Neptune Energy Center Hybrid
TBD, Boone, CO 81025Plant Summary Information
Neptune Energy Center Hybrid is ranked #14 out of 5,643 solar farms nationwide in terms of total annual net electricity generation.
Neptune Energy Center Hybrid generated 228.4 GWh during the 3-month period between May 2024 to August 2024.
Plant Name | Neptune Energy Center Hybrid |
---|---|
Utility Name | Neptune Energy Center, LLC |
Location | Pueblo County, CO |
Initial Operation Date | June 2023 |
Last Update | Aug 2024 |
Annual Generation | 707.3 GWh |
Annual Consumption | 2.8 M MMBtu |
Ranked #969 out of 11,835 Power Plants Nationwide | |
Ranked #14 out of 5,643 Solar Power Plants Nationwide | |
Ranked #19 out of 267 Colorado Power Plants | |
Ranked #1 out of 142 Colorado Solar Power Plants | |
Fuel Types | Solar |
Map of Neptune Energy Center Hybrid
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Neptune Energy Center Hybrid.
Monthly Net Generation for Neptune Energy Center Hybrid
Neptune Energy Center Hybrid Details
Summary Information | |
---|---|
Plant Name | Neptune Energy Center Hybrid (63731) |
Plant Address | TBD, Boone, CO 81025 |
Utility | Neptune Energy Center, LLC (63427) |
Latitude, Longitude | 38.33026, -104.41416 |
Generation Dates on File | Mar 2023 to Aug 2024 |
Initial Operation Date | June 2023 |
Annual Generation | 707.3 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | Public Service Company of Colorado (PSCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Public Service Co of Colorado (15466) CO |
Grid Voltage | 345.00 kV |
Energy Storage | Yes |
Generator NT125 Details Operating June 2023
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
Nameplate Capacity | 125 MW |
Summer Capacity | 125 MW |
Winter Capacity | 125 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | June 2023 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Electricity used for energy storage |
Time From Cold Shutdown To Full Load | 12H |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 500 |
---|---|
Maximum Charge Rate | 125 MW |
Maximum Discharge Rate | 125 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 33 |
Storage Enclosure Type | CS |
Co Located Renewable Firming | Yes |
System Peak Shaving | Yes |
Excess Wind And Solar Generation | P |
Ac Coupled | Yes |
Direct Support Of Another Unit | No |
Direct Support Plant Id | 63731 |
Direct Support Gen Id | NT325 |
Support T D Asset | No |
Generator NT325 Details Operating June 2023
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 325 MW |
Summer Capacity | 325 MW |
Winter Capacity | 325 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | June 2023 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 52 |
DC Net Capacity | 378.8 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Neptune Energy Center Hybrid Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#4 | Sonoran Solar Energy | Buckeye, AZ | 881.3 GWh |
#5 | Eagle Shadow Mountain Solar Farm | Moapa River Indian Re, NV | 908.6 GWh |
#6 | 2W Permian Solar Project Hybrid | Andrews, TX | 902.8 GWh |
#7 | Roseland Solar Project, LLC | Riesel, TX | 875.9 GWh |
#8 | Solar Star 1 | Rosamond, CA | 868.6 GWh |
#9 | Daggett 3 | Daggett, CA | 842.2 GWh |
#10 | Aktina Solar | El Campo, TX | 844.6 GWh |
#11 | Solana Generating Station | Gila Bend, AZ | 805.4 GWh |
#12 | Juno Solar Project | Lamesa, TX | 795.1 GWh |
#13 | Prospero Solar | Andrews, TX | 746.0 GWh |
#15 | Solar Star 2 | Rosamond, CA | 701.3 GWh |
#16 | IP Radian, LLC | Brookesmith, TX | 687.2 GWh |
#17 | Copper Mountain Solar 5, LLC | Boulder City, NV | 685.2 GWh |
#18 | Slate Hybrid | Stratford, CA | 656.4 GWh |
#19 | Prospero Solar II | Andrews, TX | 675.9 GWh |
#20 | Agua Caliente Solar Project | Dateland, AZ | 674.0 GWh |
#21 | Desert Sunlight 300, LLC | Desert Center, CA | 659.4 GWh |
#22 | Silver State Solar Power South | Primm Valley, NV | 647.5 GWh |
#23 | Texas Solar Nova 1 | Spur, TX | 640.0 GWh |
#24 | Arroyo Solar Energy Storage Hybrid | Pueblo Pintado, NM | 612.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Neptune Energy Center Hybrid.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Bighorn Solar 1 | Pueblo, CO | 600.1 GWh | 13 mi |
Carson Solar I | Colorado Springs, CO | 3.0 GWh | 33.6 mi |
CEC Solar #1117, LLC | Pueblo, CO | 7.2 GWh | 6.7 mi |
Clear Spring Ranch PV Project | Fountain, CO | 20.2 GWh | 24.1 mi |
Comanche (CO) | Pueblo, CO | 5.7 TWh | 12.1 mi |
Comanche Solar | Pueblo, CO | 251.5 GWh | 12 mi |
CSU Pueblo | Pueblo, CO | 1.1 GWh | 9.1 mi |
CSWIND America Inc. | Pueblo, CO | 5.9 GWh | 15.7 mi |
Fountain Valley Power Facility | Fountain, CO | 70.3 GWh | 21.5 mi |
Front Range Power Plant | Fountain, CO | 2.2 TWh | 26 mi |
James W. Broderick Hydropower Plant | Pueblo, CO | 20.8 GWh | 17.1 mi |
Palmer Solar | Fountain, CO | 144.1 GWh | 24.4 mi |
Pike Solar Hybrid | Fountain, CO | 307.9 GWh | 22.1 mi |
Pikes Peak Solar Garden 1 LLC CSG | Colorado Springs, CO | 10.0 GWh | 35.5 mi |
Pueblo Airport Generating Station | Pueblo, CO | 1.6 TWh | 6.1 mi |
Ray D Nixon | Fountain, CO | 928.6 GWh | 26.2 mi |
Sun Mountain Solar 1 | Unincorporated Pueblo, CO | 475.5 GWh | 11.8 mi |
Thunder Wolf Energy Center Hybrid | Avondale, CO | 567.6 GWh | 9.7 mi |
USS Giveback Solar LLC (CSG) | Pueblo, CO | 60.0 MWh | 15.6 mi |
Vestas Towers America, Inc. | Pueblo, CO | 2.4 GWh | 15.6 mi |