Progress Solar II, LLC
5719 Old Stage Road, Fairmont, NC 28340Plant Summary Information
Progress Solar II, LLC is ranked #573 out of 748 solar farms in North Carolina in terms of total annual net electricity generation.
Progress Solar II, LLC generated 1.1 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Progress Solar II, LLC |
---|---|
Utility Name | Oppidum Renewables USA, LLC |
Location | Robeson County, NC |
Initial Operation Date | November 2012 |
Last Update | Dec 2023 |
Annual Generation | 5.4 GWh |
Annual Consumption | 19.4 k MMBtu |
Ranked #7,518 out of 11,852 Power Plants Nationwide | |
Ranked #2,698 out of 5,655 Solar Power Plants Nationwide | |
Ranked #656 out of 863 North Carolina Power Plants | |
Ranked #573 out of 748 North Carolina Solar Power Plants | |
Fuel Types | Solar |
Previous Operator |
O2energies, Inc. (2013 to 2018) Oppidum Renewables USA, LLC (2019 to 2023) |
Map of Progress Solar II, LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Progress Solar II, LLC.
Monthly Net Generation for Progress Solar II, LLC
Progress Solar II, LLC Details
Summary Information | |
---|---|
Plant Name | Progress Solar II, LLC (58494) |
Plant Address | 5719 Old Stage Road, Fairmont, NC 28340 |
Utility | Oppidum Renewables USA, LLC (63026) |
Latitude, Longitude | 34.47611, -79.0975 |
Generation Dates on File | Jan 2013 to Dec 2023 |
Initial Operation Date | November 2012 |
Annual Generation | 5.4 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | SP-1605 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Duke Energy Progress East (CPLE) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Duke Energy Progress - (NC) (3046) NC |
Grid Voltage | 23.00 kV |
Energy Storage | No |
Generator PROG2 Details Operating November 2012
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 3.5 MW |
Summer Capacity | 3.5 MW |
Winter Capacity | 3.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | November 2012 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 20 |
DC Net Capacity | 4.5 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Progress Solar II, LLC Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#2688 | Charlton Solar I CSG | Charlton, MA | 5.5 GWh |
#2689 | 25 Ashdown Road Solar, LLC | Clifton Park, NY | 5.4 GWh |
#2690 | Mt. Tom Solar Project Hybrid | Holyoke, MA | 5.3 GWh |
#2691 | Sayreville Solar Project | Sayreville, NJ | 5.4 GWh |
#2692 | Baltimore Church Solar, LLC | Fairmont, NC | 5.4 GWh |
#2693 | Prairie Mist Solar | Montrose, AR | 5.4 GWh |
#2694 | 8500 Balboa PV, LLC | Northridge, CA | 5.4 GWh |
#2695 | IOS - MEW Phase 1 | Madison, ME | 5.4 GWh |
#2696 | Staunton | Brazil, IN | 5.4 GWh |
#2697 | Oak Street Solar | Springfield, MA | 5.4 GWh |
#2699 | CA - Fresno County - Juvenile Hall | Fresno, CA | 5.4 GWh |
#2700 | Putnam Erickson | Eatonton, GA | 5.4 GWh |
#2701 | ENGIE 2019 ProjectCo-MA1, LLC | Agawam, MA | 5.4 GWh |
#2702 | Cortez Solar 1, LLC | Cortez, CO | 5.4 GWh |
#2703 | SCS Penfield One 010750 Penfield, LLC | Penfield, NY | 5.4 GWh |
#2704 | Lenox Renewables | Canastota, NY | 5.4 GWh |
#2705 | Nautilus Winsted Solar (CSG) | Winsted, MN | 5.4 GWh |
#2706 | One Ten Partners PV | Palmdale, CA | 5.4 GWh |
#2707 | Minnie Solar | Graham, NC | 5.4 GWh |
#2708 | Yardville Solar Farm | Hamilton, NJ | 5.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Progress Solar II, LLC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Acme Solar, LLC | Riegelwood, NC | 7.8 GWh | 12 mi |
Baltimore Church Solar, LLC | Fairmont, NC | 5.4 GWh | 3.2 mi |
Bo Biggs Solar | Lumberton, NC | 8.8 GWh | 11.1 mi |
Broadridge Solar, LLC | Lumberton, NC | 9.9 GWh | 8.6 mi |
Fairmont-FLS 100 | Fairmont, NC | 6.4 GWh | 3.6 mi |
Floyd Solar, LLC | Fairmont, NC | 9.5 GWh | 3.2 mi |
FLS Solar 170, LLC | Lumberton, NC | 3.4 GWh | 11.2 mi |
FLS Solar 200, LLC | Lumberton, NC | 6.4 GWh | 11.6 mi |
Graham Solar Center LLC | Fair Bluff, NC | 8.5 GWh | 12.4 mi |
Holly Swamp Solar, LLC | Lumberton, NC | 4.3 GWh | 13 mi |
Jersey Holdings | Lumberton, NC | 9.6 GWh | 7 mi |
McCallum Farm | Rowland, NC | 8.9 GWh | 12.6 mi |
Panda Solar NC 1, LLC | Fairmont, NC | 1.8 GWh | 2.8 mi |
Panda Solar NC 2, LLC | Fairmont, NC | 3.3 GWh | 2.7 mi |
Panda Solar NC 3, LLC | Lumberton, NC | 4.0 GWh | 10.8 mi |
South Robeson Farm | Rowland, NC | 7.2 GWh | 12 mi |
Stone Solar | Lumberton, NC | 9.8 GWh | 8.3 mi |
Turkey Branch Solar LLC | Fairmont, NC | 8.1 GWh | 3.4 mi |
W H Weatherspoon | Lumberton, NC | 104.0 MWh | 10.4 mi |
Walters Solar (FLS 260) | Orrum, NC | 9.2 GWh | 3.1 mi |