Red Horse III
5529 N. Muleshoe Rd, Wilcox, AZ 85643Plant Summary Information
Red Horse III is ranked #37 out of 103 solar farms in Arizona in terms of total annual net electricity generation.
Red Horse III generated 7.9 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Red Horse III |
---|---|
Utility Name | Red Horse III |
Location | Cochise County, AZ |
Initial Operation Date | July 2016 |
Last Update | Dec 2023 |
Annual Generation | 48.1 GWh |
Annual Consumption | 175.6 k MMBtu |
Ranked #3,908 out of 11,852 Power Plants Nationwide | |
Ranked #793 out of 5,655 Solar Power Plants Nationwide | |
Ranked #81 out of 156 Arizona Power Plants | |
Ranked #37 out of 103 Arizona Solar Power Plants | |
Fuel Types | Solar |
Map of Red Horse III
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Red Horse III.
Monthly Net Generation for Red Horse III
Red Horse III Details
Summary Information | |
---|---|
Plant Name | Red Horse III (60285) |
Plant Address | 5529 N. Muleshoe Rd, Wilcox, AZ 85643 |
Utility | Red Horse III (60068) |
Latitude, Longitude | 32.13597, -110.05129 |
Generation Dates on File | Jul 2016 to Dec 2023 |
Initial Operation Date | July 2016 |
Annual Generation | 48.1 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | 16-56-000 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | Tucson Electric Power Company (TEPC) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Tucson Electric Power Co (24211) AZ |
Grid Voltage | 345.00 kV |
Energy Storage | No |
Generator RH3 Details Operating July 2016
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 30 MW |
Summer Capacity | 30 MW |
Winter Capacity | 30 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 2016 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Multiple Fuels | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 90 |
DC Net Capacity | 37.7 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Red Horse III Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#783 | White River Solar 2 | Alpaugh, CA | 49.3 GWh |
#784 | Corcoran Solar 3 | Corcoran, CA | 49.2 GWh |
#785 | Fence Post Solar Hybrid Project, LLC | Corsicana, TX | 49.1 GWh |
#786 | RE Rosamond One LLC | Rosamond, CA | 49.1 GWh |
#787 | Whitehouse Solar Farm | Louisa, VA | 49.0 GWh |
#788 | Picture Rocks Solar, LLC | Marana, AZ | 49.0 GWh |
#789 | Midway Solar Farm III | Calipatria, CA | 48.9 GWh |
#790 | Simon Solar Farm LLC | Social Circle, GA | 48.6 GWh |
#791 | Wonderful Lost Hills | Lost Hills, CA | 48.3 GWh |
#792 | Shafter Solar LLC | Bakersfield, CA | 48.2 GWh |
#794 | Rio Bravo Solar II LLC | McKittrick, CA | 48.0 GWh |
#795 | RE Garland A | Rosamond, CA | 47.9 GWh |
#796 | Vega Solar | Los Banos, CA | 47.7 GWh |
#797 | CED Ducor 1 | Ducor, CA | 47.7 GWh |
#798 | Long Island Solar Farm LLC | Upton, NY | 47.7 GWh |
#799 | NextEra Westside PV | Five Points, CA | 47.7 GWh |
#800 | Rawhide Prairie Solar Hybrid | Wellington, CO | 47.3 GWh |
#801 | Shoreham Solar Commons | Shoreham, NY | 47.4 GWh |
#802 | Bayshore Solar A, LLC | Lancaster, CA | 47.4 GWh |
#803 | SR Odom | Moultrie, GA | 47.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Red Horse III.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Actus Lend Lease DMAFB | Tucson, AZ | 3.0 GWh | 47.6 mi |
Amazon TUS2 | Tucson, AZ | 5.3 GWh | 46.1 mi |
Apache Solar 1 | Cochise, AZ | 55.3 GWh | 10.5 mi |
Apache Station | Cochise, AZ | 2.2 TWh | 10.6 mi |
Cogenra - TEP | Tucson, AZ | 2.1 GWh | 44.7 mi |
Davis Monthan AFB (AZ) West Airfield | Tucson, AZ | 31.5 GWh | 49.7 mi |
Fort Huachuca Solar PV Project | Sierra Vista, AZ | 37.2 GWh | 43.8 mi |
FRB Solar Farm | Tucson, AZ | 4.1 GWh | 45.3 mi |
Gato Montes Solar, LLC | Tucson, AZ | 6.2 GWh | 45 mi |
Iron Horse Battery Storage Hybrid | Tucson, AZ | 4.6 GWh | 45 mi |
Pima Community College | Tucson, AZ | 2.4 GWh | 44.8 mi |
Prairie Fire | Tucson, AZ | 7.5 GWh | 45 mi |
Raptor Ridge | Tucson, AZ | 33.5 GWh | 48.4 mi |
Red Horse 2 | Willcox, AZ | 200.4 GWh | 10.6 mi |
SR McNeal | McNeal, AZ | 44.2 GWh | 45.1 mi |
Sulphur Springs | Cochise, AZ | 53.3 GWh | 9.2 mi |
Tech Park Solar | Tucson, AZ | 13.7 GWh | 44.8 mi |
UASTP I | Tucson, AZ | 403.0 MWh | 44.5 mi |
Valencia Solar | Tucson, AZ | 26.2 GWh | 47.7 mi |
Wilmot Energy Center LLC | Tucson, AZ | 241.7 GWh | 49.7 mi |