RS Cogen
1300 PPG Drive, Lake Charles, LA 70602Plant Summary Information
RS Cogen is ranked #17 out of 77 power plants in Louisiana in terms of total annual net electricity generation.
RS Cogen is comprised of 3 generators and generated 392.7 GWh during the 3-month period between May 2024 to August 2024.
Plant Name | RS Cogen |
---|---|
Utility Name | Westlake 2 US LLC |
Location | Calcasieu Parish, LA |
Initial Operation Date | December 2002 |
Last Update | Aug 2024 |
Annual Generation | 2.4 TWh |
Annual Consumption | 28.4 M MMBtu |
Ranked #468 out of 11,835 Power Plants Nationwide | |
Ranked #287 out of 2,253 Natural Gas Power Plants Nationwide | |
Ranked #17 out of 77 Louisiana Power Plants | |
Ranked #12 out of 54 Louisiana Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Previous Operator |
Eagle 2 US LLC (2013 to 2021) Westlake 2 US LLC (2022 to 2023) |
Map of RS Cogen
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for RS Cogen.
Monthly Net Generation for RS Cogen
RS Cogen Details
Summary Information | |
---|---|
Plant Name | RS Cogen (55117) |
Plant Address | 1300 PPG Drive, Lake Charles, LA 70602 |
Utility | Westlake 2 US LLC (14306) |
Latitude, Longitude | 30.221, -93.2826 |
Generation Dates on File | Jan 2003 to Aug 2024 |
Initial Operation Date | December 2002 |
Annual Generation | 2.4 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | Yes |
FERC Cogeneration Docket Number | 00-32-000 |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
NAICS Code | Chemical Manufacturing (325) |
Sector | Industrial CHP (7) |
Water Source | Sabine River |
Ash Impoundment | No |
Transmission / Distribution Owner | Entergy Gulf States - LA LLC (55936) LA |
Grid Voltage | 230.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name |
TARGA MIDSTREAM SERVICES LLC GULF SOUTH PIPELINE COMPANY LP VARIBUS LLC |
Natural Gas Storage | No |
Generator RS-4 Details Operating December 2002
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CC1 |
Ownership | Single Owner |
Duct Burners | No |
RTO ISO LMP Node Designation | EES.AXIALL |
RTO ISO Location Designation For Reporting Wholesale Sales Data | EES.AXIALL |
Nameplate Capacity | 103 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 80 MW |
Winter Capacity | 80 MW |
Minimum Load | 20 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 2002 |
Combined Heat & Power | Yes |
Sector Name | Industrial CHP (7) |
Topping Or Bottoming | B |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | OVER |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator RS-5 Details Operating December 2002
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | EES.AXIALL |
RTO ISO Location Designation For Reporting Wholesale Sales Data | EES.AXIALL |
Nameplate Capacity | 195 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 167.7 MW |
Winter Capacity | 183.3 MW |
Minimum Load | 100 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 2002 |
Combined Heat & Power | Yes |
Sector Name | Industrial CHP (7) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator RS-6 Details Operating December 2002
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | EES.AXIALL |
RTO ISO Location Designation For Reporting Wholesale Sales Data | EES.AXIALL |
Nameplate Capacity | 195 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 167.7 MW |
Winter Capacity | 183.3 MW |
Minimum Load | 100 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 2002 |
Combined Heat & Power | Yes |
Sector Name | Industrial CHP (7) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
RS Cogen Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#277 | Jack Watson | Gulfport, MS | 2.5 TWh |
#278 | McClain Energy Facility | Newcastle, OK | 2.5 TWh |
#279 | Haynes | Long Beach, CA | 2.5 TWh |
#280 | C D McIntosh Jr | Lakeland, FL | 2.5 TWh |
#281 | Magic Valley Generating Station | Edinburg, TX | 2.4 TWh |
#282 | Chehalis Generating Facility | Chehalis, WA | 2.4 TWh |
#283 | Otay Mesa Generating Project | San Diego, CA | 2.4 TWh |
#284 | Sabine River Operations | Orange, TX | 2.4 TWh |
#285 | Bergen Generating Station | Ridgefield, NJ | 2.4 TWh |
#286 | Harry Allen | Las Vegas, NV | 2.4 TWh |
#288 | Apex Generating Station | Las Vegas, NV | 2.4 TWh |
#289 | Coyote Springs II | Boardman, OR | 2.4 TWh |
#290 | Pleasants Energy LLC | St Mary's, WV | 2.3 TWh |
#291 | Tenaska Gateway Generating Station | Mt. Enterprise, TX | 2.3 TWh |
#292 | Dogwood Energy Facility | Pleasant Hill, MO | 2.3 TWh |
#293 | Chesterfield | Chester, VA | 2.3 TWh |
#294 | Elk Hills Power LLC | Tupman, CA | 2.3 TWh |
#295 | La Paloma Generating Plant | McKittrick, CA | 2.3 TWh |
#296 | Quail Run Energy Center | Odessa, TX | 2.3 TWh |
#297 | Rolling Hills Generating | Wilkesville, OH | 2.3 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding RS Cogen.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Agrilectric Power Partners Ltd | Lake Charles, LA | 84.7 GWh | 9.4 mi |
Bayou Cove Peaking Power | Jennings, LA | 107.8 GWh | 41 mi |
Calcasieu | Sulphur, LA | 104.4 GWh | 5.6 mi |
CITGO Refinery Powerhouse | Sulphur, LA | 174.4 GWh | 3.6 mi |
Cottonwood Energy Project | Deweyville, TX | 5.6 TWh | 27.1 mi |
DeRidder Mill | DeRidder, LA | 389.0 GWh | 44.5 mi |
Elizabeth Solar Plant | Pitkin, LA | 29.4 GWh | 45.3 mi |
International Paper - Orange | Orange, TX | 238.6 GWh | 27.4 mi |
JCO Oxides Olefins Plant | Port Neeches, TX | 531.3 GWh | 42.6 mi |
Lake Charles Plant | Sulphur, LA | 154.8 GWh | 5.9 mi |
Lake Charles Polymers | Westlake, LA | 192.6 GWh | 2.9 mi |
Lake Charles Power | West Lake, LA | 5.9 TWh | 3.5 mi |
NAFTA Region Olefins Complex Cogen Fac | Port Arthur, TX | 582.0 GWh | 40.4 mi |
Port Arthur Texas Refinery | Port Arthur, TX | 234.8 GWh | 40.5 mi |
PPG Plant C Caustic | Lake Charles, LA | 6.0 GWh | 0.8 mi |
PPG Powerhouse C | Lake Charles, LA | 1.3 TWh | 0.8 mi |
PPG Riverside | Lake Charles, LA | 98.2 GWh | 0.1 mi |
R S Nelson | Westlake, LA | 1.3 TWh | 4.4 mi |
Sabine | Orange, TX | 3.4 TWh | 38.1 mi |
Sabine River Operations | Orange, TX | 2.4 TWh | 30.6 mi |