Neosho Ridge Wind Energy Center
9084 70th Road Galesburg, Galesburg, KS 66740Plant Summary Information
Neosho Ridge Wind Energy Center is ranked #26 out of 1,343 wind farms nationwide in terms of total annual net electricity generation.
Neosho Ridge Wind Energy Center generated 276.0 GWh during the 3-month period between May 2024 to August 2024.
Plant Name | Neosho Ridge Wind Energy Center |
---|---|
Utility Name | Empire District Electric Co |
Location | Neosho County, KS |
Initial Operation Date | May 2021 |
Last Update | Aug 2024 |
Annual Generation | 1.2 TWh |
Annual Consumption | 4.5 M MMBtu |
Ranked #640 out of 11,835 Power Plants Nationwide | |
Ranked #26 out of 1,343 Wind Power Plants Nationwide | |
Ranked #7 out of 152 Kansas Power Plants | |
Ranked #2 out of 49 Kansas Wind Power Plants | |
Fuel Types | Wind |
Map of Neosho Ridge Wind Energy Center
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Neosho Ridge Wind Energy Center.
Monthly Net Generation for Neosho Ridge Wind Energy Center
Neosho Ridge Wind Energy Center Details
Summary Information | |
---|---|
Plant Name | Neosho Ridge Wind Energy Center (62481) |
Plant Address | 9084 70th Road Galesburg, Galesburg, KS 66740 |
Utility | Empire District Electric Co (5860) |
Latitude, Longitude | 37.48536, -95.37673 |
Generation Dates on File | May 2021 to Aug 2024 |
Initial Operation Date | May 2021 |
Annual Generation | 1.2 TWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Westar Energy Inc (22500) KS |
Grid Voltage | 345.00 kV |
Energy Storage | No |
Generator NRW1 Details Operating May 2021
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
RTO ISO LMP Node Designation | EDE.NEOSHORDGE |
RTO ISO Location Designation For Reporting Wholesale Sales Data | EDE.NEOSHORDGE |
Nameplate Capacity | 301 MW |
Summer Capacity | 294.4 MW |
Winter Capacity | 294.4 MW |
Minimum Load | 2.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | May 2021 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 139 |
Other Planned Modifications | No |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 139 |
---|---|
Predominant Turbine Manufacturer | Vestas |
Predominant Turbine Model Number | V120-2.0 |
Design Wind Speed | 18 MPH |
Wind Quality Class | 3 - Low Wind |
Turbine Hub Height Feet | 400 |
Neosho Ridge Wind Energy Center Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#16 | Palo Alto Wind Farm | Emmetsburg, IA | 1.5 TWh |
#17 | TB Flats | Medicine Bow, WY | 1.4 TWh |
#18 | Fowler Ridge Wind Farm LLC | Fowler, IN | 1.4 TWh |
#19 | Maverick Creek Wind | Eden, TX | 1.4 TWh |
#20 | Beaver Creek Wind | Ogden, IA | 1.4 TWh |
#21 | North English | Montezuma, IA | 1.3 TWh |
#22 | Clearwater Wind I | Miles City, MT | 1.3 TWh |
#23 | Lacy Creek Wind Energy Center | Sterling City, TX | 1.3 TWh |
#24 | High Lonesome Wind Power, LLC Hybrid | Rankin, TX | 1.3 TWh |
#25 | Inertia Wind Project | Haskell, TX | 1.2 TWh |
#27 | Santa Rita Wind Energy | Big Lake, TX | 1.2 TWh |
#28 | Jordan Creek Wind Farm, LLC | Judyville, IN | 1.2 TWh |
#29 | Iron Star Wind Project | Dodge City, KS | 1.2 TWh |
#30 | Foard City Wind | Crowell, TX | 1.2 TWh |
#31 | Red Cloud Wind LLC | Corona, NM | 1.2 TWh |
#32 | Mesquite Star | Roscoe, TX | 1.2 TWh |
#33 | Ranchero Wind Farm LLC | Iraan, TX | 1.2 TWh |
#34 | Thunderhead Wind Energy LLC | Boone, NE | 1.2 TWh |
#35 | Azure Sky Wind Project, LLC Hybrid | Throckmorton, TX | 1.2 TWh |
#36 | Santa Rita East | Barnhart, TX | 1.1 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Neosho Ridge Wind Energy Center.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Burlington (KS) | Burlington, KS | 117.0 MWh | 53 mi |
Chanute 2 | Chanute, KS | 79.2 GWh | 15.2 mi |
Chanute 3 | Chanute, KS | 694.0 MWh | 11.7 mi |
CML&P Generating Facility No. 2 | Coffeyville, KS | 93.2 GWh | 29.4 mi |
Coffeyville | Coffeyville, KS | 10.9 GWh | 33.6 mi |
East Kansas Agri-Energy, LLC | Garnett, KS | 5.0 GWh | 54.9 mi |
Erie | Erie, KS | 7.0 MWh | 9.5 mi |
Erie Energy Center | Erie, KS | 1.9 GWh | 9.8 mi |
Fredonia | Fredonia, KS | 15.0 MWh | 24.4 mi |
Garnett Municipal | Garnett, KS | 9.0 MWh | 54.7 mi |
Girard | Girard, KS | 185.0 MWh | 29.5 mi |
Iola | Iola, KS | 909.0 MWh | 30.4 mi |
Jayhawk Wind Energy Center | Hepler, KS | 687.0 GWh | 24.3 mi |
North Fork Ridge Wind Energy Center | Mindenmines, MO | 547.2 GWh | 48 mi |
Oak Grove Power Producers | Arcadia, KS | 20.2 GWh | 41.5 mi |
Prairie Queen Wind Farm | Moran, KS | 649.8 GWh | 35.1 mi |
Riverton | Riverton, KS | 1.1 TWh | 46.9 mi |
State Line Combined Cycle | Joplin, MO | 2.7 TWh | 51 mi |
Wolf Creek Generating Station | Burlington, KS | 9.1 TWh | 54.8 mi |
Wolf Creek Generator | Burlington, KS | 106.0 MWh | 57 mi |