Raymond Wind Farm, LLC
TBD, Lyford, TX 78569Plant Summary Information
Raymond Wind Farm, LLC is ranked #73 out of 218 wind farms in Texas in terms of total annual net electricity generation.
Raymond Wind Farm, LLC generated 125.7 GWh during the 3-month period between May 2024 to August 2024.
Plant Name | Raymond Wind Farm, LLC |
---|---|
Utility Name | RWE Renewables Americas, LLC |
Location | Willacy County, TX |
Initial Operation Date | June 2021 |
Last Update | Aug 2024 |
Annual Generation | 615.2 GWh |
Annual Consumption | 2.3 M MMBtu |
Ranked #1,063 out of 11,835 Power Plants Nationwide | |
Ranked #239 out of 1,343 Wind Power Plants Nationwide | |
Ranked #191 out of 749 Texas Power Plants | |
Ranked #73 out of 218 Texas Wind Power Plants | |
Fuel Types | Wind |
Previous Operators |
E ON Climate Renewables N America LLC (2018 to 2018) RWE Renewables Americas LLC (2019 to 2021) RWE Renewables Americas, LLC (2022 to 2023) |
Map of Raymond Wind Farm, LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Raymond Wind Farm, LLC.
Monthly Net Generation for Raymond Wind Farm, LLC
Raymond Wind Farm, LLC Details
Summary Information | |
---|---|
Plant Name | Raymond Wind Farm, LLC (62909) |
Plant Address | TBD, Lyford, TX 78569 |
Utility | RWE Renewables Americas, LLC (56215) |
Latitude, Longitude | 26.36415, -97.78044 |
Generation Dates on File | Jun 2021 to Aug 2024 |
Initial Operation Date | June 2021 |
Annual Generation | 615.2 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | AEP Texas Central Company (3278) TX |
Grid Voltage | 345.00 kV |
Energy Storage | No |
Generator ERAYM Details Operating June 2021
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 200.2 MW |
Summer Capacity | 200.2 MW |
Winter Capacity | 200.2 MW |
Minimum Load | 22 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | June 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 91 |
Turbine Details | |
Number Of Turbines | 91 |
---|---|
Predominant Turbine Manufacturer | Vestas |
Predominant Turbine Model Number | V120-2.2 |
Design Wind Speed | 16.8 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 302 |
Raymond Wind Farm, LLC Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#229 | Glacier Sands Wind Power, LLC | Mason City, IL | 629.3 GWh |
#230 | FPL Energy Illinois Wind LLC Hybrid | Shabbona, IL | 629.1 GWh |
#231 | Logans Gap Wind LLC | Comanche, TX | 629.0 GWh |
#232 | Coyote Wind LLC | Snyder, TX | 625.5 GWh |
#233 | Brady II Wind Energy Center | Dickinson, ND | 625.5 GWh |
#234 | Headwaters Wind Farm LLC | Winchester, IN | 622.9 GWh |
#235 | Frontier Windpower II | Blackwell, OK | 621.5 GWh |
#236 | Gopher Creek Wind Farm | Fluvanna, TX | 618.0 GWh |
#237 | Boiling Springs Wind Farm | Woodward, OK | 617.2 GWh |
#238 | Brady Wind Energy Center | Dickinson, ND | 615.5 GWh |
#240 | Route 66 Wind Plant | Panhandle, TX | 614.8 GWh |
#241 | El Algodon Alto Wind Farm, LLC | Mathis, TX | 610.5 GWh |
#242 | Sweetwater Wind 4 LLC | Roscoe, TX | 609.9 GWh |
#243 | Bison 4 Wind Energy Center | New Salem, ND | 608.4 GWh |
#244 | South Plains Wind Phase I | Floydada, TX | 607.1 GWh |
#245 | Heart of Texas Wind Project | Brady, TX | 606.0 GWh |
#246 | Shamrock Wind | TBD, TX | 603.2 GWh |
#247 | NaturEner Rim Rock Energy | Kevin, MT | 601.5 GWh |
#248 | North Bend Wind Project, LLC | Highmore, SD | 599.5 GWh |
#249 | Maple Ridge Wind Farm | Lowville, NY | 599.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Raymond Wind Farm, LLC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Bruennings Breeze Wind Farm | Raymondville, TX | 508.4 GWh | 12.2 mi |
Cameron Wind 1 LLC | Rio Hondo, TX | 346.0 GWh | 22.7 mi |
E. Porte Ct. | Harlingen, TX | 599.0 MWh | 13.9 mi |
Hidalgo Energy Center | Edinburg, TX | 2.1 TWh | 24.5 mi |
La Chalupa, LLC | Rio Hondo, TX | 444.2 GWh | 18.4 mi |
Las Majadas Wind Farm | Santa Monica, TX | 861.0 GWh | 14.6 mi |
Los Vientos Wind 1A | Sebastian, TX | 352.0 GWh | 12.3 mi |
Los Vientos Wind 1B | Sebastian, TX | 182.1 GWh | 7.1 mi |
Magic Valley Generating Station | Edinburg, TX | 2.4 TWh | 25.4 mi |
Magic Valley Wind Farm I LLC | San Perlita, TX | 384.7 GWh | 9.5 mi |
Nebula Solar | La Feria, TX | 255.7 GWh | 19 mi |
Palmas Wind, LLC | Rio Hondo, TX | 324.6 GWh | 18.3 mi |
Red Gate Power Plant | Edinburg, TX | 270.9 GWh | 25.3 mi |
Ridge Rd | Alamo, TX | 684.0 MWh | 23.9 mi |
Rio Grande Valley Sugar Growers | Santa Rosa, TX | 92.0 MWh | 8.4 mi |
Santa Rosa | Santa Rosa, TX | 706.0 MWh | 9.6 mi |
Vancourt Solar Interconnections | La Feria, TX | 88.1 GWh | 19 mi |
Vaquero | Harlingen, TX | 709.0 MWh | 15.6 mi |
WAL5165 | Alamo, TX | 391.0 MWh | 24.6 mi |
West Raymond Wind Farm LLC | Lyford, TX | 709.7 GWh | 13.2 mi |