New Bern

7420 Old US 70 West, New Bern, NC 28562

Plant Summary Information

New Bern is ranked #4 out of 18 landfill gas power plants in North Carolina in terms of total annual net electricity generation.

New Bern is comprised of 18 generators and generated 7.2 GWh during the 3-month period between September 2023 to December 2023.

Plant NameNew Bern
Utility NameIndustrial Power Generating Company LLC
LocationCraven County, NC
Initial Operation DateAugust 2007
Last Update Dec 2023
Annual Generation 28.1 GWh
Annual Consumption 329.1 k MMBtu
Ranked #4,621 out of 11,835 Power Plants Nationwide
Ranked #108 out of 299 Landfill Gas Power Plants Nationwide
Ranked #135 out of 862 North Carolina Power Plants
Ranked #4 out of 18 North Carolina Landfill Gas Power Plants
Fuel Types Landfill Gas : 93.8% Distillate Fuel Oil : 6.2%

Map of New Bern

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for New Bern.

Create Your Account Today

Monthly Net Generation for New Bern

New Bern Details

Summary Information
Plant NameNew Bern (56688)
Plant Address7420 Old US 70 West, New Bern, NC 28562
UtilityIndustrial Power Generating Company LLC (55938)
Latitude, Longitude35.1681, -77.2267
Generation Dates on FileAug 2007 to Dec 2023
Initial Operation DateAugust 2007
Annual Generation 28.1 GWh
Fuel Types Landfill Gas : 93.8% Distillate Fuel Oil : 6.2%
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionSERC
Balancing AuthorityDuke Energy Progress East (CPLE)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water SourceWells
Ash Impoundment No
Transmission / Distribution OwnerDuke Energy Progress - (NC) (3046) NC
Grid Voltage 25.00 kV
Energy StorageNo

Generator 1 Details Operating August 2007

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 2007
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 10 Details Operating August 2007

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 2007
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 11 Details Operating August 2007

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 2007
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 12 Details Operating August 2007

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 2007
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 2 Details Operating August 2007

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 2007
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 3 Details Operating August 2007

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 2007
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 4 Details Operating August 2007

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 2007
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 5 Details Operating August 2007

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 2007
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 6 Details Operating August 2007

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 2007
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 7 Details Operating August 2007

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 2007
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 8 Details Operating August 2007

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 2007
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 9 Details Operating August 2007

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 2007
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 13 Details Operating May 2011

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2011
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 14 Details Operating May 2011

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2011
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 15 Details Operating May 2011

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2011
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 16 Details Operating May 2011

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2011
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 17 Details Operating May 2011

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2011
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

Generator 18 Details Operating May 2011

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2011
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas / Distillate Fuel Oil
Startup SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsYes
Cofire FuelsYes
Switch Between Oil And Natural GasNo
Multifuel Details
Cofire Energy SourceDFO / LFG

New Bern Plant Owners

Owner NameAddressGeneratorOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Landfill Gas.

RankPlant NamePlant LocationAnnual Generation
#98Bavarian LFGTEWalton, KY27.9 GWh
#99Sarasota County LFGTE FacilityNokomis, FL27.8 GWh
#100Ameresco Dallas LLCDallas, TX27.8 GWh
#101Riverbend LandfillMcMinnville, OR27.7 GWh
#102Richmond EnergyHenrico, VA27.3 GWh
#103Lennon GeneratingLennon, MI27.3 GWh
#104Brown County LFGTE Power StationGeorgetown, OH27.0 GWh
#105Liberty I & II LFGTEMonticello, IN26.7 GWh
#106Two Pine Landfill Gas RecoveryNorth Little Rock, AR26.5 GWh
#107MM Lopez EnergyLake View Terrace, CA26.4 GWh
#109Oneida HerkimerBoonville, NY26.3 GWh
#110Stanton Energy CenterOrlando, FL4.1 TWh
#111Nanticoke LFGBinghamton, NY26.1 GWh
#112Greene Valley Gas RecoveryNaperville, IL26.1 GWh
#113Apple Campus 2 Fuel CellCupertino, CA25.9 GWh
#114Salem Energy Systems LLCWinston-Salem, NC25.9 GWh
#115Mountain ViewGreencastle, PA27.0 GWh
#116Earthmovers LFGTEElkhart, IN25.5 GWh
#117Iredell County LFG FacilityStatesville, NC25.2 GWh
#118Trail Ridge Landfill Gas RecoveryBaldwin, FL25.2 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding New Bern.

Plant NamePlant LocationAnnual GenerationDistance
Andrew SolarNew Bern, NC9.1 GWh6.6 mi
Bondi SolarKinston, NC9.6 GWh17.8 mi
Buckleberry SolarGrifton, NC96.0 GWh17.8 mi
Craven County Wood Energy LPNew Bern, NC269.2 GWh4.2 mi
Daystar SolarPollocksville, NC9.4 GWh9.3 mi
Grove SolarNew Bern, NC13.2 GWh6.1 mi
Highland Solar Center LLCGrifton, NC7.5 GWh18.6 mi
Hood Farm Solar, LLCTrenton, NC8.8 GWh15.5 mi
International Paper Co. - New Bern MillNew Bern, NC205.1 GWh7 mi
Lang Solar FarmLa Grange, NC9.3 GWh15.7 mi
New Bern FarmErnul, NC8.3 GWh10 mi
Pecan Grove Solar, LLCNew Bern, NC8.4 GWh7.3 mi
Plott Hound SolarNew Bern, NC7.4 GWh7.9 mi
Pollocksville SolarPollocksville, NC9.0 GWh11.8 mi
Porter SolarNew Bern, NC8.3 GWh9.2 mi
Sweet Tea Solar, LLCNew Bern, NC6.2 GWh5.3 mi
Trent River FarmNew Bern, NC8.3 GWh7.8 mi
Trent River Solar, LLCPollocksville, NC143.7 GWh12.3 mi
TWE New Bern Solar Project, LLCNew Bern, NC6.1 GWh5.3 mi
Wyse Fork Solar Farm, LLCDover, NC3.5 GWh15.9 mi