Oregon University System OIT Klamath Falls
3201 Campus Drive, Klamath Falls, OR 97601Plant Summary Information
Oregon University System OIT Klamath Falls is ranked #98 out of 114 solar farms in Oregon in terms of total annual net electricity generation.
Oregon University System OIT Klamath Falls generated 710.9 MWh during the 3-month period between September 2022 to December 2022.
Plant Name | Oregon University System OIT Klamath Falls |
---|---|
Utility Name | Tesla Inc. |
Location | Klamath County, OR |
Initial Operation Date | January 2014 |
Last Update | Dec 2022 |
Annual Generation | 3.1 GWh |
Annual Consumption | 10.8 k MMBtu |
Ranked #8,755 out of 11,249 Power Plants Nationwide | |
Ranked #3,677 out of 5,158 Solar Power Plants Nationwide | |
Ranked #228 out of 254 Oregon Power Plants | |
Ranked #98 out of 114 Oregon Solar Power Plants | |
Fuel Types | Solar |
Previous Operator |
SolarCity Corporation (2013 to 2015) Tesla Inc. (2016 to 2022) |
Map of Oregon University System OIT Klamath Falls
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Oregon University System OIT Klamath Falls.
Monthly Net Generation for Oregon University System OIT Klamath Falls
Oregon University System OIT Klamath Falls Details
Summary Information | |
---|---|
Plant Name | Oregon University System OIT Klamath Falls (58961) |
Plant Address | 3201 Campus Drive Klamath Falls, OR 97601 |
Utility | Tesla Inc. (60947) |
Latitude, Longitude | 42.25417, -121.785 |
Generation Dates on File | Jan 2014 to Dec 2022 |
Initial Operation Date | January 2014 |
Annual Generation | 3.1 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | QF14-198-000 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | PacifiCorp - West (PACW) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | PacifiCorp (14354) OR |
Grid Voltage | 0.48 kV |
Energy Storage | No |
Generator PV Details Operating January 2014
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 1.7 MW |
Summer Capacity | 1.7 MW |
Winter Capacity | 1.7 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | January 2014 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 220 |
Tilt Angle | 35 |
DC Net Capacity | 2 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | Yes |
Net Metering DC Capacity | 2 MW |
Virtual Net Metering Agreement | No |
Oregon University System OIT Klamath Falls Plant Owners
Owner Name | Address | Ownership |
---|---|---|
Mound Solar Owner V LLC | 6800 Dumbarton Circle, Freemont, CA 94555 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#3667 | Medford DPC Solar | Medford, WI | 3.1 GWh |
#3668 | Citizens Agawam Landfill Solar | Agawam, MA | 3.1 GWh |
#3669 | 2081 Terzian Solar Project | Reedley, CA | 3.1 GWh |
#3670 | Lakeland Solar Energy LLC | Lakeland, GA | 3.1 GWh |
#3671 | Chattanooga Metropolitan Airport Solar | Chattanooga, TN | 3.1 GWh |
#3672 | Colonial Pipeline Allentown Chesterfield | Chesterfield, NJ | 3.1 GWh |
#3673 | Google Moffett Park Solar Project | Sunnyvale, CA | 3.0 GWh |
#3674 | Drinkwater Solar | Saint Johnsville, NY | 3.1 GWh |
#3675 | Pima Community College - East Campus | Tucson, AZ | 3.1 GWh |
#3676 | County of Dutchess, NY (Airport) | Wappinger Falls, NY | 3.1 GWh |
#3678 | CED Champaign Solar LLC | Champaign, IL | 3.1 GWh |
#3679 | Minke Solar | Molalla, OR | 3.0 GWh |
#3680 | SR Houston | Houston, MS | 3.0 GWh |
#3681 | Charlotte Solar LLC VT | Charlotte, VT | 3.0 GWh |
#3682 | Grassland 1&2 Solar Project | Davis, CA | 3.0 GWh |
#3683 | Mtn. Solar 1 | Watkins, CO | 3.0 GWh |
#3684 | Lafayette 2 - Internal Services Dept | Los Angeles, CA | 3.0 GWh |
#3685 | Clif Bar Bakery of Twin Falls | Twin Falls, ID | 3.0 GWh |
#3686 | Union HS at Casa Grande | Casa Grande, AZ | 3.0 GWh |
#3687 | First Baptist Church of Glenarden | Upper Marlboro, MD | 3.0 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Oregon University System OIT Klamath Falls.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Bly Solar Center | Bly, OR | 22.0 GWh | 40 mi |
Chiloquin Solar, LLC | Chiloquin, OR | 20.9 GWh | 24.9 mi |
Copco 1 | Hornbrook, CA | 68.1 GWh | 34 mi |
Copco 2 | Hornbrook, CA | 81.3 GWh | 35.1 mi |
Fall Creek | Hornbrook, CA | 6.5 GWh | 34.8 mi |
Green Springs | Columbia Falls, OR | 21.0 GWh | 40.1 mi |
Iron Gate | Hornbrook, CA | 81.6 GWh | 40.1 mi |
John C Boyle | Keno, OR | 174.0 GWh | 18.3 mi |
Klamath Cogeneration Plant | Klamath Falls, OR | 3.3 TWh | 5.7 mi |
Klamath Expansion Project | Klamath Falls, OR | 29.2 GWh | 5.8 mi |
Klamath Falls Solar 2 CSG | Klamath Falls, OR | 7.0 GWh | 5 mi |
NorWest Energy 4, LLC | Bonanza, OR | 11.6 GWh | 31.7 mi |
Old Mill Solar | Bly, OR | 7.8 GWh | 38 mi |
OR Solar 3, LLC | Malin, OR | 25.6 GWh | 24.7 mi |
OR Solar 5, LLC | Merrill, OR | 20.2 GWh | 17.8 mi |
OR Solar 8, LLC | Dairy, OR | 27.6 GWh | 10.2 mi |
Prospect 3 | Prospect, OR | 991.0 MWh | 46.1 mi |
Skysol | OR | 19.4 GWh | 20.7 mi |
Sprague Hydro | Bly, OR | 467.2 MWh | 44.1 mi |
Woodline Solar | Dairy, OR | 20.2 GWh | 10.7 mi |