Overman Solar
191 Herring Road, Goldsboro, NC 27530Plant Summary Information
Overman Solar is ranked #106 out of 748 solar farms in North Carolina in terms of total annual net electricity generation.
Overman Solar generated 2.0 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Overman Solar |
---|---|
Utility Name | Overman Solar, LLC |
Location | Wayne County, NC |
Initial Operation Date | December 2021 |
Last Update | Dec 2023 |
Annual Generation | 10.9 GWh |
Annual Consumption | 39.0 k MMBtu |
Ranked #5,770 out of 11,852 Power Plants Nationwide | |
Ranked #1,455 out of 5,655 Solar Power Plants Nationwide | |
Ranked #176 out of 863 North Carolina Power Plants | |
Ranked #106 out of 748 North Carolina Solar Power Plants | |
Fuel Types | Solar |
Map of Overman Solar
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Overman Solar.
Monthly Net Generation for Overman Solar
Overman Solar Details
Summary Information | |
---|---|
Plant Name | Overman Solar (66721) |
Plant Address | 191 Herring Road, Goldsboro, NC 27530 |
Utility | Overman Solar, LLC (65734) |
Latitude, Longitude | 35.29923, -78.07718 |
Generation Dates on File | Jan 2022 to Dec 2023 |
Initial Operation Date | December 2021 |
Annual Generation | 10.9 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | 15-329-001, 15-329-002 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Duke Energy Progress East (CPLE) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Duke Energy Progress - (NC) (3046) NC |
Grid Voltage | 22.86 kV |
Energy Storage | No |
Generator OVRMN Details Operating December 2021
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 5 MW |
Summer Capacity | 5 MW |
Winter Capacity | 5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
DC Net Capacity | 7 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Overman Solar Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1445 | Summer North Solar | Lancaster, CA | 11.1 GWh |
#1446 | 77 Farm to Market Rd Hybrid(CSG) | Wareham, MA | 11.0 GWh |
#1447 | Polk Farm | Hamlet, NC | 11.1 GWh |
#1448 | Snow Camp Solar, LLC | Snow Camp, NC | 11.1 GWh |
#1449 | Jamesville Road Solar, LLC | Jamesville, NC | 11.0 GWh |
#1450 | AFA Solar Farm | Colorado Springs, CO | 11.0 GWh |
#1451 | HL Solar | Wendel, CA | 10.9 GWh |
#1452 | Walnut Springs Solar | Walnut Springs, TX | 10.9 GWh |
#1453 | Kearsarge Smithfield LLC | Burrillville, RI | 10.9 GWh |
#1454 | Selwyn Farm | Lilesville, NC | 10.9 GWh |
#1456 | Winslow PV - BD Solar 2 LLC | Winslow, ME | 10.9 GWh |
#1457 | Buttercup Solar, LLC | Rose Hill, NC | 10.9 GWh |
#1458 | Oxford PV - BD Solar Oxford LLC | Oxford, ME | 10.9 GWh |
#1459 | IND Solar Farm (Phase IIA) | Indianapolis, IN | 10.8 GWh |
#1460 | RE Bruceville 1 LLC | Elk Grove, CA | 10.8 GWh |
#1461 | USPS PV | Los Angeles, CA | 10.8 GWh |
#1462 | Imeson Solar | Jscksonville, FL | 10.8 GWh |
#1463 | Overhill Solar | Clinton, NC | 10.8 GWh |
#1464 | Albertson Solar LLC | Albertson, NC | 10.8 GWh |
#1465 | Saw Solar | China Grove, NC | 10.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Overman Solar.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Belafonte | Calypso, NC | 7.3 GWh | 9.5 mi |
Blueberry One | Grantham, NC | 9.3 GWh | 4.5 mi |
Eros Solar, LLC | Mt Olive, NC | 9.9 GWh | 9.3 mi |
Harrell's Hill Solar Center LLC | Mt. Olive, NC | 6.0 GWh | 6.2 mi |
Lane II Solar, LLC | Goldsboro, NC | 10.4 GWh | 7.1 mi |
Lane Solar | Goldsboro, NC | 9.7 GWh | 6.8 mi |
Lee Combined Cycle Plant | Goldsboro, NC | 6.6 TWh | 5.2 mi |
Mount Olive Farm | Mount Olive, NC | 9.6 GWh | 6.7 mi |
Mount Olive Solar | Mount Olive, NC | 2.2 GWh | 8.3 mi |
Mt Olive Farm 2 | Mt Olive, NC | 9.0 GWh | 5.6 mi |
Mt Olive Solar 1 | Mt. Olive, NC | 7.3 GWh | 8.2 mi |
Oakwood Solar | Mebane, NC | 9.5 GWh | 0 mi |
Robin Solar | Dudley, NC | 8.1 GWh | 2.4 mi |
Ruskin Solar | Dudley, NC | 3.9 GWh | 3.6 mi |
Solar Lee, LLC | Mount Olive, NC | 7.7 GWh | 7.9 mi |
Summit Solar | Mount Olive, NC | 6.6 GWh | 5.4 mi |
Terreva Wayne County RNG, LLC | Dudley, NC | 8.2 GWh | 0.8 mi |
Wayne County | Goldsboro, NC | 90.7 GWh | 5.4 mi |
Wayne Solar I LLC | Mount Olive, NC | 2.3 GWh | 6.3 mi |
Wayne Solar II LLC | Goldsboro, NC | 5.9 GWh | 1.1 mi |