R W Miller
2217 F.M.Road 3137, Palo Pinto, TX 76484Plant Summary Information
R W Miller is ranked #105 out of 304 natural gas power plants in Texas in terms of total annual net electricity generation.
R W Miller is comprised of 5 generators and generated 178.8 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | R W Miller |
---|---|
Utility Name | RW Miller Power LLC |
Location | Palo Pinto County, TX |
Initial Operation Date | October 1968 |
Last Update | Sep 2024 |
Annual Generation | 417.5 GWh |
Annual Consumption | 6.7 M MMBtu |
Ranked #1,457 out of 11,852 Power Plants Nationwide | |
Ranked #595 out of 2,254 Natural Gas Power Plants Nationwide | |
Ranked #272 out of 754 Texas Power Plants | |
Ranked #105 out of 304 Texas Natural Gas Power Plants | |
Fuel Types | Natural Gas : 96.4% Distillate Fuel Oil : 3.6% |
Previous Operator |
Brazos Electric Power Coop Inc (2013 to 2022) RW Miller Power LLC (2023 to 2023) |
Map of R W Miller
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for R W Miller.
Monthly Net Generation for R W Miller
R W Miller Details
Summary Information | |
---|---|
Plant Name | R W Miller (3628) |
Plant Address | 2217 F.M.Road 3137, Palo Pinto, TX 76484 |
Utility | RW Miller Power LLC (66086) |
Latitude, Longitude | 32.6581, -98.3103 |
Generation Dates on File | Jan 2001 to Sep 2024 |
Initial Operation Date | October 1968 |
Annual Generation | 417.5 GWh |
Fuel Types | Natural Gas : 96.4% Distillate Fuel Oil : 3.6% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Lake Palo Pinto |
Ash Impoundment | Yes Lined Operating |
Transmission / Distribution Owner | Brazos Electric Power Coop Inc (2172) |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | ATMOS ENERGY CORPORATION |
Natural Gas Storage | No |
Generator 1 Details Out of Service October 1968
Technology | Natural Gas Steam Turbine |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | MIL_MILG1_2 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | MIL_MILG1_2 |
Nameplate Capacity | 66 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 66 MW |
Winter Capacity | 66 MW |
Minimum Load | 20 MW |
Uprate/Derate Completed | No |
Status | Out of Service |
First Operation Date | October 1968 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Subcritical Technology | No |
Multiple Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 2 Details Operating July 1972
Technology | Natural Gas Steam Turbine |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | MIL_MILG1_2 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | MIL_MILG1_2 |
Nameplate Capacity | 100 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 100 MW |
Winter Capacity | 100 MW |
Minimum Load | 38 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 1972 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas / Distillate Fuel Oil |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Subcritical Technology | No |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Cofire Energy Source | NG / DFO |
---|---|
Switch When Operating | Yes |
Net Summer Capacity With Natural Gas | 100 MW |
Net Winter Capacity With Natural Gas | 100 MW |
Net Summer Capacity With Oil | 100 MW |
Net Winter Capacity With Oil | 100 MW |
Time To Switch From Gas To Oil | 6H |
Time To Switch From Oil To Gas | 6H |
Factors That Limit Switching | Yes |
Air Permit Limits | Yes |
Generator 3 Details Operating August 1975
Technology | Natural Gas Steam Turbine |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | MIL_MILG345 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | MIL_MILG345 |
Nameplate Capacity | 200 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 200 MW |
Winter Capacity | 200 MW |
Minimum Load | 40 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | August 1975 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas / Distillate Fuel Oil |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Subcritical Technology | No |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Cofire Energy Source | NG / DFO |
---|---|
Switch When Operating | Yes |
Net Summer Capacity With Natural Gas | 200 MW |
Net Winter Capacity With Natural Gas | 200 MW |
Net Summer Capacity With Oil | 200 MW |
Net Winter Capacity With Oil | 200 MW |
Time To Switch From Gas To Oil | 6H |
Time To Switch From Oil To Gas | 6H |
Factors That Limit Switching | Yes |
Air Permit Limits | Yes |
Generator 4 Details Operating July 1994
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | MIL_MILG345 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | MIL_MILG345 |
Nameplate Capacity | 118.8 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 104 MW |
Winter Capacity | 104 MW |
Minimum Load | 35 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 1994 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Subcritical Technology | No |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Cofire Energy Source | NG / DFO |
---|---|
Switch When Operating | Yes |
Net Summer Capacity With Natural Gas | 104 MW |
Net Winter Capacity With Natural Gas | 104 MW |
Net Summer Capacity With Oil | 104 MW |
Net Winter Capacity With Oil | 104 MW |
Time To Switch From Gas To Oil | 6H |
Time To Switch From Oil To Gas | 6H |
Factors That Limit Switching | Yes |
Air Permit Limits | Yes |
Generator 5 Details Operating July 1994
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | MIL_MILG345 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | MIL_MILG345 |
Nameplate Capacity | 118.8 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 104 MW |
Winter Capacity | 104 MW |
Minimum Load | 35 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 1994 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Subcritical Technology | No |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Cofire Energy Source | NG / DFO |
---|---|
Switch When Operating | Yes |
Net Summer Capacity With Natural Gas | 104 MW |
Net Winter Capacity With Natural Gas | 104 MW |
Net Summer Capacity With Oil | 104 MW |
Net Winter Capacity With Oil | 104 MW |
Time To Switch From Gas To Oil | 6H |
Time To Switch From Oil To Gas | 6H |
Factors That Limit Switching | Yes |
Air Permit Limits | Yes |
R W Miller Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#585 | Geismar | Geismar, LA | 584.4 GWh |
#586 | Spindle Hill Energy Center | Fort Lupton, CO | 424.3 GWh |
#587 | Nevada Cogen Assoc#1 GarnetVly | Las Vegas, NV | 420.9 GWh |
#588 | Nikiski Combined Cycle | Nikiski, AK | 416.8 GWh |
#589 | Victoria Texas Plant | Victoria, TX | 411.2 GWh |
#590 | Richard M Flynn | Holtsville, NY | 429.5 GWh |
#591 | HO Clarke Generating | Houston, TX | 410.4 GWh |
#592 | Thomas Fitzhugh | Ozark, AR | 404.5 GWh |
#593 | Rumford Power LLC | Rumford, ME | 403.4 GWh |
#594 | Primient Loudon Plant | Loudon, TN | 402.4 GWh |
#596 | Mulberry Cogeneration Facility | Bartow, FL | 399.7 GWh |
#597 | Astoria Station | Astoria, SD | 395.9 GWh |
#598 | Pearsall | Pearsall, TX | 395.1 GWh |
#599 | Gordon Evans Energy Center | Colwich, KS | 401.1 GWh |
#600 | Orange Cogeneration Facility | Bartow, FL | 391.0 GWh |
#601 | Primient | Lafayette, IN | 389.3 GWh |
#602 | Port Jefferson | Port Jefferson, NY | 396.4 GWh |
#603 | Brotman Power Station | Rosharon, TX | 383.3 GWh |
#604 | Oleander Power Project LP | Cocoa, FL | 383.6 GWh |
#605 | University of Florida | Gainesville, FL | 377.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding R W Miller.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Barton Chapel Wind Farm | Jacksboro, TX | 241.6 GWh | 27.3 mi |
Bridgeport Gas Processing Plant | Bridgeport, TX | 49.6 GWh | 47.4 mi |
Buckthorn Wind | Mingus, TX | 362.2 GWh | 20.2 mi |
Comanche Peak | Glen Rose, TX | 19.7 TWh | 39.4 mi |
DeCordova Steam Electric Station | Granbury, TX | 95.5 GWh | 39.7 mi |
Graham | Graham, TX | 1.2 TWh | 37.3 mi |
Jack County | Bridgeport, TX | 6.8 TWh | 36.8 mi |
Keechi Wind | Jacksboro, TX | 411.9 GWh | 34.6 mi |
Roadrunner Wind Farm | Cisco, TX | 177.9 GWh | 48.9 mi |
Senate Wind LLC | Bryson, TX | 463.1 GWh | 38 mi |
Silver Star I Wind Power Project | Dublin, TX | 186.1 GWh | 24.1 mi |
TPE Erath Solar, LLC | Stephenville, TX | 25.2 GWh | 28 mi |
WAL3773 | Fort Worth, TX | 371.0 MWh | 48.6 mi |
WAL4509 | Tarrant, TX | 353.0 MWh | 49 mi |
Walnut Springs Solar | Walnut Springs, TX | 10.9 GWh | 51 mi |
Westside Landfill Gas Recovery | Aledo, TX | 22.0 GWh | 45.2 mi |
Wise County Power LLC | Poolville, TX | 3.8 TWh | 36.1 mi |
Wolf Hollow I LP | Granbury, TX | 3.0 TWh | 40.5 mi |
Wolf Hollow II | Granbury, TX | 7.2 TWh | 40.2 mi |
Young Wind | Graham, TX | 1.6 TWh | 44.8 mi |