NCSU Cates Cogeneration Plant
2815 Cates Avenue, Raleigh, NC 27695Plant Summary Information
NCSU Cates Cogeneration Plant is ranked #16 out of 30 natural gas power plants in North Carolina in terms of total annual net electricity generation.
NCSU Cates Cogeneration Plant is comprised of 2 generators and generated 17.3 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | NCSU Cates Cogeneration Plant |
---|---|
Utility Name | NC State University, Energy Systems |
Location | Wake County, NC |
Initial Operation Date | August 2012 |
Last Update | Dec 2023 |
Annual Generation | 76.4 GWh |
Annual Consumption | 1.3 M MMBtu |
Ranked #3,487 out of 11,852 Power Plants Nationwide | |
Ranked #976 out of 2,254 Natural Gas Power Plants Nationwide | |
Ranked #90 out of 863 North Carolina Power Plants | |
Ranked #16 out of 30 North Carolina Natural Gas Power Plants | |
Fuel Types | Natural Gas : 99.1% Distillate Fuel Oil : 0.9% |
Map of NCSU Cates Cogeneration Plant
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for NCSU Cates Cogeneration Plant.
Monthly Net Generation for NCSU Cates Cogeneration Plant
NCSU Cates Cogeneration Plant Details
Summary Information | |
---|---|
Plant Name | NCSU Cates Cogeneration Plant (61676) |
Plant Address | 2815 Cates Avenue, Raleigh, NC 27695 |
Utility | NC State University, Energy Systems (61292) |
Latitude, Longitude | 35.78403, -78.6747 |
Generation Dates on File | Jan 2017 to Dec 2023 |
Initial Operation Date | August 2012 |
Annual Generation | 76.4 GWh |
Fuel Types | Natural Gas : 99.1% Distillate Fuel Oil : 0.9% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | Yes |
FERC Cogeneration Docket Number | QF11-261-000 |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Duke Energy Progress East (CPLE) |
NAICS Code | Educational Services (611) |
Sector | Commercial CHP (5) |
Water Source | NA |
Ash Impoundment | No |
Transmission / Distribution Owner | Duke Energy Carolinas, LLC (5416) NC |
Grid Voltage | 12.50 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | Other - See pipeline notes. |
Pipeline Notes | Dominion Energy bought out Public Svc Co of North Carolina |
Natural Gas Storage | No |
Generator CTG1 Details Operating August 2012
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
Nameplate Capacity | 5.6 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 4.7 MW |
Winter Capacity | 5.3 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | August 2012 |
Combined Heat & Power | Yes |
---|---|
Sector Name | Commercial CHP (5) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Distillate Fuel Oil / Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Other Planned Modifications | No |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | Yes |
---|---|
Net Summer Capacity With Natural Gas | 4.7 MW |
Net Winter Capacity With Natural Gas | 5.3 MW |
Net Summer Capacity With Oil | 4.7 MW |
Net Winter Capacity With Oil | 5.2 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | No |
Generator CTG2 Details Operating August 2012
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
Nameplate Capacity | 5.6 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 4.7 MW |
Winter Capacity | 5.3 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | August 2012 |
Combined Heat & Power | Yes |
---|---|
Sector Name | Commercial CHP (5) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Distillate Fuel Oil / Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Other Planned Modifications | No |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | Yes |
---|---|
Net Summer Capacity With Natural Gas | 4.7 MW |
Net Winter Capacity With Natural Gas | 5.3 MW |
Net Summer Capacity With Oil | 4.7 MW |
Net Winter Capacity With Oil | 5.2 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | No |
NCSU Cates Cogeneration Plant Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#966 | Cleveland Works | Cleveland, OH | 232.6 GWh |
#967 | DeRidder Mill | DeRidder, LA | 389.0 GWh |
#968 | Chino Mines | Hurley, NM | 77.4 GWh |
#969 | Sowega Power | Baconton, GA | 77.2 GWh |
#970 | Wolf Hills Energy | Bristol, VA | 77.1 GWh |
#971 | Fountain Valley Power Facility | Fountain, CO | 77.0 GWh |
#972 | Cargill Corn Milling Division | Eddyville, IA | 76.3 GWh |
#973 | Camden Plant Holding LLC | Camden, NJ | 76.0 GWh |
#974 | AES Huntington Beach LLC | Huntington Beach, CA | 75.9 GWh |
#975 | Gibson City Energy Center LLC | Gibson City, IL | 75.8 GWh |
#977 | Ford Utilities Center | Albuquerque, NM | 75.7 GWh |
#978 | Hamlet Generating Facility | Hamlet, NC | 76.7 GWh |
#979 | Neil Simpson II | Gillette, WY | 685.7 GWh |
#980 | Gilroy Power Plant | Gilroy, CA | 74.5 GWh |
#981 | Essex | Essex, MO | 74.3 GWh |
#982 | Georgia-Pacific Corp - Nekoosa Mill | Nekoosa, WI | 177.0 GWh |
#983 | WestRock (TX) | Evadale, TX | 406.8 GWh |
#984 | Boise Cascade International Falls | International Falls, MN | 336.6 GWh |
#985 | Corpus Christi | Corpus Christi, TX | 72.9 GWh |
#986 | UMCP CHP Plant | College Park, MD | 75.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding NCSU Cates Cogeneration Plant.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
315 Vinson Road | Clayton, NC | 4.4 GWh | 19.4 mi |
Angier Farm | Angier, NC | 7.1 GWh | 19 mi |
CBC Solar Energy Gen Fac Phase 2 | Garner, NC | 3.2 GWh | 11.3 mi |
Church Road Solar LLC | Angier, NC | 7.1 GWh | 18.2 mi |
Creech Solar 2, LLC | Garner, NC | 9.1 GWh | 5.8 mi |
Durham Solar | Durham, NC | 5.6 GWh | 18.1 mi |
Farrington Farm | Chapel Hill, NC | 1.5 GWh | 19.9 mi |
Fuquay Farm | Middle Creek Township, NC | 8.6 GWh | 15.3 mi |
Harris | New Hill, NC | 7.7 TWh | 18.9 mi |
HCE Johnston I, LLC | Willow Springs, NC | 3.4 GWh | 16.1 mi |
Murdock Solar | Clayton, NC | 6.5 GWh | 12 mi |
NCSU CCUP Cogeneration Plant | Raleigh, NC | 43.7 GWh | 0.6 mi |
Neuse River Solar Farm | Raleigh, NC | 1.5 GWh | 11 mi |
Page Solar | Willow Spring, NC | 2.4 GWh | 17.4 mi |
SAS Solar Farm | Cary, NC | 1.7 GWh | 4.7 mi |
Sunfish Farm | Willow Spring, NC | 8.8 GWh | 16 mi |
Wake County LFG Facility | Apex, NC | 57.9 GWh | 12.6 mi |
Wake RJ3 Solar Energy Storage | Wake Forest, NC | 234.9 MWh | 18.3 mi |
Wendell Solar Farm LLC | Wendell, NC | 8.3 GWh | 18.2 mi |
XPF Solar Field | Durham, NC | 4.3 GWh | 14.2 mi |