Mesquite Creek LFGTE Project

1000 Kohlenberg, New Braunfels, TX 78130

Plant Summary Information

Mesquite Creek LFGTE Project is ranked #5 out of 8 landfill gas power plants in Texas in terms of total annual net electricity generation.

Mesquite Creek LFGTE Project is comprised of 2 generators and generated 5.6 GWh during the 3-month period between September 2023 to December 2023.

Plant NameMesquite Creek LFGTE Project
Utility NameWM Renewable Energy LLC
LocationComal County, TX
Initial Operation DateDecember 2010
Last Update Dec 2023
Annual Generation 21.4 GWh
Annual Consumption 256.0 k MMBtu
Ranked #4,994 out of 11,852 Power Plants Nationwide
Ranked #150 out of 299 Landfill Gas Power Plants Nationwide
Ranked #522 out of 754 Texas Power Plants
Ranked #5 out of 8 Texas Landfill Gas Power Plants
Fuel Types Landfill Gas

Map of Mesquite Creek LFGTE Project

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Mesquite Creek LFGTE Project.

Create Your Account Today

Monthly Net Generation for Mesquite Creek LFGTE Project

Mesquite Creek LFGTE Project Details

Summary Information
Plant NameMesquite Creek LFGTE Project (57167)
Plant Address1000 Kohlenberg, New Braunfels, TX 78130
UtilityWM Renewable Energy LLC (54842)
Latitude, Longitude29.7372, -98.0228
Generation Dates on FileDec 2010 to Dec 2023
Initial Operation DateDecember 2010
Annual Generation 21.4 GWh
Fuel Types Landfill Gas
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusYes
FERC Small Power Producer Docket Number11-6-000
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionTRE
Balancing AuthorityElectric Reliability Council of Texas, Inc. (ERCO)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water Source
Ash Impoundment No
Transmission / Distribution OwnerCity of New Braunfels - (TX) (13418) TX
Grid Voltage 13.00 kV
Energy StorageNo

Generator GEN1 Details Operating December 2010

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node DesignationZONAL
RTO ISO Location Designation For Reporting Wholesale Sales DataZONAL
Nameplate Capacity1.6 MW
Nameplate Power Factor0.98
Summer Capacity1.6 MW
Winter Capacity1.6 MW
Minimum Load0.8 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateDecember 2010
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator GEN2 Details Operating December 2010

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node DesignationZONAL
RTO ISO Location Designation For Reporting Wholesale Sales DataZONAL
Nameplate Capacity1.6 MW
Nameplate Power Factor0.98
Summer Capacity1.6 MW
Winter Capacity1.6 MW
Minimum Load0.8 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateDecember 2010
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Mesquite Creek LFGTE Project Plant Owners

Owner NameAddressGeneratorOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Landfill Gas.

RankPlant NamePlant LocationAnnual Generation
#140Chestnut Ridge Gas RecoveryHeiskell, TN22.3 GWh
#141Short MountainEugene, OR22.2 GWh
#142Millersville LFGSevern, MD22.1 GWh
#143Westside Landfill Gas RecoveryAledo, TX22.0 GWh
#144Five Oaks Gas RecoveryTaylorville, IL21.9 GWh
#145Oak Ridge LFGTELogansport, IN21.7 GWh
#146Terry Bundy Generating StationLincoln, NE138.7 GWh
#147Eagle Valley (MI)Orion, MI21.6 GWh
#148Energy Developments, HancockFindlay, OH21.4 GWh
#149Cumberland County Solid Waste ComplexMillville, NJ21.4 GWh
#151Union Renewable Energy FacilityEnoree, SC21.1 GWh
#152Gaston County Renewable Energy CenterDallas, NC21.0 GWh
#153Covel Gardens Gas RecoverySan Antonio, TX20.6 GWh
#154DADS Gas RecoveryAurora, CO20.6 GWh
#155Oak Grove Power ProducersArcadia, KS20.2 GWh
#156Spruce Ridge Gas RecoveryGlencoe, MN20.2 GWh
#157Greater New Bedford LFG Utiliz. FacilityNew Bedford, MA19.9 GWh
#158BMW Manufacturing CoGreer, SC31.7 GWh
#159Waste Management Crossroads LFGTENorridgewock, ME19.5 GWh
#160GenevaGeneva, OH19.5 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Mesquite Creek LFGTE Project.

Plant NamePlant LocationAnnual GenerationDistance
Abbott TP 3McQueeney, TX5.5 GWh10 mi
Blue Wing Solar Energy GenerationSan Antonio, TX17.8 GWh37.6 mi
CanyonCanyon Lake, TX1.0 MWh13.8 mi
CPS 1 Community SolarAdkins, TX1.8 GWh28.9 mi
Dunlap TP 1New Brannfels, TX698.0 MWh6.8 mi
FELPS 1 - CalaverasFloresville, TX2.1 GWh38.3 mi
FELPS 2 - CalaverasFloresville, TX2.1 GWh38.2 mi
Guadalupe Generating StationMarion, TX7.1 TWh10.6 mi
Hays Energy ProjectSan Marcos, TX5.3 TWh3.6 mi
HEB_CPSSADCSan Antonio, TX1.2 GWh30 mi
IKEA Live Oak Rooftop PV SystemLive Oak, TX2.1 GWh22.4 mi
J K SpruceSan Antonio, TX6.1 TWh34.5 mi
Niagara Bottling - SeguinSeguin, TX8.1 GWh10.6 mi
NolteSeguin, TX2.4 GWh14.8 mi
O W SommersSan Antonio, TX1.9 TWh34.7 mi
OCI Alamo 2, LLCConverse, TX9.5 GWh26.2 mi
OCI Alamo 3 LLCSan Antonio, TX10.3 GWh24.3 mi
OCI Alamo 4, LLCBrackettville, TX78.9 GWh24.3 mi
Rio Nogales Power ProjectSeguin, TX5.0 TWh10.4 mi
V H BraunigElmendorf, TX1.6 TWh39.6 mi