Malden
405 South Beckwith, Malden, MO 63863Plant Summary Information
Malden is ranked #25 out of 47 distillate fuel oil power plants in Missouri in terms of total annual net electricity generation.
Malden is comprised of 7 generators and generated 14.5 MWh during the 3-month period between September 2023 to December 2023.
Plant Name | Malden |
---|---|
Utility Name | City of Malden - (MO) |
Location | Dunklin County, MO |
Initial Operation Date | August 1957 |
Last Update | Dec 2023 |
Annual Generation | 75.0 MWh |
Annual Consumption | 968 MMBtu |
Ranked #11,486 out of 11,852 Power Plants Nationwide | |
Ranked #809 out of 1,262 Distillate Fuel Oil Power Plants Nationwide | |
Ranked #103 out of 120 Missouri Power Plants | |
Ranked #25 out of 47 Missouri Distillate Fuel Oil Power Plants | |
Fuel Types | Distillate Fuel Oil |
Map of Malden
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Malden.
Monthly Net Generation for Malden
Malden Details
Summary Information | |
---|---|
Plant Name | Malden (2142) |
Plant Address | 405 South Beckwith, Malden, MO 63863 |
Utility | City of Malden - (MO) (11540) |
Latitude, Longitude | 36.5531, -89.9682 |
Generation Dates on File | Jan 2001 to Dec 2023 |
Initial Operation Date | August 1957 |
Annual Generation | 75.0 MWh |
Fuel Types | Distillate Fuel Oil |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Municipality |
Ash Impoundment | No |
Transmission / Distribution Owner | Southwestern Power Administration (17716) |
Grid Voltage | 69.00 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | LIBERTY ENERGY DBA LIBERTY UTILITIES |
Natural Gas Storage | No |
Generator 5 Details Standby August 1957
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 1.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.2 MW |
Winter Capacity | 1.2 MW |
Minimum Load | 0.7 MW |
Uprate/Derate Completed | No |
Status | Standby |
Synchronized To Transmission Grid | Yes |
First Operation Date | August 1957 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil / Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 6 Details Standby August 1963
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 2 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.8 MW |
Winter Capacity | 1.8 MW |
Minimum Load | 0.7 MW |
Uprate/Derate Completed | No |
Status | Standby |
Synchronized To Transmission Grid | Yes |
First Operation Date | August 1963 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil / Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 7 Details Standby August 1973
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 2.8 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 2.5 MW |
Winter Capacity | 2.5 MW |
Minimum Load | 1 MW |
Uprate/Derate Completed | No |
Status | Standby |
Synchronized To Transmission Grid | Yes |
First Operation Date | August 1973 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil / Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 8 Details Standby August 1973
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 4.3 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 3.8 MW |
Winter Capacity | 3.8 MW |
Minimum Load | 1.5 MW |
Uprate/Derate Completed | No |
Status | Standby |
Synchronized To Transmission Grid | Yes |
First Operation Date | August 1973 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil / Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 2A Details Standby February 1996
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 1.8 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.8 MW |
Winter Capacity | 1.8 MW |
Minimum Load | 0.3 MW |
Uprate/Derate Completed | No |
Status | Standby |
Synchronized To Transmission Grid | Yes |
First Operation Date | February 1996 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 3A Details Standby February 1996
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 1.8 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.8 MW |
Winter Capacity | 1.8 MW |
Minimum Load | 0.3 MW |
Uprate/Derate Completed | No |
Status | Standby |
Synchronized To Transmission Grid | Yes |
First Operation Date | February 1996 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 4A Details Standby February 1996
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 1.8 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.8 MW |
Winter Capacity | 1.8 MW |
Minimum Load | 0.3 MW |
Uprate/Derate Completed | No |
Status | Standby |
Synchronized To Transmission Grid | Yes |
First Operation Date | February 1996 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Malden Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Distillate Fuel Oil.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#799 | Broken Bow | Broken Bow, NE | 82.0 MWh |
#800 | Wilkins Station | Marblehead, MA | 78.0 MWh |
#801 | Shenandoah | Shenandoah, IA | 78.0 MWh |
#802 | Litchfield | Litchfield, MN | 185.0 MWh |
#803 | CNN Center | Atlanta, GA | 77.0 MWh |
#804 | Johnson County | Cleburne, TX | 1.1 TWh |
#805 | Alliant SBD0201 Ingredion | Cedar Rapids, IA | 76.4 MWh |
#806 | Lake Preston | Lake Preston, SD | 76.0 MWh |
#807 | WAL202 | Frisco, TX | 76.0 MWh |
#808 | Holton | City of Holton, KS | 1.0 GWh |
#810 | Woodville RTO BTM | Woodville, OH | 75.0 MWh |
#811 | Ephrata PA BTM | Lancaster, PA | 75.0 MWh |
#812 | Midulla Generating Station | Bowling Green, FL | 2.1 TWh |
#813 | BYUI Central Energy Facility | Rexburg, ID | 39.4 GWh |
#814 | Algonquin Windsor Locks | Windsor Locks, CT | 128.9 GWh |
#815 | IMEA Flora | Flora, IL | 73.0 MWh |
#816 | Southwark | Philadelphia, PA | 73.0 MWh |
#817 | St Marys | St. Marys, OH | 73.0 MWh |
#818 | Vitro Architectural Glass (PA) | Carlisle, PA | 72.5 MWh |
#819 | West Group Data Center | Eagan, MN | 72.0 MWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Malden.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Cape Girardeau Renewable Energy Center | Cape Girardeau, MO | 1.8 GWh | 58.3 mi |
Clay County Electrical Cooperative | Corning, AR | 2.3 GWh | 38.6 mi |
Craighead Electric Solar One | Brookland, AR | 2.3 GWh | 54.9 mi |
Crooked Lake Solar, LLC | Blytheville, AR | 189.6 GWh | 45.3 mi |
Dell Power Station | Dell, AR | 4.1 TWh | 47.9 mi |
Essex | Essex, MO | 74.3 GWh | 22.9 mi |
Fredericktown Energy Center | Fredericktown, MO | 8.1 GWh | 73 mi |
Jackson (MO) | Jackson, MO | 137.0 MWh | 59.9 mi |
Jonesboro City Water & Light Plant | Jonesboro, AR | 84.7 GWh | 64.4 mi |
Kennett | Kennett, MO | 2.5 GWh | 22.5 mi |
Lagoon Creek | Brownsville, TN | 3.4 TWh | 69.6 mi |
New Madrid | New Madrid, MO | 5.3 TWh | 22.7 mi |
OETN1 | Obion, TN | 185.1 GWh | 55.5 mi |
Paragould Reciprocating | Paragould, AR | 649.0 MWh | 47.4 mi |
Paragould Solar Farm | Paragould, AR | 3.3 GWh | 46.5 mi |
Paragould Turbine | Paragould, AR | 161.0 MWh | 47.4 mi |
Plum Point Energy Station | Osceola, AR | 3.0 TWh | 61.4 mi |
Poplar Bluff Generating Station | Poplar Bluff, MO | 579.0 MWh | 27.4 mi |
Sikeston Power Station | Sikeston, MO | 1.5 TWh | 29.6 mi |
St Francis Energy Facility | Campbell, MO | 2.0 TWh | 11.8 mi |