Mount Olive Farm
1001 W Main St, Mount Olive, NC 28365Plant Summary Information
Mount Olive Farm is ranked #162 out of 738 solar farms in North Carolina in terms of total annual net electricity generation.
Mount Olive Farm generated 2.6 GWh during the 3-month period between September 2022 to December 2022.
Plant Name | Mount Olive Farm |
---|---|
Utility Name | Strata Manager, LLC |
Location | Wayne County, NC |
Initial Operation Date | December 2014 |
Last Update | Dec 2022 |
Annual Generation | 10.3 GWh |
Annual Consumption | 37.8 k MMBtu |
Ranked #5,812 out of 11,249 Power Plants Nationwide | |
Ranked #1,452 out of 5,158 Solar Power Plants Nationwide | |
Ranked #238 out of 858 North Carolina Power Plants | |
Ranked #162 out of 738 North Carolina Solar Power Plants | |
Fuel Types | Solar |
Previous Operator |
Mount Olive Farm LLC (2013 to 2020) Strata Manager, LLC (2021 to 2022) |
Map of Mount Olive Farm
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Mount Olive Farm.
Monthly Net Generation for Mount Olive Farm
Mount Olive Farm Details
Summary Information | |
---|---|
Plant Name | Mount Olive Farm (59107) |
Plant Address | 1001 W Main St Mount Olive, NC 28365 |
Utility | Strata Manager, LLC (64778) |
Latitude, Longitude | 35.20194, -78.08167 |
Generation Dates on File | Dec 2014 to Dec 2022 |
Initial Operation Date | December 2014 |
Annual Generation | 10.3 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | 13-31 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Duke Energy Progress East (CPLE) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Duke Energy Progress - (NC) (3046) NC |
Grid Voltage | 12.40 kV |
Energy Storage | No |
Generator 1 Details Operating December 2014
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 5 MW |
Summer Capacity | 5 MW |
Winter Capacity | 5 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 2014 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Multiple Fuels | No |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 20 |
DC Net Capacity | 6.8 MW |
Thin Film CDTE | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Mount Olive Farm Plant Owners
Owner Name | Address | Ownership |
---|---|---|
Mount Olive Farm, LLC | 800 Taylor St, Suite 200, Durham, NC 27701 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1442 | Hamlin Solar 1, LLC | Hamlin, NY | 10.3 GWh |
#1443 | Hamilton Solar-Crosswicks | Hamilton, NJ | 10.3 GWh |
#1444 | ZV Solar 1 | Red Springs, NC | 10.3 GWh |
#1445 | Freedom Solar | Nichols, SC | 10.3 GWh |
#1446 | Foxfire Solar Farm | West End, NC | 10.3 GWh |
#1447 | Shelter Solar | Raeford, NC | 10.3 GWh |
#1448 | Sneads Grove | Laurinburg, NC | 10.3 GWh |
#1449 | Bondi Solar | Kinston, NC | 10.3 GWh |
#1450 | Southerland Farm Solar | Henderson, NC | 10.3 GWh |
#1451 | CB Bladen Solar, LLC | Fayetteville, NC | 10.3 GWh |
#1453 | ESA Boston Solar, LLC | Roxboro, NC | 10.3 GWh |
#1454 | Stone Solar | Lumberton, NC | 10.3 GWh |
#1455 | Wakefield Solar | Nebulon, NC | 10.3 GWh |
#1456 | Siler 421 Farm, LLC | Siler City, NC | 10.3 GWh |
#1457 | Pfizer Peapack Solar | Peapack, NJ | 10.2 GWh |
#1458 | West Siler | Siler City, NC | 10.2 GWh |
#1459 | Kendall Farm | Liberty, NC | 10.2 GWh |
#1460 | Roper Farm, LLC | Grover, NC | 10.2 GWh |
#1461 | Lillington Solar | Lillington, NC | 10.2 GWh |
#1462 | Clipperton Holdings LLC | Clinton, NC | 10.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Mount Olive Farm.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Belafonte | Calypso, NC | 7.1 GWh | 2.8 mi |
Blueberry One | Grantham, NC | 10.1 GWh | 8.7 mi |
Eros Solar, LLC | Mt Olive, NC | 10.7 GWh | 2.5 mi |
Faison Solar | Faison, NC | 3.1 GWh | 9.3 mi |
Harrell's Hill Solar Center LLC | Mt. Olive, NC | 9.3 GWh | 1.3 mi |
Long Henry Solar | Seven Springs, NC | 4.2 GWh | 10.5 mi |
Mount Olive Solar | Mount Olive, NC | 3.6 GWh | 1.8 mi |
Mt Olive Farm 2 | Mt Olive, NC | 9.9 GWh | 1.3 mi |
Mt Olive Solar 1 | Mt. Olive, NC | 9.4 GWh | 1.7 mi |
Oakwood Solar | Mebane, NC | 10.8 GWh | 6.7 mi |
Overman Solar | Goldsboro, NC | 11.4 GWh | 6.7 mi |
Panda Solar NC 7, LLC | Faison, NC | 2.7 GWh | 8.9 mi |
PG Solar, LLC | Mt Olive, NC | 4.0 GWh | 4.3 mi |
Robin Solar | Dudley, NC | 8.8 GWh | 4.3 mi |
Ruskin Solar | Dudley, NC | 4.2 GWh | 6 mi |
Solar Lee, LLC | Mount Olive, NC | 9.8 GWh | 1.2 mi |
Summit Solar | Mount Olive, NC | 713.0 MWh | 3 mi |
Terreva Wayne County RNG, LLC | Dudley, NC | 9.9 GWh | 6 mi |
Wayne Solar I LLC | Mount Olive, NC | 7.8 GWh | 3.8 mi |
Wayne Solar II LLC | Goldsboro, NC | 8.7 GWh | 7.9 mi |