Rhinelander Mill
515 W Davenport Street, Rhinelander, WI 54501Plant Summary Information
Rhinelander Mill is ranked #57 out of 66 hydroelectric power plants in Wisconsin in terms of total annual net electricity generation.
Rhinelander Mill is comprised of 5 generators and generated 838.0 MWh during the 3-month period between June 2024 to September 2024.
Plant Name | Rhinelander Mill |
---|---|
Utility Name | Ahlstrom-Munksjo |
Location | Oneida County, WI |
Initial Operation Date | December 1917 |
Last Update | Sep 2024 |
Annual Generation | 4.2 GWh |
Annual Consumption | 2.3 M MMBtu |
Ranked #8,009 out of 11,852 Power Plants Nationwide | |
Ranked #1,201 out of 1,371 Water Power Plants Nationwide | |
Ranked #154 out of 216 Wisconsin Power Plants | |
Ranked #57 out of 66 Wisconsin Water Power Plants | |
Fuel Types | Water |
Previous Operator |
Expera Specialty Solutions (2013 to 2017) Ahlstrom-Munksjo (2018 to 2023) |
Map of Rhinelander Mill
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Rhinelander Mill.
Monthly Net Generation for Rhinelander Mill
Rhinelander Mill Details
Summary Information | |
---|---|
Plant Name | Rhinelander Mill (50933) |
Plant Address | 515 W Davenport Street, Rhinelander, WI 54501 |
Utility | Ahlstrom-Munksjo (61707) |
Latitude, Longitude | 45.6394, -89.4205 |
Generation Dates on File | Jan 2001 to Sep 2024 |
Initial Operation Date | December 1917 |
Annual Generation | 4.2 GWh |
Fuel Types | Water |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | MRO |
Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
NAICS Code | (322122) |
Sector | Industrial CHP (7) |
Water Source | Wisconsin River |
Ash Impoundment | No |
Transmission / Distribution Owner | Wisconsin Public Service Corp (20860) WI |
Grid Voltage | 115.00 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | WISCONSIN PUB SVC CORP |
Pipeline Name |
ANR PIPELINE COMPANY ANR PIPELINE COMPANY |
Natural Gas Storage | No |
Generator HYD1 Details Operating December 1917
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 0.5 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.5 MW |
Winter Capacity | 0.5 MW |
Minimum Load | 0.3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 1917 |
Combined Heat & Power | No |
Sector Name | Industrial CHP (7) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Generator HYD2 Details Operating December 1917
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 0.5 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.5 MW |
Winter Capacity | 0.5 MW |
Minimum Load | 0.3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 1917 |
Combined Heat & Power | No |
Sector Name | Industrial CHP (7) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Generator HYD3 Details Operating December 1926
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 1 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1 MW |
Winter Capacity | 1 MW |
Minimum Load | 0.6 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 1926 |
Combined Heat & Power | No |
Sector Name | Industrial CHP (7) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Generator GEN5 Details Standby February 1951
Technology | Natural Gas Steam Turbine |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 4 MW |
Winter Capacity | 7 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Standby |
Synchronized To Transmission Grid | No |
First Operation Date | February 1951 |
Combined Heat & Power | Yes |
---|---|
Sector Name | Industrial CHP (7) |
Topping Or Bottoming | B |
Energy Source | Natural Gas / Distillate Fuel Oil |
Startup Source | Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | Yes |
---|---|
Net Summer Capacity With Natural Gas | 4 MW |
Net Winter Capacity With Natural Gas | 7 MW |
Net Summer Capacity With Oil | 4 MW |
Net Winter Capacity With Oil | 7 MW |
Time To Switch From Gas To Oil | 6H |
Time To Switch From Oil To Gas | 6H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Air Permit Limits | Yes |
Generator GEN6 Details Operating July 1958
Technology | Conventional Steam Coal |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
Nameplate Capacity | 9.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 6.3 MW |
Winter Capacity | 8.5 MW |
Minimum Load | 3.8 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 1958 |
Combined Heat & Power | Yes |
Sector Name | Industrial CHP (7) |
---|---|
Topping Or Bottoming | B |
Energy Source | Bituminous Coal |
Startup Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Other Combustion Technology | Yes |
Subcritical Technology | Yes |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Rhinelander Mill Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1191 | Salisbury | Salisbury, VT | 4.5 GWh |
#1192 | West Danville 15 | Danville, VT | 4.5 GWh |
#1193 | Little Cottonwood | Sandy, UT | 4.4 GWh |
#1194 | Piedmont Hydro Power Project | Piedmont, SC | 4.4 GWh |
#1195 | Oconto Falls Lower | Oconto Falls, WI | 4.4 GWh |
#1196 | Robert D Willis | Jasper, TX | 4.4 GWh |
#1197 | Pine View Dam | Ogden, UT | 4.4 GWh |
#1198 | Lochmere Hydroelectric Plant | Tilton, NH | 4.3 GWh |
#1199 | Mile 28 Water Power Project | Eden, ID | 4.3 GWh |
#1200 | Cornell Hydro | Ithaca, NY | 4.3 GWh |
#1202 | Dam No. 4 Hydro Station | Shepherdstown, WV | 4.2 GWh |
#1203 | Lacomb Irrigation District | Lebanon, OR | 4.2 GWh |
#1204 | Potato Rapids | Town of Porterfield, WI | 4.2 GWh |
#1205 | Corona | Corona, CA | 4.1 GWh |
#1206 | Lower Middlebury | Middlebury Lower, VT | 4.1 GWh |
#1207 | Smith (VT) | Bradford, VT | 4.0 GWh |
#1208 | Rollinsford | Rollinsford, NH | 4.0 GWh |
#1209 | China Mill Hydro | Allenstown, NH | 4.0 GWh |
#1210 | Ogdensburg | Ogdensburg, NY | 4.0 GWh |
#1211 | East Portal Generator | Chatsworth, CA | 4.0 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Rhinelander Mill.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Alexander | Merrill, WI | 19.0 GWh | 35.2 mi |
Caldron Falls | Town of Stephenson, WI | 12.5 GWh | 60.8 mi |
Crystal Falls | Crystal Falls, MI | 5.4 GWh | 61.4 mi |
Domtar Paper Company Rothschild | Rothschild, WI | 3.1 GWh | 53 mi |
Flambeau Crowley Rapids Project | Park Falls, WI | 3.5 GWh | 58.3 mi |
Flambeau Lower Project | Park Falls, WI | 2.8 GWh | 53 mi |
Flambeau Solar Partners | Phillips, WI | 4.5 GWh | 51.1 mi |
Grandfather Falls | Irma, WI | 76.4 GWh | 29.4 mi |
Hat Rapids | Rhinelander, WI | 5.9 GWh | 5.5 mi |
Hodag Solar | Rhinelander, WI | 13.2 GWh | 2.2 mi |
Medford DPC Solar | Medford, WI | 3.4 GWh | 56.7 mi |
Merrill | Merrill, WI | 8.2 GWh | 34.3 mi |
Mosinee Mill | Mosinee, WI | 120.1 GWh | 60.3 mi |
Packaging of America Tomahawk Mill | Tomahawk, WI | 112.9 GWh | 20.4 mi |
Pine | Florence, WI | 12.1 GWh | 58 mi |
Rothschild Biomass Cogen Facility | Rothschild, WI | 143.2 GWh | 52.9 mi |
Tomahawk | Tomahawk, WI | 6.5 GWh | 20.3 mi |
Wausau | Wausau, WI | 22.8 GWh | 48.3 mi |
Weston | Rothschild, WI | 4.0 TWh | 55 mi |
Weston RICE | Kronenwetter, WI | 48.9 GWh | 55.3 mi |