Priddy Wind Project
500 FM-575, Goldthwaite, TX 76844Plant Summary Information
Priddy Wind Project is ranked #27 out of 218 wind farms in Texas in terms of total annual net electricity generation.
Priddy Wind Project generated 167.4 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | Priddy Wind Project |
---|---|
Utility Name | Engie North America |
Location | Mills County, TX |
Initial Operation Date | January 2022 |
Last Update | Sep 2024 |
Annual Generation | 944.0 GWh |
Annual Consumption | 3.4 M MMBtu |
Ranked #765 out of 11,852 Power Plants Nationwide | |
Ranked #80 out of 1,345 Wind Power Plants Nationwide | |
Ranked #122 out of 754 Texas Power Plants | |
Ranked #27 out of 218 Texas Wind Power Plants | |
Fuel Types | Wind |
Map of Priddy Wind Project
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Priddy Wind Project.
Monthly Net Generation for Priddy Wind Project
Priddy Wind Project Details
Summary Information | |
---|---|
Plant Name | Priddy Wind Project (64165) |
Plant Address | 500 FM-575, Goldthwaite, TX 76844 |
Utility | Engie North America (56201) |
Latitude, Longitude | 31.5481, -98.49491 |
Generation Dates on File | Jan 2022 to Sep 2024 |
Initial Operation Date | January 2022 |
Annual Generation | 944.0 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
Grid Voltage | 345.00 kV |
Energy Storage | No |
Generator WTG1 Details Operating January 2022
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 302.4 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 302.4 MW |
Winter Capacity | 302.4 MW |
Minimum Load | 4 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | January 2022 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Turbines/Hydrokinetic Buoys | 63 |
Turbine Details | |
Number Of Turbines | 63 |
---|---|
Predominant Turbine Manufacturer | Nordex |
Predominant Turbine Model Number | N149/4.0-4.5 |
Design Wind Speed | 18.6 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 489 |
Priddy Wind Project Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#70 | Little Blue Wind Project, LLC | Blue Hill, NE | 974.7 GWh |
#71 | Pomeroy Wind Farm | Fonda, IA | 967.1 GWh |
#72 | Chisholm View Wind Project | Hunter, OK | 967.0 GWh |
#73 | Irish Creek Wind | Frankfort, KS | 966.5 GWh |
#74 | Wake Wind Energy Center | Floydada, TX | 954.0 GWh |
#75 | Biglow Canyon Wind Farm | Wasco, OR | 949.7 GWh |
#76 | Balko Wind LLC | Balko, OK | 949.1 GWh |
#77 | La Joya NM | Encino, NM | 947.1 GWh |
#78 | Seven Cowboy Wind Project, LLC | Gage, OK | 944.9 GWh |
#79 | Rush Springs Wind | Marlow, OK | 944.3 GWh |
#81 | Western Trail Wind, LLC | Electra, TX | 943.1 GWh |
#82 | Ponderosa Wind Energy Center | Beaver, OK | 940.1 GWh |
#83 | Ida Grove Wind | Ida Grove, IA | 939.8 GWh |
#84 | TX Jumbo Road Wind | Hereford, TX | 937.4 GWh |
#85 | Great Western Wind Energy, LLC | Arnett, OK | 931.7 GWh |
#86 | Sapphire Sky Wind Energy LLC | Farmer City, IL | 930.9 GWh |
#87 | Pratt Wind, LLC | Andover, KS | 928.8 GWh |
#88 | Armadillo Flats Wind Project, LLC | Enid, OK | 911.4 GWh |
#89 | Maverick Wind Project, LLC | Meno, OK | 909.9 GWh |
#90 | Miami Wind Energy Center | Miami, TX | 905.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Priddy Wind Project.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Buchanan Dam (TX) | Buchanan Dam, TX | 14.1 GWh | 55.3 mi |
Buckthorn Wind | Mingus, TX | 362.2 GWh | 57.3 mi |
Castle Gap Wind | Goldthwaite, TX | 583.4 GWh | 13.3 mi |
Dileo Solar | Clifton, TX | 142.0 GWh | 60.1 mi |
Flat Top Wind I | Mullin, TX | 786.7 GWh | 11.4 mi |
Goldthwaite Wind Energy Facility | Goldthwaite, TX | 490.1 GWh | 11.5 mi |
Grizzly Ridge Solar | Hamilton County, TX | 172.1 GWh | 21.1 mi |
Heart of Texas Wind Project | Brady, TX | 586.8 GWh | 58.6 mi |
Inks | Buchanan Dam, TX | 8.4 GWh | 56.8 mi |
IP Radian, LLC | Brookesmith, TX | 681.1 GWh | 40.8 mi |
Logans Gap Wind LLC | Comanche, TX | 613.6 GWh | 22.2 mi |
Phantom Solar | Fort Hood, TX | 26.5 GWh | 48.6 mi |
Ranchland Wind Project I | Cisco, TX | 400.8 GWh | 65.6 mi |
Ranchland Wind Project II | Cisco, TX | 497.4 GWh | 65.6 mi |
Rattlesnake Power, LLC | Brady, TX | 541.8 GWh | 63.6 mi |
Silver Star I Wind Power Project | Dublin, TX | 186.1 GWh | 54.6 mi |
TPE Erath Solar, LLC | Stephenville, TX | 25.2 GWh | 52.2 mi |
WAL407 | Killeen, TX | 369.0 MWh | 55.2 mi |
Walnut Springs Solar | Walnut Springs, TX | 10.9 GWh | 56.2 mi |
Yellow Jacket | Meridian, TX | 10.5 GWh | 56.2 mi |