Madera 1 PV
20995 Avenue 21, Madera, CA 93638Plant Summary Information
Madera 1 PV is ranked #499 out of 747 solar farms in California in terms of total annual net electricity generation.
Madera 1 PV generated 854.5 MWh during the 3-month period between September 2022 to December 2022.
Plant Name | Madera 1 PV |
---|---|
Utility Name | ZGlobal Inc |
Location | Madera County, CA |
Initial Operation Date | December 2017 |
Last Update | Dec 2022 |
Annual Generation | 3.3 GWh |
Annual Consumption | 12.0 k MMBtu |
Ranked #8,551 out of 11,249 Power Plants Nationwide | |
Ranked #3,506 out of 5,158 Solar Power Plants Nationwide | |
Ranked #1,181 out of 1,501 California Power Plants | |
Ranked #499 out of 747 California Solar Power Plants | |
Fuel Types | Solar |
Map of Madera 1 PV
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Madera 1 PV.
Monthly Net Generation for Madera 1 PV
Madera 1 PV Details
Summary Information | |
---|---|
Plant Name | Madera 1 PV (61421) |
Plant Address | 20995 Avenue 21 Madera, CA 93638 |
Utility | ZGlobal Inc (60059) |
Latitude, Longitude | 37.05647, -120.16702 |
Generation Dates on File | Jan 2018 to Dec 2022 |
Initial Operation Date | December 2017 |
Annual Generation | 3.3 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Pacific Gas & Electric Co (14328) CA |
Grid Voltage | 12.00 kV |
Energy Storage | No |
Generator MDRA1 Details Operating December 2017
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 1.5 MW |
Summer Capacity | 1.5 MW |
Winter Capacity | 1.5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2017 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
DC Net Capacity | 2.1 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Madera 1 PV Plant Owners
Owner Name | Address | Ownership |
---|---|---|
GL Madera, LLC | 604 Sutter Street, Suite 250, Folsom, CA 95630 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#3496 | Hollygrove CSG | Red Creek, NY | 3.3 GWh |
#3497 | Rantoul Solar | Rantoul, IL | 3.3 GWh |
#3498 | Quincy II Solar Garden | Aurora, CO | 3.3 GWh |
#3499 | Bashaw Solar CSG 1, LLC | Newbury, MA | 3.3 GWh |
#3500 | Matrix Buildings A&B (Perth Amboy) Solar | Perth Amboy, NJ | 3.3 GWh |
#3501 | Podunk Road CSG | Enfield, NY | 3.3 GWh |
#3502 | Chester CSG | Chester, NY | 3.3 GWh |
#3503 | Duke Building 87 | Indianapolis, IN | 3.3 GWh |
#3504 | NSE Camber Solar PS11 LLC (CSG) | Sterling, CO | 3.3 GWh |
#3505 | Amazon TUS2 | Tucson, AZ | 3.3 GWh |
#3507 | Greenfield Solar PV | Greenfield, MA | 3.3 GWh |
#3508 | Oak Leaf Solar XXVII LLC | Greely, CO | 3.3 GWh |
#3509 | Tranquillity ID | Tranquillity, CA | 3.3 GWh |
#3510 | CMEEC - Bozrah | Bozrah, CT | 3.3 GWh |
#3511 | Dynamic Madison | Madison, ME | 3.3 GWh |
#3512 | Jackson Legler Solar 1 LLC | Jackson Township, NJ | 3.3 GWh |
#3513 | Wallace | Wallace, NC | 3.3 GWh |
#3514 | Gloucester | Gloucester City, NJ | 3.3 GWh |
#3515 | Blue Shld Of Cal- El Dorado Hlls Mtr B | El Dorado Hills, CA | 3.3 GWh |
#3516 | Solar Photovoltaic Project #07 | Redlands, CA | 3.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Madera 1 PV.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Adera Solar | Chowchilla, CA | 27.5 GWh | 9.8 mi |
Ampersand Chowchilla Biomass LLC | Chowchilla, CA | 58.4 GWh | 5.7 mi |
Borden Solar Farm | Madera, CA | 130.8 GWh | 13.9 mi |
CalRenew-1 | Mendota, CA | 8.7 GWh | 23.4 mi |
Chowchilla II | Chowchilla, CA | 25.9 GWh | 5.7 mi |
City of Madera WWTP | Madera, CA | 1.8 GWh | 8 mi |
DGS Central California Womens Facility | Chowchilla, CA | 4.2 GWh | 2.5 mi |
DGS Valley State Prison | Chowchilla, CA | 4.3 GWh | 3.2 mi |
Diamond H Dairy Power | Chowchilla, CA | 11.4 GWh | 11.7 mi |
El Nido Facility | El Nido, CA | 47.8 GWh | 20 mi |
Five H Farms Solar Array | Merced, CA | 1.5 GWh | 8.2 mi |
Fresno Bullard High School Hybrid | Fresno, CA | 2.3 GWh | 25.6 mi |
Madera Community Hospital | Madera, CA | 1.9 GWh | 10.4 mi |
Merced Solar LLC | Merced, CA | 4.5 GWh | 22.8 mi |
Mission Solar LLC | Merced, CA | 4.5 GWh | 22.7 mi |
Pacific Ethanol Madera Solar Array | Madera, CA | 1.8 GWh | 14.5 mi |
Sealed Air Madera Solar Project | Madera, CA | 2.0 MWh | 9.8 mi |
Site 980 65 | Madera, CA | 715.7 MWh | 14.7 mi |
Wonderful Firebaugh | Firebaugh, CA | 4.8 GWh | 17.4 mi |
Wonderful Orchards - New Columbia | Firebaugh, CA | 11.0 GWh | 18 mi |