MU Combined Heat and Power Plant
417 South Fifth St, Columbia, MO 65211Plant Summary Information
MU Combined Heat and Power Plant is ranked #30 out of 120 power plants in Missouri in terms of total annual net electricity generation.
MU Combined Heat and Power Plant is comprised of 8 generators and generated 56.1 GWh during the 3-month period between May 2024 to August 2024.
Plant Name | MU Combined Heat and Power Plant |
---|---|
Utility Name | Curators of the University of Missouri |
Location | Boone County, MO |
Initial Operation Date | July 1961 |
Last Update | Aug 2024 |
Annual Generation | 190.5 GWh |
Annual Consumption | 3.9 M MMBtu |
Ranked #2,361 out of 11,835 Power Plants Nationwide | |
Ranked #827 out of 2,253 Natural Gas Power Plants Nationwide | |
Ranked #30 out of 120 Missouri Power Plants | |
Ranked #13 out of 37 Missouri Natural Gas Power Plants | |
Fuel Types | Natural Gas : 72.8% Wood/Wood Waste Solids : 24.3% Bituminous Coal : 2.9% |
Map of MU Combined Heat and Power Plant
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for MU Combined Heat and Power Plant.
Monthly Net Generation for MU Combined Heat and Power Plant
MU Combined Heat and Power Plant Details
Summary Information | |
---|---|
Plant Name | MU Combined Heat and Power Plant (50969) |
Plant Address | 417 South Fifth St, Columbia, MO 65211 |
Utility | Curators of the University of Missouri (34359) |
Latitude, Longitude | 38.9461, -92.3328 |
Generation Dates on File | Jan 2001 to Aug 2024 |
Initial Operation Date | July 1961 |
Annual Generation | 190.5 GWh |
Fuel Types | Natural Gas : 72.8% Wood/Wood Waste Solids : 24.3% Bituminous Coal : 2.9% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | Yes |
FERC Cogeneration Docket Number | 89-281-000 |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
NAICS Code | Educational Services (611) |
Sector | Commercial CHP (5) |
Water Source | Wells |
Ash Impoundment | No |
Transmission / Distribution Owner | City of Columbia - (MO) (4045) MO |
Grid Voltage | 69.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | PANHANDLE EASTERN PIPELINE COMPANY |
Natural Gas Storage | No |
Generator GEN2 Details Operating July 1974
Technology | Natural Gas Steam Turbine |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | CWLD.UMC |
Nameplate Capacity | 12.5 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 12.2 MW |
Winter Capacity | 12.3 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 1974 |
Combined Heat & Power | Yes |
Sector Name | Commercial CHP (5) |
---|---|
Topping Or Bottoming | T |
Energy Source | Natural Gas / Distillate Fuel Oil / Bituminous Coal |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Fluidized Bed Technology | No |
Stoker Technology | Yes |
Subcritical Technology | Yes |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Cofire Energy Source | BIT / NG / DFO / WDS |
---|---|
Switch When Operating | Yes |
Net Summer Capacity With Natural Gas | 12.2 MW |
Net Winter Capacity With Natural Gas | 12.2 MW |
Net Summer Capacity With Oil | 12.2 MW |
Net Winter Capacity With Oil | 12.2 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | Yes |
Air Permit Limits | Yes |
Generator GEN3 Details Operating August 1986
Technology | Natural Gas Steam Turbine |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | CWLD.UMC |
Nameplate Capacity | 19.8 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 19.2 MW |
Winter Capacity | 19.4 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | August 1986 |
Combined Heat & Power | Yes |
Sector Name | Commercial CHP (5) |
---|---|
Topping Or Bottoming | T |
Energy Source | Natural Gas / Distillate Fuel Oil / Bituminous Coal |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Fluidized Bed Technology | No |
Stoker Technology | Yes |
Subcritical Technology | Yes |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Cofire Energy Source | BIT / NG / DFO / WDS |
---|---|
Switch When Operating | Yes |
Net Summer Capacity With Natural Gas | 19.2 MW |
Net Winter Capacity With Natural Gas | 19.2 MW |
Net Summer Capacity With Oil | 19.2 MW |
Net Winter Capacity With Oil | 19.2 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | Yes |
Air Permit Limits | Yes |
Generator GEN4 Details Operating July 1988
Technology | Natural Gas Steam Turbine |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | CWLD.UMC |
Nameplate Capacity | 14.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 13.3 MW |
Winter Capacity | 13.4 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 1988 |
Combined Heat & Power | Yes |
Sector Name | Commercial CHP (5) |
---|---|
Topping Or Bottoming | T |
Energy Source | Natural Gas / Distillate Fuel Oil / Bituminous Coal |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Fluidized Bed Technology | No |
Stoker Technology | Yes |
Subcritical Technology | Yes |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Cofire Energy Source | BIT / NG / DFO / WDS |
---|---|
Switch When Operating | Yes |
Net Summer Capacity With Natural Gas | 13.3 MW |
Net Winter Capacity With Natural Gas | 13.3 MW |
Net Summer Capacity With Oil | 13.3 MW |
Net Winter Capacity With Oil | 13.3 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | Yes |
Air Permit Limits | Yes |
Generator GEN7 Details Standby June 1997
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | CWLD.UMC |
Nameplate Capacity | 1 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1 MW |
Winter Capacity | 1 MW |
Minimum Load | 0.5 MW |
Uprate/Derate Completed | No |
Status | Standby |
---|---|
Synchronized To Transmission Grid | Yes |
First Operation Date | June 1997 |
Combined Heat & Power | No |
Sector Name | Commercial CHP (5) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator DGT1 Details Standby September 2002
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | CWLD.UMC |
Nameplate Capacity | 2 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 2 MW |
Winter Capacity | 2 MW |
Minimum Load | 1 MW |
Uprate/Derate Completed | No |
Status | Standby |
---|---|
Synchronized To Transmission Grid | Yes |
First Operation Date | September 2002 |
Combined Heat & Power | No |
Sector Name | Commercial CHP (5) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator NTG1 Details Operating September 2002
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | CWLD.UMC |
Nameplate Capacity | 17.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 11.4 MW |
Winter Capacity | 14.5 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2002 |
---|---|
Combined Heat & Power | Yes |
Sector Name | Commercial CHP (5) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | Yes |
---|---|
Net Summer Capacity With Natural Gas | 11.4 MW |
Net Winter Capacity With Natural Gas | 14.5 MW |
Net Summer Capacity With Oil | 11.4 MW |
Net Winter Capacity With Oil | 14.5 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Air Permit Limits | Yes |
Generator NTG2 Details Operating September 2002
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | CWLD.UMC |
Nameplate Capacity | 17.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 11.4 MW |
Winter Capacity | 14.5 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2002 |
---|---|
Combined Heat & Power | Yes |
Sector Name | Commercial CHP (5) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | Yes |
---|---|
Net Summer Capacity With Natural Gas | 11.4 MW |
Net Winter Capacity With Natural Gas | 14.5 MW |
Net Summer Capacity With Oil | 11.4 MW |
Net Winter Capacity With Oil | 14.5 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Air Permit Limits | Yes |
Generator 6025 Details Operating December 2017
Technology | Natural Gas Steam Turbine |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | CWLD.UMC |
Nameplate Capacity | 0.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.3 MW |
Winter Capacity | 0.3 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2017 |
Combined Heat & Power | Yes |
Sector Name | Commercial CHP (5) |
---|---|
Topping Or Bottoming | B |
Energy Source | Natural Gas / Wood/Wood Waste Solids / Distillate Fuel Oil / Bituminous Coal |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Stoker Technology | Yes |
Subcritical Technology | Yes |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Cofire Energy Source | BIT / NG / DFO / WDS |
---|---|
Switch When Operating | Yes |
Net Summer Capacity With Natural Gas | 0.3 MW |
Net Winter Capacity With Natural Gas | 0.3 MW |
Net Summer Capacity With Oil | 0.3 MW |
Net Winter Capacity With Oil | 0.3 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | Yes |
Air Permit Limits | Yes |
MU Combined Heat and Power Plant Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#817 | James River Power Station | Springfield, MO | 154.2 GWh |
#818 | International Paper Valliant OK | Valliant, OK | 428.7 GWh |
#819 | Colorado Energy Nations Company | Golden, CO | 144.6 GWh |
#820 | Georgia-Pacific Palatka Operations | Palatka, FL | 320.3 GWh |
#821 | El Segundo Energy Center LLC | El Segundo, CA | 142.7 GWh |
#822 | Marsh Landing Generating Station | Antioch, CA | 141.3 GWh |
#823 | Greenwood (MO) | Greenwood, MO | 150.3 GWh |
#824 | Montpelier Electric Generating Station | Poneto, IN | 141.5 GWh |
#825 | Peno Creek | Bowling Green, MO | 140.5 GWh |
#826 | Spiritwood Station | Spiritwood, ND | 181.6 GWh |
#828 | Wasson CO2 Removal Plant | Denver City, TX | 137.2 GWh |
#829 | Berry Cogen Tanne Hills 18 | Maricopa, CA | 137.2 GWh |
#830 | James H Miller Jr | Quinton, AL | 17.1 TWh |
#831 | Middletown | Middletown, CT | 169.8 GWh |
#832 | Rand Whitney CHP Plant | Montville, CT | 133.5 GWh |
#833 | Handsome Lake Energy LLC | Kennerdell, PA | 132.7 GWh |
#834 | PSEG Kearny Generating Station | Kearny, NJ | 132.3 GWh |
#835 | De Pere Energy Center | De Pere, WI | 144.4 GWh |
#836 | Escanaba Mill | Escanaba, MI | 411.8 GWh |
#837 | Algonquin Windsor Locks | Windsor Locks, CT | 130.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding MU Combined Heat and Power Plant.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Altona Solar, LLC | Centralia, MO | 7.8 GWh | 25.5 mi |
Ameresco Jefferson City | Jefferson City, MO | 22.4 GWh | 31.3 mi |
Audrain Generating Station | Vandalia, MO | 197.1 GWh | 49.5 mi |
Callaway | Fulton, MO | 9.4 TWh | 32.5 mi |
Columbia (MO) | Columbia, MO | 16.6 GWh | 1.5 mi |
Columbia Energy Center | Columbia, MO | 20.1 GWh | 6.3 mi |
Fairgrounds | Jefferson City, MO | 1.5 GWh | 25.1 mi |
Fulton (MO) | Fulton, MO | 206.0 MWh | 21.4 mi |
Marshall (MO) | Marshall, MO | 1.7 GWh | 48.4 mi |
Marshall Solar Farm (MO) | Marshall, MO | 4.2 GWh | 48.2 mi |
Mexico | Mexico, MO | 12.7 MWh | 30.3 mi |
MJMEUC Generating Station #1 | Laddonia, MO | 110.4 GWh | 42.7 mi |
Moberly | Moberly, MO | 30.0 MWh | 34 mi |
Montgomery County Community Solar Center | New Florence, MO | 11.2 GWh | 49 mi |
Moreau | Moreau, MO | 2.1 GWh | 29.7 mi |
Osage Dam | Eldon, MO | 176.1 GWh | 53.6 mi |
Shelbina Power #1 | Shelbina, MO | 7.0 MWh | 53.9 mi |
Shelbina Power #2 | Shelbina, MO | 31.0 MWh | 53.9 mi |
Thomas Hill | Clifton Hill, MO | 6.2 TWh | 45 mi |
Truman Solar | Colombia, MO | 22.7 GWh | 4.9 mi |