Redstone Arsenal Hybrid
Redstone Arsenal Base, Huntsville, AL 35808Plant Summary Information
Redstone Arsenal Hybrid is ranked #8 out of 10 solar farms in Alabama in terms of total annual net electricity generation.
Redstone Arsenal Hybrid generated 2.5 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Redstone Arsenal Hybrid |
---|---|
Utility Name | MN8 Energy LLC |
Location | Madison County, AL |
Initial Operation Date | December 2017 |
Last Update | Dec 2023 |
Annual Generation | 15.5 GWh |
Annual Consumption | 55.6 k MMBtu |
Ranked #5,375 out of 11,852 Power Plants Nationwide | |
Ranked #1,295 out of 5,655 Solar Power Plants Nationwide | |
Ranked #68 out of 75 Alabama Power Plants | |
Ranked #8 out of 10 Alabama Solar Power Plants | |
Fuel Types | Solar |
Previous Operators |
Redstone Solar I, LLC (2017 to 2019) Goldman Sachs Renewable Power Group (2020 to 2020) Goldman Sachs Renewable Power LLC (2021 to 2021) MN8 Energy LLC (2022 to 2023) |
Map of Redstone Arsenal Hybrid
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Redstone Arsenal Hybrid.
Monthly Net Generation for Redstone Arsenal Hybrid
Redstone Arsenal Hybrid Details
Summary Information | |
---|---|
Plant Name | Redstone Arsenal Hybrid (61901) |
Plant Address | Redstone Arsenal Base, Huntsville, AL 35808 |
Utility | MN8 Energy LLC (61944) |
Latitude, Longitude | 34.61099, -86.61155 |
Generation Dates on File | Dec 2017 to Dec 2023 |
Initial Operation Date | December 2017 |
Annual Generation | 15.5 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | 18-326 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Tennessee Valley Authority (TVA) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Tennessee Valley Authority (18642) AL |
Grid Voltage | 46.00 kV |
Energy Storage | Yes |
Generator BA Details Operating December 2017
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
Nameplate Capacity | 1 MW |
Summer Capacity | 1 MW |
Winter Capacity | 1 MW |
Minimum Load | 1 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2017 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Electricity used for energy storage |
Time From Cold Shutdown To Full Load | 10M |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 2 |
---|---|
Maximum Charge Rate | 0.5 MW |
Maximum Discharge Rate | 0.5 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 1 |
Storage Enclosure Type | CS |
Arbitrage | Yes |
Excess Wind And Solar Generation | P |
Ac Coupled | Yes |
Direct Support Of Another Unit | Yes |
Direct Support Plant Id | 61901 |
Direct Support Gen Id | REDST |
Support T D Asset | No |
Generator REDST Details Operating December 2017
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 10 MW |
Summer Capacity | 7.2 MW |
Winter Capacity | 4.2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 2017 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Multiple Fuels | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
DC Net Capacity | 12.5 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Redstone Arsenal Hybrid Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1285 | DSM Nutritional Products Solar | Township of White, NJ | 15.9 GWh |
#1286 | Pennsauken Brownfield Solar | Pennsauken, NJ | 15.8 GWh |
#1287 | Berry Plastics Solar | Phillipsburg, NJ | 15.8 GWh |
#1288 | Camp Ripley Solar | Little Falls, MN | 15.8 GWh |
#1289 | GD Hopkinton Main I, LLC | Hopkinton, RI | 15.8 GWh |
#1290 | Brightwood Solar, LLC | Sandy, OR | 15.8 GWh |
#1291 | Leavenworth Greenworks LLC | Calverton, NY | 15.7 GWh |
#1292 | Pittsfield Solar LLC | Pittsfield, ME | 15.7 GWh |
#1293 | Blackville Solar Farm, LLC | Blackville, SC | 15.6 GWh |
#1294 | Apple Campus 2 PV | Cupertino, CA | 15.6 GWh |
#1296 | E W Brown | Harrodsburg, KY | 1.4 TWh |
#1297 | Sandoval Solar Energy Center | Rio Rancho, NM | 15.6 GWh |
#1298 | SR Rattlesnake | Platteville, CO | 15.6 GWh |
#1299 | Bishopville Solar II, LLC | Bishopville, SC | 15.5 GWh |
#1300 | West Plains Solar I | West Plains, MO | 15.5 GWh |
#1301 | Newman Solar | El Paso, TX | 15.5 GWh |
#1302 | Hermsdorf Solar | Madison, WI | 15.4 GWh |
#1303 | NJ Oak Solar Plant | Bridgetown, NJ | 15.4 GWh |
#1304 | Milford Solar Farm | Milford, DE | 15.2 GWh |
#1305 | Jacksonville Solar | Jacksonville, FL | 15.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Redstone Arsenal Hybrid.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
ABC Coke | Tarrant, AL | 83.0 MWh | 71.7 mi |
Browns Ferry | Decatur, AL | 29.7 TWh | 29.5 mi |
Colbert | Tuscumbia, AL | 78.7 GWh | 70.9 mi |
Cumblerland Land Holdings, LLC | Elkmont, AL | 28.6 GWh | 27.6 mi |
Decatur Energy Center | Decatur, AL | 3.3 TWh | 23.3 mi |
Decatur-Morgan Co LFG Recovery Project | Trinity, AL | 10.7 GWh | 27.9 mi |
Elora Solar | Elora, TN | 304.6 GWh | 34.6 mi |
Guntersville | Guntersville, AL | 453.4 GWh | 18 mi |
H Neely Henry Dam | Ohatchee, AL | 196.7 GWh | 65.4 mi |
Lewis Smith Dam | Jasper, AL | 233.4 GWh | 54.3 mi |
Morgan Energy Center | Decatur, AL | 4.5 TWh | 25.8 mi |
Nickajack | New Hope, TN | 509.6 GWh | 62.3 mi |
River Bend Solar, LLC | Florence, AL | 148.7 GWh | 71.5 mi |
Sand Valley Power Station | Collinsville, AL | 30.6 GWh | 46.3 mi |
SR Bell Buckle | Shelbyville, TN | 63.0 GWh | 66.8 mi |
TAI Huntsville Solar Hybrid | Huntsville, AL | 18.4 GWh | 15.1 mi |
Tims Ford | Winchester, TN | 41.7 GWh | 44.7 mi |
Weiss Dam | Leesburg, AL | 183.2 GWh | 57.5 mi |
Wheeler Dam | Town Creek, AL | 1.1 TWh | 45.8 mi |
Wilson Dam | Muscle Shoals, AL | 2.2 TWh | 59 mi |