christi | Corpus Christi, TX | 72.9 GWh |
#986 | UMCP CHP Plant | College Park, MD | 75.5 GWh |
#987 | Summit Lake | Creston, IA | 72.1 GWh |
#988 | Berry NMW Cogens | Bakersfield, CA | 71.7 GWh |
#989 | Western Michigan University Power Plant | Kalamazoo, MI | 71.3 GWh |
#990 | Whiting Refinery | Whiting, IN | 445.2 GWh |
#991 | Port Comfort Power LLC | Point Comfort, TX | 70.8 GWh |
#993 | Dan E Karn | Essexville, MI | 75.6 GWh |
#994 | Berkshire Power | Agawam, MA | 70.1 GWh |
#995 | Anheuser-Busch Jacksonville | Jacksonville, FL | 69.5 GWh |
#996 | Parnassus Central Utility Plant | San Francisco, CA | 69.2 GWh |
#997 | Pfizer Groton Plant | Groton, CT | 70.3 GWh |
#998 | Ormond Beach | Oxnard, CA | 68.8 GWh |
#999 | New York University Central Plant | New York, NY | 74.2 GWh |
#1000 | Nippon Dynawave Packaging Longview WA | Longview, WA | 293.2 GWh |
#1001 | Greenville Electric Generating Station | Greenville, OH | 68.5 GWh |
#1002 | Beaver Dam | Canton Township, PA | 68.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Rubart.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Arkalon Ethanol LLC | Liberal, KS | 3.2 GWh | 35 mi |
Bonanza BioEnergy LLC | Garden City, KS | 5.7 GWh | 31.2 mi |
Buffalo Dunes Wind Project | Satanta, KS | 861.3 GWh | 4.5 mi |
Cimarron Bend III | Minneola, KS | 551.8 GWh | 62 mi |
Cimarron Bend Wind Project I, LLC | Minneola, KS | 852.6 GWh | 62.4 mi |
Cimarron Bend Wind Project II, LLC | Minneola, KS | 817.7 GWh | 62.4 mi |
Cimarron River | Liberal, KS | 25.8 GWh | 33.1 mi |
Cimarron Wind Energy LLC | Cimmaron, KS | 482.0 GWh | 49.8 mi |
Cimarron Windpower II | Cimarron, KS | 475.5 GWh | 46.3 mi |
Ensign Wind LLC | Montezuma, KS | 483.0 GWh | 45.1 mi |
Garden City | Garden City, KS | 79.5 GWh | 30.5 mi |
Gray County Wind Energy | Montezuma, KS | 304.3 GWh | 39.7 mi |
Holcomb | Holcomb, KS | 1.2 TWh | 26.6 mi |
Holly | Holly, CO | 20.0 MWh | 62.5 mi |
Hugoton 2 | Hugoton, KS | 18.6 MWh | 30.3 mi |
Iron Star Wind Project | Dodge City, KS | 1.2 TWh | 61.5 mi |
Jameson Energy Center | Garden City, KS | 1.1 GWh | 31.1 mi |
Johnson | Johnson, KS | 35.0 MWh | 35.7 mi |
Johnson Corner Solar 1 | Johnson City, KS | 39.8 GWh | 38.3 mi |
Meade | Meade, KS | 105.0 MWh | 46.1 mi |