Malaga Power LLC
2611 E North Ave, Fresno, CA 93725Plant Summary Information
Malaga Power LLC is ranked #204 out of 346 natural gas power plants in California in terms of total annual net electricity generation.
Malaga Power LLC is comprised of 2 generators and generated 6.6 GWh during the 3-month period between May 2024 to August 2024.
Plant Name | Malaga Power LLC |
---|---|
Utility Name | CalPeak Power, LLC |
Location | Fresno County, CA |
Initial Operation Date | September 2005 |
Last Update | Aug 2024 |
Annual Generation | 10.5 GWh |
Annual Consumption | 134.8 k MMBtu |
Ranked #5,823 out of 11,835 Power Plants Nationwide | |
Ranked #1,573 out of 2,253 Natural Gas Power Plants Nationwide | |
Ranked #837 out of 1,569 California Power Plants | |
Ranked #204 out of 346 California Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Previous Operators |
Kings River Conservation Dist (2013 to 2014) Calpeak Operating Services, LLC (2015 to 2018) CalPeak Power, LLC (2019 to 2023) |
Map of Malaga Power LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Malaga Power LLC.
Monthly Net Generation for Malaga Power LLC
Malaga Power LLC Details
Summary Information | |
---|---|
Plant Name | Malaga Power LLC (56239) |
Plant Address | 2611 E North Ave, Fresno, CA 93725 |
Utility | CalPeak Power, LLC (59527) |
Latitude, Longitude | 36.68957, -119.73989 |
Generation Dates on File | Sep 2005 to Aug 2024 |
Initial Operation Date | September 2005 |
Annual Generation | 10.5 GWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | EG15-44 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | Municipality |
Ash Impoundment | No |
Transmission / Distribution Owner | Pacific Gas & Electric Co (14328) CA |
Grid Voltage | 115.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | PACIFIC GAS |
Natural Gas Storage | No |
Generator GT-1 Details Operating September 2005
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | MALAGA_1_CTG1 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | MALAGA_1_CTG1 |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 48 MW |
Winter Capacity | 48 MW |
Minimum Load | 46 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2005 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Generator GT-2 Details Operating September 2005
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | MALAGA_1_CTG2 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | MALAGA_1_CTG2 |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 48 MW |
Winter Capacity | 48 MW |
Minimum Load | 46 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2005 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Malaga Power LLC Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
Malaga Power, LLC | 4350 Executive Drive, Suite 320, San Diego, CA 92121 | Generator GT-1 | 100.00% |
Malaga Power, LLC | 4350 Executive Drive, Suite 320, San Diego, CA 92121 | Generator GT-2 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1563 | Foxwoods CoGen | Mashantucket, CT | 10.8 GWh |
#1564 | San Antonio Regional Hospital | Upland, CA | 10.7 GWh |
#1565 | Logan City | Logan, UT | 10.7 GWh |
#1566 | Leaf River Cellulose LLC | New Augusta, MS | 422.9 GWh |
#1567 | OLS Energy Chino | Chino, CA | 10.7 GWh |
#1568 | Sycamore (IA) | Johnston, IA | 10.7 GWh |
#1569 | Santa Rita Jail Hybrid | Dublin, CA | 13.1 GWh |
#1570 | Borger Plant | Borger, TX | 45.6 GWh |
#1571 | Gowanus Gas Turbines Generating | Brooklyn, NY | 11.3 GWh |
#1572 | Holcomb | Holcomb, KS | 1.2 TWh |
#1574 | UB Fuel Cell | Bridgeport, CT | 10.5 GWh |
#1575 | South District Wastewater Treatment Plt | Miami, FL | 21.7 GWh |
#1576 | Wesleyan University Cogen 1 | Middletown, CT | 10.5 GWh |
#1577 | EQX002 Secaucus Rd Fuel Cell | Secaucus, NJ | 10.4 GWh |
#1578 | Kaiser Deer Valley Rd. Fuel Cell | Antioch, CA | 10.4 GWh |
#1579 | Tesoro Mandan Cogeneration Plant | Mandan, ND | 34.1 GWh |
#1580 | Agua Mansa Power Plant | Colton, CA | 10.2 GWh |
#1581 | CCSU Fuel Cell Project | New Britain, CT | 10.2 GWh |
#1582 | Goal Line LP | Escondido, CA | 10.2 GWh |
#1583 | Long Beach Generation LLC | Long Beach, CA | 10.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Malaga Power LLC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Algonquin Power Sanger LLC | Sanger, CA | 5.5 GWh | 10.4 mi |
CA - Fresno County - Juvenile Hall | Fresno, CA | 5.4 GWh | 2.1 mi |
Clovis East High School | Clovis, CA | 1.4 GWh | 9.4 mi |
Clovis High School | Clovis, CA | 1.3 GWh | 9.4 mi |
Clovis North High School | Fresno, CA | 1.4 GWh | 13.9 mi |
CSU Fresno Solar Project | Fresno, CA | 1.1 GWh | 8.3 mi |
Fresno Bullard High School Hybrid | Fresno, CA | 2.2 GWh | 9.7 mi |
Fresno Hoover High School Hybrid | Fresno, CA | 2.1 GWh | 9 mi |
Fresno Sunnyside High School Hybrid | Fresno, CA | 2.5 GWh | 3.3 mi |
Kingsburg Cogen | Kingsburg, CA | 4.6 GWh | 13.7 mi |
La Joya Del Sol | Fresno, CA | 89.3 MWh | 3.3 mi |
Moonlight Packing - Phase 2 | Reedley, CA | 2.7 GWh | 16.6 mi |
National Raisin | Fowler, CA | 4.8 GWh | 5.8 mi |
OK Produce Fresno Carport | Fresno, CA | 3.1 GWh | 3 mi |
POM Plant 1 | Del Rey, CA | 2.1 GWh | 8.8 mi |
POM Plant 2 | Del Rey, CA | 292.0 MWh | 8.5 mi |
Rio Bravo Fresno | Fresno, CA | 145.1 GWh | 0.9 mi |
Saint Agnes Medical Center | Fresno, CA | 26.1 GWh | 10.1 mi |
SCCCD - Clovis Community College | Fresno, CA | 2.0 GWh | 13.5 mi |
SCCCD - Fresno Community College | Fresno, CA | 3.8 GWh | 6.2 mi |