12025 30th Avenue SE, Granite Falls, MN 56241Plant Summary Information
Palmer's Creek Wind Farm, LLC is ranked #30 out of 125 wind farms in Minnesota in terms of total annual net electricity generation.
Palmer's Creek Wind Farm, LLC generated 27.6 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | Palmer's Creek Wind Farm, LLC |
---|---|
Utility Name | Palmer's Creek Wind Farm, LLC |
Location | Chippewa County, MN |
Initial Operation Date | December 2018 |
Last Update | Sep 2024 |
Annual Generation | 124.5 GWh |
Annual Consumption | 453.4 k MMBtu |
Ranked #2,913 out of 11,852 Power Plants Nationwide | |
Ranked #820 out of 1,345 Wind Power Plants Nationwide | |
Ranked #51 out of 736 Minnesota Power Plants | |
Ranked #30 out of 125 Minnesota Wind Power Plants | |
Fuel Types | Wind |
Map of Palmer's Creek Wind Farm, LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Palmer's Creek Wind Farm, LLC.
Monthly Net Generation for Palmer's Creek Wind Farm, LLC
Palmer's Creek Wind Farm, LLC Details
Summary Information | |
---|---|
Plant Name | Palmer's Creek Wind Farm, LLC (62291) |
Plant Address | 12025 30th Avenue SE, Granite Falls, MN 56241 |
Utility | Palmer's Creek Wind Farm, LLC (61815) |
Latitude, Longitude | 44.85769, -95.56889 |
Generation Dates on File | Dec 2018 to Sep 2024 |
Initial Operation Date | December 2018 |
Annual Generation | 124.5 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | EG18-98 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | WAPA-- Western Area Power Administration (27000) MN |
Grid Voltage | 115.00 kV |
Energy Storage | No |
Generator PCWF Details Operating December 2018
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WAUEGRANITFUNPALMERCREEK_WF_RA |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WAPA Granite Falls 115 kV substation |
Nameplate Capacity | 44.6 MW |
Summer Capacity | 44.6 MW |
Winter Capacity | 44.6 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2018 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 18 |
Time From Cold Shutdown To Full Load | 10M |
Other Planned Modifications | No |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 18 |
---|---|
Predominant Turbine Manufacturer | GE |
Predominant Turbine Model Number | 2.5-120 |
Design Wind Speed | 16 MPH |
Wind Quality Class | 3 - Low Wind |
Turbine Hub Height Feet | 295.3 |
Palmer's Creek Wind Farm, LLC Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#810 | Rollins Wind Project | Winn Village, ME | 132.2 GWh |
#811 | Michigan Wind 1 | Ubly, MI | 131.9 GWh |
#812 | Macho Springs Power I | Deming, NM | 131.8 GWh |
#813 | Prairie Breeze III | Elgin, NE | 131.3 GWh |
#814 | Central Plains Wind Farm | Marienthal, KS | 129.7 GWh |
#815 | Northern Iowa Windpower II | Kensett, IA | 129.1 GWh |
#816 | Stony Creek Wind Farm LLC | Berlin, PA | 128.0 GWh |
#817 | Great Plains Windpark LLC | Spearman, TX | 127.7 GWh |
#818 | Storm Lake II | Alta, IA | 125.6 GWh |
#819 | Cameron Ridge LLC | Mojave, CA | 125.1 GWh |
#821 | Ashtabula Wind Energy Center | Luverne, ND | 123.2 GWh |
#822 | Golden Hills North Wind Energy Center | Livermore, CA | 123.2 GWh |
#823 | Clinton | Churubusco, NY | 123.1 GWh |
#824 | Cambria Wind LLC | Sidman, PA | 121.6 GWh |
#825 | Passadumkeag Windpark LLC | Greenbush, ME | 121.1 GWh |
#826 | Kawailoa Wind | Haleiwa, HI | 120.9 GWh |
#827 | Altona | Altona, NY | 120.2 GWh |
#828 | Ridgetop | Mojave, CA | 119.5 GWh |
#829 | Beebe 1B | Ithaca, MI | 119.0 GWh |
#830 | Crofton Bluffs Wind LLC | Bloomfield, NE | 119.0 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Palmer's Creek Wind Farm, LLC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Andresen Solar | Clara City, MN | 2.4 GWh | 10.9 mi |
Centaurus Community Solar | Maynard, MN | 3.5 GWh | 6.9 mi |
Clara City Solar | Clara City, MN | 1.9 GWh | 12.3 mi |
Crater Community Solar | Granite Falls, MN | 5.3 GWh | 5 mi |
Granite Falls | Granite Falls, MN | 604.0 MWh | 3.6 mi |
Hormel CSG Solar | Montevideo, MN | 1.0 GWh | 9.1 mi |
Lantana Solar, LLC | Glenwood, MN | 2.2 GWh | 17.9 mi |
Montevideo Solar LLC, CSG | Montevideo, MN | 9.8 GWh | 6.8 mi |
Novel Handeland Solar LLC (CSG) | Clarkfield, MN | 2.2 GWh | 11.8 mi |
Novel Historical Society Solar CSG | Sacred Heart, MN | 1.7 GWh | 11.3 mi |
Novel Shelly Solar LLC (CSG) | Cottonwood, MN | 2.3 GWh | 17.2 mi |
Sacred Heart CSG1, LLC | Sacred Heart, MN | 2.3 GWh | 11.4 mi |
Sagitta Community Solar | Clara City, MN | 1.9 GWh | 10.9 mi |
Skalbeck Solar | Sacred Heart, MN | 2.5 GWh | 11 mi |
Syncarpha Clara City CSG I (Stamer) | Clara City, MN | 1.9 GWh | 12.4 mi |
Taurus Community Solar | Montevideo, MN | 5.4 GWh | 8.8 mi |
USS Christoffer Solar LLC CSG | Montevideo, MN | 2.2 GWh | 13.1 mi |
USS Pheasant Solar LLC CSG | Clara City, MN | 2.3 GWh | 16.4 mi |
USS Wolf Solar LLC | Wood Lake, MN | 1.1 GWh | 16.8 mi |
Wolverine Solar | Maynard, MN | 59.0 MWh | 8.1 mi |