Newport Solar Project
660 County Road 42, Newport, AR 72112Plant Summary Information
Newport Solar Project is ranked #18 out of 79 power plants in Arkansas in terms of total annual net electricity generation.
Newport Solar Project generated 50.5 GWh during the 3-month period between October 2024 to January 2025.
Plant Name | Newport Solar Project |
---|---|
Utility Name | Newport Solar, LLC |
Location | Jackson County, AR |
Initial Operation Date | October 2023 |
Last Update | Jan 2025 |
Annual Generation | 353.8 GWh |
Annual Consumption | 1.2 M MMBtu |
Ranked #1,668 out of 11,979 Power Plants Nationwide | |
Ranked #136 out of 5,765 Solar Power Plants Nationwide | |
Ranked #18 out of 79 Arkansas Power Plants | |
Ranked #2 out of 33 Arkansas Solar Power Plants | |
Fuel Types | Solar |
Map of Newport Solar Project
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Newport Solar Project.
Monthly Net Generation for Newport Solar Project
Newport Solar Project Details
Summary Information | |
---|---|
Plant Name | Newport Solar Project (66112) |
Plant Address | 660 County Road 42, Newport, AR 72112 |
Utility | Newport Solar, LLC (65276) |
Latitude, Longitude | 35.6689, -91.18711 |
Generation Dates on File | Aug 2023 to Jan 2025 |
Initial Operation Date | October 2023 |
Annual Generation | 353.8 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | NA |
Ash Impoundment | |
Transmission / Distribution Owner | Entergy Arkansas LLC (814) AR |
Grid Voltage | 161.00 kV |
Energy Storage | No |
Generator U1 Details Operating October 2023
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 180 MW |
Summer Capacity | 180 MW |
Winter Capacity | 66 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | October 2023 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 90 |
Tilt Angle | 60 |
DC Net Capacity | 231.7 MW |
Thin Film CDTE | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | Yes |
Virtual Net Metering DC Capacity | 231. MW |
Newport Solar Project Plant Owners
Owner Name | Address | Ownership | |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#126 | Solar Gen 2 Solar Facility | Calipatria, CA | 376.5 GWh |
#127 | Prairie Wolf Solar LLC | Ashmore Township, IL | 375.5 GWh |
#128 | Buckthorn Westex | Ft. Stockton, TX | 375.4 GWh |
#129 | Indiana Crossroads Solar Park | Reynolds, IN | 372.3 GWh |
#130 | RE Roserock | Fort Stockton, TX | 365.9 GWh |
#131 | Calhoun Solar | Battle Creek, MI | 364.4 GWh |
#132 | Blythe Solar III, LLC Hybrid | Blythe, CA | 352.8 GWh |
#133 | Edwards Sanborn E1B | Mojave, CA | 342.6 GWh |
#134 | Camilla Solar Energy Project | Camilla, GA | 359.5 GWh |
#135 | Lund Hill Solar | Bickleton, WA | 359.3 GWh |
#137 | Fifth Standard Solar PV, LLC (Hybrid) | Huron, CA | 328.0 GWh |
#138 | Copper Mountain Solar 2 | Boulder City, NV | 348.7 GWh |
#139 | Arlington Valley Solar Energy II | Arlington, AZ | 348.5 GWh |
#140 | Wright Solar Park | Los Banos, CA | 347.2 GWh |
#141 | Blythe Solar II, LLC | Blythe, CA | 337.5 GWh |
#142 | Imperial Valley Solar, LLC | Calexico, CA | 346.4 GWh |
#143 | Edwards Sanborn E1A | Mojave, CA | 329.9 GWh |
#144 | Skipjack Solar Center | Wayside, VA | 345.1 GWh |
#145 | Aragorn Solar Project | Van Horn, TX | 343.7 GWh |
#146 | BigBeau Solar, LLC | Rosamond, CA | 338.0 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Newport Solar Project.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Big Cypress Solar, LLC | Crawfordsville, AR | 418.1 GWh | 54.3 mi |
Clay County Electrical Cooperative | Corning, AR | 2.3 GWh | 60.1 mi |
Craighead Electric Solar One | Brookland, AR | 2.3 GWh | 38.9 mi |
Dell Power Station | Dell, AR | 4.1 TWh | 66.5 mi |
Farmers Electric Cooperative | Newport, AR | 2.2 GWh | 3.7 mi |
Forrest City- Eldridge Road | Forrest City, AR | 2.1 GWh | 48.6 mi |
Forrest City- Prison Site | Forrest City, AR | 2.1 GWh | 52.3 mi |
Greers Ferry Lake | Heber Springs, AR | 209.7 GWh | 46.5 mi |
Happy Solar 1 | Searcy, AR | 207.7 GWh | 43.7 mi |
Independence Steam Electric Station | Newark, AR | 5.4 TWh | 12.5 mi |
Jonesboro City Water & Light Plant | Jonesboro, AR | 84.7 GWh | 28.7 mi |
Paragould Reciprocating | Paragould, AR | 649.0 MWh | 45.2 mi |
Paragould Solar Farm | Paragould, AR | 3.3 GWh | 46.3 mi |
Paragould Turbine | Paragould, AR | 161.0 MWh | 45.2 mi |
Searcy Solar Hybrid | Searcy, AR | 209.6 GWh | 41.3 mi |
West Memphis Solar, LLC | Crawfordsville, AR | 37.9 GWh | 60.7 mi |
White River Lock and Dam 1 | Batesville, AR | 15.3 GWh | 26 mi |
White River Lock and Dam 2 | Locust Grove, AR | 15.4 GWh | 32.9 mi |
White River Lock and Dam 3 | Marcella, AR | 30.7 GWh | 39.1 mi |
Woodruff County Solar | Augusta, AR | 58.5 GWh | 29.8 mi |