Muscogee Public Works
7154 Manor Road, Columbus, GA 31907Plant Summary Information
Muscogee Public Works is ranked #107 out of 139 solar farms in Georgia in terms of total annual net electricity generation.
Muscogee Public Works generated 575.0 MWh during the 3-month period between September 2023 to December 2023.
Plant Name | Muscogee Public Works |
---|---|
Utility Name | Westbound Solar LLC |
Location | Muscogee County, GA |
Initial Operation Date | January 2019 |
Last Update | Dec 2023 |
Annual Generation | 2.9 GWh |
Annual Consumption | 10.5 k MMBtu |
Ranked #9,064 out of 11,852 Power Plants Nationwide | |
Ranked #3,914 out of 5,655 Solar Power Plants Nationwide | |
Ranked #194 out of 239 Georgia Power Plants | |
Ranked #107 out of 139 Georgia Solar Power Plants | |
Fuel Types | Solar |
Map of Muscogee Public Works
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Muscogee Public Works.
Monthly Net Generation for Muscogee Public Works
Muscogee Public Works Details
Summary Information | |
---|---|
Plant Name | Muscogee Public Works (62881) |
Plant Address | 7154 Manor Road, Columbus, GA 31907 |
Utility | Westbound Solar LLC (62715) |
Latitude, Longitude | 32.49375, -84.86133 |
Generation Dates on File | Jan 2019 to Dec 2023 |
Initial Operation Date | January 2019 |
Annual Generation | 2.9 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Southern Company Services, Inc. - Trans (SOCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Georgia Power Co (7140) GA |
Grid Voltage | 12.47 kV |
Energy Storage | No |
Generator MUSPW Details Operating January 2019
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 1.5 MW |
Summer Capacity | 1.5 MW |
Winter Capacity | 1.5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | January 2019 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 10 |
DC Net Capacity | 2.1 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Muscogee Public Works Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#3904 | Mtn. Solar 3 CSG | Brush, CO | 3.0 GWh |
#3905 | Lockheed Martin Solar | Orlando, FL | 3.0 GWh |
#3906 | Hadley 2 Solar, LLC CSG | Hadley, MA | 3.0 GWh |
#3907 | Mattas Farms | Amsterdam, NY | 3.0 GWh |
#3908 | Manheim New Jersey | Bordentown, NJ | 2.9 GWh |
#3909 | Mendota | Mendota, IL | 2.9 GWh |
#3910 | Rockland Solar CSG | Rockland, MA | 2.9 GWh |
#3911 | Minke Solar | Molalla, OR | 2.9 GWh |
#3912 | Lowndes IDA | Valdosta, GA | 2.9 GWh |
#3913 | Sandy River Solar (CSG) | Sandy, OR | 2.9 GWh |
#3915 | CJ Solar I, LLC | Lisbon, NY | 2.9 GWh |
#3916 | Amsterdam North | Amsterdam, NY | 2.9 GWh |
#3917 | Dickinson Solar Array | Buffalo, MN | 2.9 GWh |
#3918 | Spruce - WCMD - Rubble I | Williamsport, MD | 2.9 GWh |
#3919 | Walden NY 1 | Walden, NY | 2.9 GWh |
#3920 | 9150 Hermosa Solar GM | Rancho Cucamonga, CA | 2.9 GWh |
#3921 | Troup RC50 II | Pine Mountain, GA | 2.9 GWh |
#3922 | Beverly | Beverly, MA | 2.9 GWh |
#3923 | Nostrand | Manteno Township, IL | 2.9 GWh |
#3924 | Platteville Solar CSG, LLC | Platteville, CO | 2.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Muscogee Public Works.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Bartletts Ferry | Salem, AL | 397.0 GWh | 17.8 mi |
Butler Solar Farm 20 | Butler, GA | 39.5 GWh | 32.2 mi |
Butler Solar Project 103 | Butler, GA | 208.4 GWh | 34.4 mi |
Fort Benning Solar Facility | Fort Benning, GA | 50.7 GWh | 11.6 mi |
Goat Rock | Smiths, AL | 99.4 GWh | 15 mi |
H Allen Franklin Combined Cycle | Smiths, AL | 12.1 TWh | 15.9 mi |
Harris Shiloh | Shiloh, GA | 4.3 GWh | 23.1 mi |
Mead Coated Board | Mahrt, AL | 757.7 GWh | 24 mi |
Meriwether Jackson | Machester, GA | 5.9 GWh | 29.4 mi |
North Highlands | Columbus, GA | 98.0 GWh | 7.9 mi |
Oliver Dam | Columbus, GA | 134.4 GWh | 8.2 mi |
Richland | Columbus, GA | 1.5 GWh | 30.3 mi |
SR Lumpkin | Lumpkin, GA | 224.8 GWh | 33.3 mi |
Talbot County Energy | Box Springs, GA | 521.8 GWh | 11.9 mi |
Taylor | Mauk, GA | 31.7 GWh | 27.8 mi |
Taylor County Solar | Butler, GA | 206.7 GWh | 33.4 mi |
Troup RC50 | Pine Mountain, GA | 4.6 GWh | 27.8 mi |
Troup RC50 II | Pine Mountain, GA | 2.9 GWh | 28.1 mi |
Walton Discover Power Facility | Smiths, AL | 195.0 MWh | 10.8 mi |