PEC Headworks
SR 262, Moses Lake, WA 98837Plant Summary Information
PEC Headworks is ranked #53 out of 70 hydroelectric power plants in Washington in terms of total annual net electricity generation.
PEC Headworks is comprised of 1 generator and generated 5.0 GWh during the 3-month period between July 2023 to October 2023.
Plant Name | PEC Headworks |
---|---|
Utility Name | PUD No 2 of Grant County |
Location | Grant County, WA |
Initial Operation Date | September 1990 |
Last Update | Oct 2023 |
Annual Generation | 18.7 GWh |
Annual Consumption | 66.6 k MMBtu |
Ranked #5,137 out of 11,835 Power Plants Nationwide | |
Ranked #779 out of 1,371 Water Power Plants Nationwide | |
Ranked #103 out of 134 Washington Power Plants | |
Ranked #53 out of 70 Washington Water Power Plants | |
Fuel Types | Water |
Map of PEC Headworks
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for PEC Headworks.
Monthly Net Generation for PEC Headworks
PEC Headworks Details
Summary Information | |
---|---|
Plant Name | PEC Headworks (7113) |
Plant Address | SR 262, Moses Lake, WA 98837 |
Utility | PUD No 2 of Grant County (14624) |
Latitude, Longitude | 47.15955, -119.89631 |
Generation Dates on File | Mar 2001 to Oct 2023 |
Initial Operation Date | September 1990 |
Annual Generation | 18.7 GWh |
Fuel Types | Water |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | Public Utility District No. 2 of Grant County, Washington (GCPD) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Potholes Reservoir |
Ash Impoundment | |
Transmission / Distribution Owner | PUD No 2 of Grant County (14624) WA |
Grid Voltage | 115.00 kV |
Energy Storage | No |
Generator 1 Details Operating September 1990
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Jointly Owned |
Nameplate Capacity | 6.6 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 6.6 MW |
Winter Capacity | 6.6 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | September 1990 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Time From Cold Shutdown To Full Load | 10M |
PEC Headworks Plant Owners
Owner Name | Address | Ownership |
---|---|---|
Quincy-Columbia Basin Irr Dist | 1720 Central Ave S, P.O. Box 188 Quincy, WA 98848 | 33.34% |
East Columbia Basin Irr Dist | 55 N 8th Ave, Othello, WA 99344 | 33.33% |
South Columbia Basin Irr Dist | 1135 E Hillsboro St # A, Pasco, WA 99301 | 33.33% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#769 | Deep Creek | Oakland, MD | 19.7 GWh |
#770 | Foothill Feeder | Castaic, CA | 19.6 GWh |
#771 | Fort Miller Hydroelectric Facility | Northumberland, NY | 19.5 GWh |
#772 | Gaston Shoals | Blacksburg, SC | 19.3 GWh |
#773 | Power Creek | Cordova, AK | 19.2 GWh |
#774 | Verdi | Verdi, NV | 19.1 GWh |
#775 | Kansas River Project | Lawrence, KS | 19.0 GWh |
#776 | Alexander | Merrill, WI | 19.0 GWh |
#777 | Rochester 5 | Rochester, NY | 18.9 GWh |
#778 | Pioneer | Ogden, UT | 18.7 GWh |
#780 | Nacimiento Hydro Project | Bradley, CA | 18.6 GWh |
#781 | Nottely | Blairsville, GA | 18.6 GWh |
#782 | Lower Molina | Molina, CO | 18.6 GWh |
#783 | Lachute Hydro Lower | Ticonderoga, NY | 18.5 GWh |
#784 | Lachute Hydro Upper | Ticonderoga, NY | 18.5 GWh |
#785 | Beldens | New Haven, VT | 18.5 GWh |
#786 | Olsen | Whitmore, CA | 18.4 GWh |
#787 | Spirit Mountain | Cody, WY | 18.4 GWh |
#788 | Spaulding 3 | Emigrant Gap, CA | 18.3 GWh |
#789 | Fish Creek | Idleyld Park, OR | 18.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding PEC Headworks.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Camas Solar Project | Ellensburg, WA | 10.3 GWh | 32 mi |
Chelan | Wenatchee, WA | 305.8 GWh | 47 mi |
Cowiche | Tieton, WA | 3.4 GWh | 51.1 mi |
Main Canal Headworks | Coulee City, WA | 118.7 GWh | 42.1 mi |
Orchard Avenue 1 | Yakima, WA | 2.6 GWh | 53.6 mi |
Penstemon Solar Project | Ellensburg, WA | 10.4 GWh | 32 mi |
Priest Rapids | Mattawa, WA | 3.7 TWh | 35.5 mi |
Quincy Chute | Quincy, WA | 33.8 GWh | 32.4 mi |
Rock Island | Wenatchee, WA | 2.0 TWh | 15.8 mi |
Rocky Reach | Wenatchee, WA | 4.8 TWh | 31.9 mi |
Roza | Yakima, WA | 54.5 GWh | 46.4 mi |
Russell D Smith | Othello, WA | 17.0 GWh | 47 mi |
Sagebrush Power Partners | Ellensburg, WA | 255.0 GWh | 37.2 mi |
Summer Falls Power Plant | Coulee City, WA | 447.2 GWh | 36.9 mi |
Swauk Wind LLC | Thorp, WA | 6.0 GWh | 40.3 mi |
Urtica Solar Project | Ellensburg, WA | 11.4 GWh | 37.5 mi |
Vantage Wind Energy LLC | Ellensburg, WA | 231.6 GWh | 19.5 mi |
Wanapum | Beverly, WA | 3.9 TWh | 20.1 mi |
Wells | Pateros, WA | 3.4 TWh | 54.4 mi |
Wild Horse | Ellensburg, WA | 592.7 GWh | 16.9 mi |