OER Checkerspot
5963 Franklin Gibson Rd, Tracy's Landing, MD 20779Plant Summary Information
OER Checkerspot is ranked #64 out of 140 solar farms in Maryland in terms of total annual net electricity generation.
OER Checkerspot generated 522.0 MWh during the 3-month period between September 2023 to December 2023.
Plant Name | OER Checkerspot |
---|---|
Utility Name | Standard Solar |
Location | Anne Arundel County, MD |
Initial Operation Date | December 2021 |
Last Update | Dec 2023 |
Annual Generation | 3.0 GWh |
Annual Consumption | 10.8 k MMBtu |
Ranked #8,993 out of 11,852 Power Plants Nationwide | |
Ranked #3,853 out of 5,655 Solar Power Plants Nationwide | |
Ranked #94 out of 179 Maryland Power Plants | |
Ranked #64 out of 140 Maryland Solar Power Plants | |
Fuel Types | Solar |
Map of OER Checkerspot
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for OER Checkerspot.
Monthly Net Generation for OER Checkerspot
OER Checkerspot Details
Summary Information | |
---|---|
Plant Name | OER Checkerspot (64790) |
Plant Address | 5963 Franklin Gibson Rd, Tracy's Landing, MD 20779 |
Utility | Standard Solar (60531) |
Latitude, Longitude | 38.78357, -76.57415 |
Generation Dates on File | Dec 2021 to Dec 2023 |
Initial Operation Date | December 2021 |
Annual Generation | 3.0 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | RFC |
Balancing Authority | PJM Interconnection, LLC (PJM) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Baltimore Gas & Electric Co (1167) MD |
Grid Voltage | 15.00 kV |
Energy Storage | No |
Generator CHECK Details Operating December 2021
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 1.5 MW |
Summer Capacity | 1.5 MW |
Winter Capacity | 1.5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Fixed Tilt | Yes |
---|---|
East West Fixed Tilt | No |
DC Net Capacity | 2 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | Yes |
Virtual Net Metering DC Capacity | 1.5 MW |
OER Checkerspot Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#3843 | Griffith | Griffith, IN | 3.0 GWh |
#3844 | Leominster | Leominster, MA | 3.0 GWh |
#3845 | PG Solar, LLC | Mt Olive, NC | 3.0 GWh |
#3846 | Albertsons at Melrose Park | Melrose Park, IL | 3.0 GWh |
#3847 | Hickory Grove #1 | Horseheads, NY | 3.0 GWh |
#3848 | Yellow Mills Rd #1 Community Solar Farm | Farmington, NY | 3.0 GWh |
#3849 | Williamsburg Solar LLC VNEM CSG | Haydenville, MA | 3.0 GWh |
#3850 | Actus Lend Lease DMAFB | Tucson, AZ | 3.0 GWh |
#3851 | Claire Solar Farm | South Burlington, VT | 3.0 GWh |
#3852 | Time Warner Cable - Knowles | Bath, NY | 3.0 GWh |
#3854 | ER Center Road Solar, LLC | Hardwick, VT | 3.0 GWh |
#3855 | Gilead Sciences La Verne Rooftop Solar | La Verne, CA | 3.0 GWh |
#3856 | Chicopee River Solar | Springfield, MA | 3.0 GWh |
#3857 | Vacaville Hospital | Vacaville, CA | 3.0 GWh |
#3858 | Costanza Solar | Westerlo, NY | 3.0 GWh |
#3859 | Hollygrove CSG | Red Creek, NY | 3.0 GWh |
#3860 | Carson Solar I | Colorado Springs, CO | 3.0 GWh |
#3861 | East Chicago | East Chicago, IN | 3.0 GWh |
#3862 | County of San Diego COC Hybrid | San Diego, CA | 3.1 GWh |
#3863 | Oak Leaf Solar XXV LLC (CSG) | Watkins, CO | 3.0 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding OER Checkerspot.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Annapolis Solar Park, LLC | Annapolis, MD | 22.8 GWh | 14.4 mi |
Bluefin Origination 1 | Brandywine, MD | 3.8 GWh | 14.2 mi |
Brandywine Power Facility | Brandywine, MD | 545.5 GWh | 17.7 mi |
Bulldog Solar One, LLC | Bowie, MD | 3.4 GWh | 11.2 mi |
Chalk Point Power | Aquasco, MD | 979.6 GWh | 17.6 mi |
Chalk Point Steam | Aquasco, MD | 1.2 GWh | 17.6 mi |
Chester Woods Point Solar, LLC CSG | Chester, MD | 4.0 GWh | 18.6 mi |
City of Bowie | Mitchellville, MD | 3.8 GWh | 10.4 mi |
FedEx Field Solar Facility | Landover, MD | 3.5 GWh | 17.8 mi |
First Baptist Church of Glenarden | Upper Marlboro, MD | 2.8 GWh | 16.1 mi |
Holly Spring Meadows | District Heights, MD | 656.0 MWh | 19 mi |
Keys Energy Center | Brandywine, MD | 4.8 TWh | 15 mi |
Kirby Road Solar, LLC | Clinton, MD | 2.6 GWh | 18.8 mi |
MD - CS - BGE - PR24 TPE | Mitchellville, MD | 4.1 GWh | 12 mi |
MD - PR97 (CSG) | Bowie, MD | 4.4 GWh | 12.9 mi |
MNCPPC Randall Farm | Upper Marlboro, MD | 2.4 GWh | 12.8 mi |
NRG Chalk Point CT | Aquasco, MD | 704.0 MWh | 17.6 mi |
OER Monarch CSG | Upper Marlboro, MD | 3.4 GWh | 11.6 mi |
OER Patuxent CSG | Lothian, MD | 4.2 GWh | 7 mi |
Upper Marlboro 1 CSG | Upper Marlboro, MD | 2.8 GWh | 12.2 mi |